FORPARK AUSTRALIA INSTALLATION MANUAL
FREESTANDING TIMBER
INSTALLATION MANUAL FREESTANDING TIMBER
10 May 2022 2
PREPARE THE SITE
Prior to any installation you should be familiar with the requirements of AS 4685 (Parts 1-6) – 2021
“Playground equipment – safety requirements and test methods” (particularly relating to fall zone
requirements), AS/NZS 4422:2016 “Playground surfacing – specifications, requirements and test method”
(relating to the type and depth of your soft-fall surfacing), and AS/NZS 4685.0:2017 “Playgrounds and
playground equipment – development, installation, maintenance and operation” (dealing with your site
requirements and ongoing maintenance).–
1. Check that the site is clear of underground power and services before you commencedigging.
2. Measure the site to ensure that it is large enough to allow for the correct fall zones between the
equipment and the outside of the soft-fall surface, and for correct distances between various items
of equipment. If you are unsure of these requirements you should check with your Forpark
representative.
3. For ease of installation, do not put the soft-fall surfacing in until after the equipment has been
installed. Ensure that you allow for the required soft-fall depth when excavating the site. Any
excavation should take place prior to commencing installation of theequipment.
EQUIPMENT REQUIRED FOR INSTALLATION
1. Shovel for digging holes (preferably long handled)
2. If digging in hard ground you may need a 300mm auger and a crow bar
3. Spirit level
4. ‘G’ clamps (for holding items in place prior to bolting)
5. String line
6. ‘Vice-grip’ pliers (for closing ‘S’ hooks)
7. Concrete for footings
8. Machine for lifting if necessary
9. Basic socket set
10. 125mm Grinder (for Swing A Frames)
11. 500mm X 16mm Drill Bit Auger (for Swing A Frames)
12. 38mm Spade Drill Bit (for Swing A Frames)
13. Galv Spray Can
Forpark recommends General Purpose Concrete. This is a concrete with a compressive strength of 20MPa
(at 28 days) or higher.
The concrete used in playground footings should only be mixed and/or worked by a suitably experienced
person following supplier/manufacturer’s instructions.