3
CL-TALO N ®Installation Manual
300
Phase 1
1.1. Clear the installation area of all debris and obstructions.
1.2. Check that the substrate is of an approved mounting surface
for the CL-Talon Cladding Support System.
1.3. Apply a moisture barrier by CL-Talon or an equivalent.
1.4. Align the Base Track to the substrate. Base Track
should be spaced every 16” on the center typically or per
project specication. Base track can be installed vertically or
horizontally.
Important Note: If it is chosen to do the installation horizontally, the Base Track should
be oriented as the bigger lip should be on the top and the smaller lip should be on the
bottom (as shown on right) in order to stabilize the Therme Clip during installation.
• The leveling device is to be placed at the top and bottom of the
Wall Mount Track to ensure that it is plumb.
• With the installation of each Base Track we are leaving
a quarter inch space for expansion and contraction, this
space also allows water penetration when the system
has been installed horizontal.
Phase 2
2.1. Use the Leveling Device to level the Base Track before
securing to the substrate.
2.2. Install the approved fasteners at the top and bottom of the
Base Track to hold in place.
2.3. Install additional approved fasteners as needed or per
project specication.