briquette without letting any air leakage.Side section and backside of the boiler Concrete step must be done in appropriate dimensions to the place where landing
are being built with brick and briquette as seen the figure to make ash space. boiler and the boiler must be placed there.
The place where the furnace and reverse chamber is attached (fig 1) ,must be built A hole which the barrel of the burner can enter in ,is drilling on the door of coal
by fire bricks.It is height must be as much as explotion doors height. Appropriate parts of assemblying are done on the connecting flange of the burner.
If the boiler will be used with solid fuel or gas fuel ,concrete step must be boiler and the boiler must be placed there.
spilled as we make scotch type boiler to the place where the boiler wll land and
the boiler must be setted on this concrete step.A hole which the barrel of burner Burner must be fitted up by these parts.
can enter in ,is drilling on the door of coal inlet.Appropriate parts of assemblying
are done on the connecting flange of the burner. CHMNEY CONNECTION
CONNECTION OF SCOTCH TYPE OF STEAM BOILER Boiler must be connected chimney by connecting parts which have the same
dimensions of stack connection of the boiler.
The distance between chimney and the boiler must be less than 3m.If it is possible
If you have to use elbow ,you cant use more than two elbows .
Becareful about sharp turning because tar can be formed n the chimney by
by chimney fumes pipe.Too long chimney connection pipes in horizantal section
cause poor draft of chimney because of quick cooling .Chimney draft is very
is important for the burning quality .The diameter of chimney must be in appropriate
dimensions for your boiler.
ASSEMBLNG ACCESSORIES OF STEAM BOLER
All accessories must have the specifications and quantities as inidicated in norms and standards
Fig 4 : Connection of scotch type steam boiler
Fitting up steam boiler and chimney connecting must be done by qualified service.
Attaching safety and control nstruments connectings existed nstallition.
Similiar services are made by recommended company by qualified service.
The height of the boiler 2m higher than the boiler height.
1 m distance must be between boilers and at least 1 m distance from side wall
of the boiler There must be at least two doors facing each other .one of them
must have ventilation to let to the boiler room.
These doors must be 2 m height and 0.6 m width.These doors must be divided The failures caused by the accessories provided by the customer is not at our responsibility and
from other places.The boiler room must be ventilated.Pressure decrase can be max. guarantee conditions do not apply.
0.5 mbar in the boiler room. Fig. 5 : Accessories Of Steam Boiler
9 10