Land requirements
Total power cord line adopt three-phase five-wire system. Voltage above 350V into line GB
copper cable specifications selection shall not be less than 10 ㎡, the voltage 350V below line
GB copper cable specifications selection shall not be less than 16 ㎡. National standard
aluminum line with specification not less than 25 ㎡.
The distance between machine and devices room less than 15 meters.
Recommend water tank capacity more than 2 ton, the distance between water pump and water
tank less than 3 meters, water tank location should above water pump or in same level.
The devices room should be kept dry, the main control box and touch screen box can not be
placed in a humid environment.
Air compressor parameters (cylinder capacity> 85L, nominal volume flow> 0.36m³/ min)
The floor where install the six columns must have concrete embedded, length and width not less
than 40cmX40CM, height not less than 30cm