STANDBY BATTERY RACKS
ASSEMBLY INSTRUCTIONS
Applies to All rdb series pAcks
(reAd All instructions prior to instAllAtion)
Standard and Earthquake-Protected (EP) Racks:
Earthquake-protected racks are similar to standard racks, with
the exception of additional frame bracing, battery constraints and
spacer elements. Frames are the same for both Standard and EP
series. EP racks are certified to Section 1630 of the Uniform Building
Code, 1994 edition. See Figure 1.
Configuration:
Racks are available in single or multiple tier/step arrangements as
shown in Figure 2. Rack components are supplied loose and must
be assembled and secured on-site in accordance with these C&D
assembly instructions, the drawings included with the rack shipment,
and applicable codes.
Rack Location:
Locate racks in a clean, cool, dry place so the batteries are not affected
by sources of radiant heat, such as sunshine, heating units, radiators,
steam pipes, etc. Variations of more than 5 degrees F between cells
may cause the battery to become electrically unbalanced. Top rows of
batteries in multiple-tier configurations tend to operate at slightly higher
temperature than those on lower tiers. Always provide adequate
ceiling clearance for ventilation and maintenance.
Anchoring:
To provide stability, safety, and seismic integrity (for EP series),
racks must be securely anchored to the floor. Anchor bolts are to
be installed per contractor specifications and in accordance with
applicable codes. Do not attach rack to walls without consulting
C&D first. Mounting holes are provided in the base of each frame.
All frames must be secured to floor using all anchor bolt locations.
It is the responsibility of the customer to secure racks in accordance
with allowable floor loading, applicable codes and regulations.
• Donotinstallbatteriesuntiltherackhasbeenproperly
installed, with all bolts tightened to specified torque and
frames anchored to the floor.
• Donotuseoilorgreaseasalubricantforcellinstallation.
Lubrication is usually not required due to the low friction
interface of the insulating covers. If necessary, a small
amount of water or unscented talcum can be applied to
the rail covers to reduce friction.
CAUTION:
Grounding:
Rack grounding provisions are integrated into the base of each
frame. Two through holes are located at the center of the frame’s
bottom cross member and may be used to secure a standard NEMA
lug. These holes are 0.44” in diameter and 1.0” between centers.
The surfaces surrounding the holes have been masked and are free
of powder coat to allow electrical contact. Frame to frame grounding
integrity is accomplished via the lower support rail, attached to each
frame with Internal/External “star” washers.
Two Tier Standard Rack Two Tier EP Rack
Figure 1. Standard Vs. EP Rack
2-Step 1 Tier 2 Tier 3 Tier
Figure 2. Typical Rack Configurations
RS-937
These instructions detail the proper procedure for installing C&D
Standard and EP (Earthquake Protected) battery racks. The following
describes how to locate, assemble, and load open-frame battery
racks for C&D battery mounting applications. Proper attention to
these instructions will help ensure safe, trouble-free performance.
Assembly InstructIons for
stAndArd And eP rAcks
1Material Verification: Battery racks are shipped
unassembled with a complete set of related drawings and
documentation. Check received parts and quantities against
the rack’s bill of materials on provided drawings and/or
packing list. Do not assemble rack if parts are missing or
quantities are incomplete.
2Required Tools: Torque wrench (0 to 65 ft.-lb.) with 9/16”
and 3/4” Hex socket. Adjustable wrench or 9/16” and 3/4” box
wrenches, tape measure, square and leveling device.
Note: Consult manufacturer’s instructions for tools required to
install floor mounting hardware.
3Location of Rack Assembly: When determining rack
location and floor bolt pattern, use applicable drawings
provided with rack shipment. Locate the rack’s general position,
considering boundary and aisle clearances. Locate floor
mounting locations using provided drawings. See Figure 3.
Note: Floor mounting hardware is to be determined in
accordance with applicable building codes, not by C&D.
4Initial Assembly: Place frames over installed floor
mounting hardware, finger tight. (Hardware not supplied by
C&D). All frames must face the same direction. Install back
cross braces, finger tight. See Figure 4. Do not install front
cross braces at this time (if required).
Note: Cross bracing pattern along the length of the rack
may not necessarily be symmetric. Cross bracing pattern
and location(front, middle, or back) is detailed on assembly
drawing provided with the racks.
Figure 3. Rack Assembly Location
and Anchor Bolt Pattern
External Rack Dimensions.
See Assembly Drawing.
36” Typical Aisle
Clearance
2” Typical Clearance Around
Existing Boundary
Detail 1. Brace to Frame
connection (Reverse View)
1/2-13 Bolt, Lock
Washer and Nut
Cross Brace
Frame Upright
Figure 4. Initial Assembly
Frame and Cross
Brace Connection.
See Detail 1.
Floor Mounting
Hardware
Frame
Cross Brace(s)
5Installing Support Rail(s): Place support rail(s) in
location using supplied 3/8” bolt, washer, serrated strut nut,
finger tight. Align support rails with “A” dimension from rack
assembly drawing. Install rail covers. See figure 5.
Note: An internal/external “star” washer is used in place of
lock washer on bottom tier or step, for grounding connection.
Optional third rail should be installed at this time (L-Series only).
Assembly InstructIons for
stAndArd And eP rAcks (contInued)
At this point, you have installed a C&D Standard Rack, please proceed to step 8 for cell installation or if you have
an EP Rack, continue on in this procedure.
Rail to Frame
Connection.
See Detail 2.
Support Rail
and Cover
