Hilti UNIRAC SolarMount-I User manual

INSTALLATION MANUAL
Pub 110518-1ii, May 2011
© 2011 by Unirac, Inc. All rights reserved.
SolarMount-I™
R
A HILTI GROUP COMPANY
1411 Broadway Boulevard NE
Albuquerque, NM 87102-1545 USA

Unirac Inc. makes no warranty of any kind with regard
to this material, including, but not limited to, the
implied warranties of merchantability and fitness for a
particular purpose.
The information in this document is subject to change
without notice.
Unirac shall not be liable for errors contained herein or
for incidental or consequential damages in connection
with the furnishing, performance, or use of this
material.
This document contains proprietary information that
is protected by copyright. All rights are reserved.
No part of this document may be photocopied,
reproduced, or translated to another language
without the prior written consent of Unirac.
Unirac Inc.
Marketing Department
1411 Broadway Boulevard, NE
Albuquerque, NM 87102-1545
© Unirac Inc., 2011. All rights reserved.
SOLARMOUNT-I™is a trademark of Unirac Inc. in the
United States of America and other countries.
SOLARMOUNT-I™
Thank you for choosing SolarMount-I™.
This quick start guide provides easy step-by-step
installation instructions. For additional information,
please visit us at www.unirac.com.
BEFORE YOU BEGIN
1 Verify that all of the components are included and
consistent with your order.
2 To avoid conflicts, never modify or combine Unirac’s
SolarMount-I™ with components that are not made
for SolarMount-I. Doing so will void any warranty
associated with SolarMount-I.
IMPORTANT!
INTRODUCTION

Beam
1 Flange Connection
(1) 5/16” x 3-1/2” Zinc Plated Lag Bolt
(1) Stainless steel washer
(1) 1 Flange Connector
End Clamp
(1) Stainless steel hex bolt
(1) Stainless steel flange nut
(1) Slider
(1) End Clamp
2 Flange Connection *
Shown without butyl option
(2) #14 X 3” Concealor™ screws
(1) 2 Flange Connector
UGC-2 Grounding
Beam Splice **
Shown without grounding option
(2) Stainless steel hex bolt
(2) Stainless steel flange nut
(1) Beam Splice
Mid Clamp
(1) Stainless steel hex bolt
(1) Stainless steel flange nut
(1) Slider
(1) Mid Clamp
COMPONENTS
ADDITIONAL COMPONENTS
* Butyl (optional with 2 Flange Connection)
** WEEB 9.5 Grounding (optional with Grounding Splice Kit)
SolarMount-I 1.0 Beam = 1.094” Height
144” Length
SolarMount-I 2.5 Beam = 2.5” Height
144” and 192” Lengths

2-Piece Aluminum Standoff
(2) 5/16 x 3-1/2” Zinc Plated Lag Bolt
(1) 1 Flange Connection
(1) 3/8” x 3/4” Hex Head Bolt
(1) 3/8” x 1-3/4” EPDM Washer
PV Quick Mount
(1) 5/16” x 3-1/2” Stainless Steel Lag Bolt
(1) 5/16” Sealing Washer
(1) 5/16” EPDM Washer
(1) 1 Flange Connection
CreoTecc Tile Hook (Top)
(2) 5/16” x 3-1/2” Zinc Plated Lag Bolt
(1) 3/8-16 x 3/4” Hex Head Bolt
(1) 3/8” Hex Head Nut
OPTIONAL ATTACHMENTS

PLANNING YOUR SOLARMOUNT-I™ INSTALLATION
The installation can be laid out with beams parallel to
the rafters or perpendicular to the rafters. Note that
SolarMount-I™ Beams make excellent straight edges
for doing layouts.
Center the installation area over the structural members
as much as possible.
Leave enough room to safely move around the array
during installation. Some building codes require
minimum clearances around such installations, and the
user should be directed to also check ‘The Code’.
The width of the installation area equals the length of
one module.
The length of the installation area is equal to:
• Thetotalwidthofthemodules,
• Plus1inchforeachspacebetweenmodules(for
mid-clamp),
• Plus3inches(1½inchesforeachpairof
end clamps).
To speed installation, mark beam at approximate
proper foot space before clicking connections to beam.
High-profile
mode
Low-profile
mode
Peak
Gutter
Eave
Eave
Flange Attachment
SolarMount-I Rail
Rail Splice
Key
}}
}}
}}
}}
B
B
B
B
A
A
A
A
Dimension A: Attachments on either side of a splice
that is NOT positioned over an attachment must be
within ⅓ the max span for your installation.
Note: There must be a minimum of TWO attachments
on either side of a splice.
Dimension B: Maximum canitlever cannot exceed ⅓
the max span for your installation

Roof
Double-
wall side of
connection
INSTALLING SOLARMOUNT-I™
Step 1: Attach beam to 2 Flange Connection or 1 Flange Connection
NOTE: Always engage the double-wall side before clicking connection into beam.
NOTE: Do not use connection if the engagement features on the connection are bent, damaged, or obstructed by debris.
1 2 3
Beam
NOTE: When installing on pitched roof configurations, locate double-wall section of connection on the downhill side of roof slope.
NOTE: DO NOT re-use flange connections.

Step 2: Attach 2 Flange Connection or 1 Flange Connection to rafter
NOTE: When using 2 Flange Connection w/Butyl Pad, remove liner before installing screws.
2 Flange Connection Option 1FlangeConnectionOption
Lag Bolt
Concealor Screw
Step 3: Install appropriate number of sliders and optional UGC-2 grounding clips
1 2 3
UGC-2
(optional)
Slider
Hex Bolt

NOTEs ON ThErmal ExpaNsiON:
SOLARMOUNT-I is designed to minimize the effects of thermal expansion by allowing the beams to expand and contract independently between con-
nections and attachments. To minimize the effect of thermal expansion, restrict continuous beam lengths to 36 feet or three standard beam lengths.
NOTE ON spliCEs:
Please refer to technical datasheets for recommended distances between splices.
NOTE: Use anti-seize on bolt and tighten nut to 10 foot-pounds.
Step 4A: Install Splices (1) - Use when splicing two beams at a connection.
Splice Bar
NOTE: Tighten nut to 10 foot pounds with anti-seize
Step 4B: Install Splices (2) - Place at least one splice to act as a retaining clip over a flange
connection for every run of beam. This may require field drilling.
Splice as
Retaining Clip
(field drill holes
as required)
Mid-span
Splice
Optional
Grounding Clip

Step 5: Installing Grounding Lugs
Grounding Lug
Step 6: Install modules using top mounting hardware
NOTE: Use anti-seize on bolt and tighten nut to 10 foot-pounds.
Module
End Clamp
Module
Module
Mid Clamp