8. Mixing unit is now ready for piping.
9. Install water supply lines to mixing unit inlets. (Pipe
thread sealant or alternative such as Teon tape is
recommended on piping thread)
10.Attach hose to ¾” NPT outlet of mixing unit. (Pipe thread
sealant or alternative such as Teon tape is recommended
on tting thread)
11. Attach spray nozzle to the other end of the hose.
(Pipe thread sealant or alternative such as Teon tape is
recommended on tting thread)
12.Gradually open cold water globe valve or ball valve to
pressurize mixing station and check for leaks. If there are
visible leaks, immediately turn globe valve or ball valve o,
depressurize mixing unit by spraying nozzle. Disassemble
and reseal leakage points. Once complete, reassemble and
restart procedure to check for leaks. If there are no more
leaks, continue. If there are leaks, repeat procedure.
13.Gradually open hot water globe valve or ball valve to
pressurize mixing station and check for leaks. If there are
visible leaks, immediately turn globe valve or ball valve o,
depressurize mixing unit by spraying nozzle, allow mixing
unit to cool down prior to disassembly, and reseal leakage
points. Once complete, reassemble and restart procedure to
check for leaks. If there are no more leaks, continue. If there
are leaks, repeat procedure.
14.With both globe valves or ball valves fully open, unit is
ready.
Repair Instructions
CAUTION: Check and make sure that hot & cold water
supply globe valves or ball valves are turned o prior to
disassembly. Depressurize mixing unit by spraying nozzle
and allow mixing unit to cool down prior to disassembly. Unit
is now ready for maintenance.
Check Valve Replacement (For Globe Valve Units Only):
1. Remove check valve connection nut.
2. Remove check valve from globe valve.
3. Reverse instructions to install new check valve (CV-
Water-B (Brass) / CV-Water-S (SS)) .
Globe Valve Stem Guide Filling & Poppet:
1. Remove globe valve stem nut using crescent wrench or
box end wrench by turning it counter-clockwise. Once
completely loosened, entire stem will simply fall o along
with globe valve poppet and stem nut gasket. Please
note that globe valve poppet is “free oating” and thus will
simply fall o its guide.
2. Remove hand wheel nut, lock washer, and name plate
from globe valve hand wheel.
3. Gently tap hand wheel outward and then wiggle o by
hand.
4. On globe valve, remove push down cap and push down
sleeve from stem guide and Teon stem guide lling will
be visible.
5. Turn hand wheel stem guide clockwise until it can be
extracted through the inside.
6. Using a pick or equivalent, remove as much packing
material as possible from the inside of the globe valve.
7. Reinsert the hand wheel stem by turning it counter-
clockwise.
8. Insert new Teon lling into stem (GVCP-8).
9. Insert push down nut into stem and begin to tighten.
Please only hand tighten at this moment.
10.Insert new globe valve poppet and gasket on globe valve
stem (GVCP-10).
11. Reverse instructions to reassemble.
12.Once reassembled and reinstalled onto unit, operate
unit as usual, if there is minimal leakage through stem
packing, tighten push down nut slowly until leakage
disappears.
NOTE: Never reuse gaskets. Always use a new gasket when
reassembling the unit to prevent leaks.