Figure 5. Support Rail Installation
6Leveling: Check that the rack is level and square. Torque
down all bolts. First torque the cross brace bolts to 55-65 ft.-lb.,
then torque the rail to frame bolts to 15-20 ft.-lbs. Torque anchor
bolts to manufacturer’s recommended value.
Detail 2. Frame and Support Rail Connection
3/8-16 Hex Bolt,
Washer (Lock or star)
and Serrated Nut
Support Rail
and Cover
Frame
AdditionAl Assembly instructions
for eArthquAke Protected (eP) rAcks
7EP Rack Assembly (Continued): Install all back
restraint rail(s) and cover(s). See Figure 6. If installing a
rack to hold either a JC or XTJ battery system, the provided
spacer block must be installed between the restraint rails and
the frame. See Detail 3. Position front restraint rail and cover
temporarily next to front support rail prior to installing cells. DJ
Series battery racks to utilize lower set of restraint rail holes to
avoid interference with the handles.
8Cell Installation Procedure: If not instructed otherwise,
install cells starting at the center of the bottom row and,
working out to each end, leave a half inch space between
cells. For EP racks, use spacers between cells as supplied.
Do not use oil or grease as lubricants. Instead a small
amount of water or unscented talcum may be applied to the
rail cover to help reduce friction. For rows having an odd
number of batteries, the center of the first battery installed
will match the center of the row. For rows having an even
number of batteries, a cell space will coincide with the center
of the row. Pay attention to polarities and terminal placement.
Refer to the battery’s Installation and Operating Instruction
manual for more details. All cells should be pushed back
against back restraint rail and cover. Up to 1/8” gap between
restraint rail and cells is acceptable. Repeat this procedure
for remaining steps and tiers, working upward. See Figure 7.
Figure 7a. Cell Spacer Detail (L-Series)
Front Restraint Rail
and Cover (loose)
Figure 7. Cell Installation
Battery Units
Back Restraint
Rail to Frame
Connection.
See Detail 3.
Figure 6. Initial Step For EP Rack
Back Restraint
Rail and Cover
Frame
Detail 3. Frame and Restraint Rail(s)
(Reverse View)
3/8-16 Hex Bolt,
Lock Washer and
Serrated Nut
Back Restraint
Rail and Cover
1/2” Spacer
Block. Used for
“J” Series Only
Assembly InstructIons for
stAndArd And eP rAcks
9Front Restraint Rail (EP only): With the batteries in
place, slide the front side support rail and cover up from its
resting location to its mounting location, aligning with rear
side restraint rail. Install hardware and torque to 15-20 ft.-lbs.
See Figure 8.
10 Final Assembly: Install corner brackets, end restraint rails,
and covers. Position end restraint rail against end battery unit.
See Detail 4. Note that the corner bracket may be reversed
by 180° if required. Install all front cross braces if indicated by
rack assembly drawing. Torque to 55-65 ft.-lbs. See Figure 9
for final rack assembly.
11 Battery Arrangement: Install inter-cell and inter-
unit connectors and cable assemblies as specified by
battery arrangement. Refer to Battery Installation Manual
(RS-1476) for more detail on battery connection and
initialization change.
Figure 9. Assembled EP Rack,
With Front Cross Braces
Detail 4. End Restraint Rail(s)
and Corner Brackets
3/8-16 Hex Bolt, Lock
Washer and Serrated Nut
Side Restraint
Rail and Cover
End Restraint
Rail and Cover
Corner
Bracket
Figure 8. Installed Front Restraint Rail
Restraint Rails and
Cover (Installed)
Any data, descriptions or specifications presented herein are subject to revision by C&D Technologies, Inc. with-
out notice. While such information is believed to be accurate as indicated herein, C&D Technologies, Inc. makes
no warranty and hereby disclaims all warranties, express or implied, with regard to the accuracy or completeness
of such information. Further, because the product(s) featured herein may be used under conditions beyond its
control, C&D Technologies, Inc. hereby disclaims all warranties, either express or implied, concerning the fitness
or suitability of such product(s) for any particular use or in any specific application or arising from any course of
dealing or usage of trade. The user is solely responsible for determining the suitability of the product(s) featured
herein for user’s intended purpose and in user’s specific application.
Copyright 2007 C&D TECHNOLOGIES, INC. Printed in U.S.A. 12-334 5M/0107/TD/3
1400 Union Meeting Road
P.O. Box 3053 • Blue Bell, PA 19422-0858
(215) 619-2700 • Fax (215) 619-7899 • (800) 543-8630
customersvc@cdtechno.com
www.cdtechno.com
Back to Back Assembly:
Where two rows of racks are required, two rack assemblies may be
installed in parallel front to back.
Frame Location:
Locate back to back frames relative to each other as shown, such
that the rear cross brace attachment holes align for the two adjoining
frames. All braces must be installed, as described previously, except
that a single bolt may be used to connect the front and rear frames
and respective cross braces. Use 3/16” spacers and/or washers to
ll gaps between adjacent frames. See gure 10.
End to End Rack Installation Instructions:
Where a continuous rack string is required, two racks may be
installed adjacent in length.
Frame Location:
End to end rack assemblies are installed as two individual, stand-
alone rack assemblies as shown. When installing standard racks,
the minimum clearance between racks is 0”. When installing EP
racks the two racks must be spaced apart so that the minimum
distance between the ends of the support rails is 5”. See Figure 11.
ADDITIONAL INSTRUCTIONS FOR
MULTI-RACK ARRANGEMENTS
Figure 10. Back to Back Assembly
Front of Rack B
Back of Racks A and BFront of Rack A
Figure 11. End to End Installation
5” Min. Between
End to End EP Racks

