Note: Intermediate version only.
Working (soldering) from inside the tender, fit the junction box (23), marker lamps (24x2), grab handle
(0.4mm wire). Fold the ladder (22) as shown and fit to the tender back.
Fit the lamp iron (21). Fix the brake hose (26) to the buffer beam (11), followed by the buffers (25x2).
To assist those building the intermediate version, the support lip for the hungry boards has been left on the tender top (12). As the original
version did not have hungry boards on the tender, file the hungry board support lip off the tender top (12), and fit the rear coal partition
(14A).
Note: Intermediate version only.
Fit the hungry boards (13x2) and rear coal partition (14B).
Fit the toolbox (15), air vent (16), water filler (,17) and jacks (18x1or2) to the tender top (12). Note that when fitting the tender top (12) you
will have to cut out a small section at the rear of the tender top (12) to clear the lamp iron (21). Now fit the tender top (12) to the tender body,
placing the rear section under the ladder uprights (if fitted) before final positioning of the tender top.
At the front of the tender fit the brake handle (28) into the brake stand (27) and fix the assembly into the tender floor (4). Using 0.4mm wire
fit the vertical handrails either side of the tender front.
Fit the fire irons (19x2) now or after coaling. Note that there was no fire iron standard (bracket) on this tender. There are two styles of
builders plates, refer to photographs to choose those applicable to your locomotive.
Locomotive Drawing 2 (Parts 43 - 84)
As mentioned previously all holes shown on the drawings should be drilled prior to assembly.
Clean up the footplate (41) and remove any feed sprues from the centre cutout under the boiler. Use a file to remove 1.Omm from the front of
this cutout as shown on the drawing. Fix the smokebox/boiler (48) to the firebox (47) then fit the completed assembly to the footplate (41),
fixing at the rear, and using the M2 C/S screw (49) at the front.
Note: Intermediate version only.
Many intermediate version locomotives had a modified cab for improved vision. If modelling this cab
style trim the top front corner of each cab side (42) level with the leading edge. Trim the front of the cab roof (46) back 3.5mm to match. We
suggest modellers refer to photographs for this task.
Fold up the cab (42) and fit spectacle plate (45) as shown. Fold and fit the cab under tray (43) to the cab floor (42).
At this stage we recommend fitting the following parts to the cab (some are from drawing 3). Fit the tap handles (92&124) and short handrail
knobs (101x2& 133x2) to make up vertical handrail - Note: these parts are not on the
intermediate version.
Fit the cab step treads (103&135). Fold and fit the side horizontal handrails using 0.4mm wire. Fit the air tank (112) to the rear of the
footplate (41). Fix the cab (42) to the footplate (41) ensuring that the cab is also secured to the firebox (47). Fit the cab floor support (44) into
the cab (42). The cab roof (46) is probably best fitted later, after the cab is detailed.
Note: Intermediate version only.
Drill the buffer beam (50) to fit the front step (72) and handrail post (73). Fix the buffer beam (50) to the
footplate (41) followed by buffers (70x2), dummy coupling (71) and brake hose (77).
Smokebox doors - the kit contains three types, select the style appropriate to your version.
Original: Door (56) fitted with handle (68), lamp iron holder (98), lamp iron (99), shorthand rail knob (100) and two handles (0.4mm wire).
Intermediate A: Door (57) fitted with handle (69), lamp iron holder (98), lamp iron (99), short handrail knob (100) and one handle (0.4mm
wire).
Intermediate B: Door (67) fitted with handle (68), headlight (54), short handrail (100), step tread (67) and two handles (0.4mm wire).
We recommend that the smokebox door be fitted later to allow the securing of some detail parts, eg the pump, from inside the smokebox.
Commence detailing the top and right side of the locomotive, fitting the chimney (53), dome (52), safety valve (51), small whistle (58), safety
valve (59), steam generator -
intermediate version
only (60 - add 0.5mm wire), large whistle (61), globe valve (62), pipe connection (63), oil
boxes - not on
intermediate version
(64x2), clack valve -
intermediate version
move to the front of the boiler (65), superheater relief valve -
not on
intermediate version (66),
lubricators (74x2 - add 0.4mm wire). Fit the pump (78). Continue detailing adding short handrail knob (93),
short bracket (94), medium bracket (95), long bracket (96), short handrail knobs (97x2) and pipe bracket (102).
Page 4