OUTDOOR CASE INSTALLATION GUIDE
Outdoor Case Installaon Guide
1.
2.
4.
5.
Place the boom piece of the Outdoor Case on secure,
level ground that can support the weight of the baery.
Put the Stack’d Series base into posion on the boom
piece of the case.
Stack the baery modules on the baery base (2-4 module
stack). Add the BMS on top of the modules. The Stack’d
Series baery installaon manual can be found at
homegridenergy.com
3. Drill out holes on the back of the case that correspond to
the right stack height and conduit that you’ve chosen to
use. When drilling holes, make sure to leave room between
the holes for the waterproof conduit aachment.
Secure the back of the case to the base using two bolts at
the boom (make sure the rubber washers are used here).
Make all connecons through the conduit (finish baery
install).
Pass the Wi-Fi antenna through the included compression
fing at the top of the case.
OPTIONAL: Place bolts through the boom holes to
secure the enre stack to ground.