Other C&D Technologies Rack & Stand manuals

C&D Technologies RDC Series User manual

C&D Technologies

C&D Technologies RDC Series User manual

C&D Technologies L Series User manual

C&D Technologies

C&D Technologies L Series User manual

Popular Rack & Stand manuals by other brands

Adaptive Technologies Group MM-3RDX-18 installation guide

Adaptive Technologies Group

Adaptive Technologies Group MM-3RDX-18 installation guide

Ergotron MXV manual

Ergotron

Ergotron MXV manual

AVteq RPS-500 S Easy setup guide

AVteq

AVteq RPS-500 S Easy setup guide

Wheelock Cooper DB specification

Wheelock

Wheelock Cooper DB specification

Maximum 057-2330-8 instruction manual

Maximum

Maximum 057-2330-8 instruction manual

Twinhead ADK07 quick start guide

Twinhead

Twinhead ADK07 quick start guide

Proslat Storage Elevator Assembly instructions

Proslat

Proslat Storage Elevator Assembly instructions

Konig & Meyer 21320 INFORMATION FOR USE

Konig & Meyer

Konig & Meyer 21320 INFORMATION FOR USE

Icy Box IB-EW206B-T manual

Icy Box

Icy Box IB-EW206B-T manual

QSC LA108-AF quick start guide

QSC

QSC LA108-AF quick start guide

Vivo STAND-V003T/W instruction manual

Vivo

Vivo STAND-V003T/W instruction manual

Weber BOB ROSS U-BR1000 Assembly instructions

Weber

Weber BOB ROSS U-BR1000 Assembly instructions

Chauvet CH-03 Quick reference guide

Chauvet

Chauvet CH-03 Quick reference guide

Vivanco LARGE FIXED WALL BRACKET - PROGRAMMING quick guide

Vivanco

Vivanco LARGE FIXED WALL BRACKET - PROGRAMMING quick guide

Edbak RMSA1 installation manual

Edbak

Edbak RMSA1 installation manual

Rivers Edge LOCKDOWN Operator's manual

Rivers Edge

Rivers Edge LOCKDOWN Operator's manual

DSPro TS-21906T operating instructions

DSPro

DSPro TS-21906T operating instructions

Premier Mounts LMVSP installation guide

Premier Mounts

Premier Mounts LMVSP installation guide

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.