4. BOILER INSTALLATION MANUAL
The boiler is delivered assembled, with additional accessories attached, which must be
connected to the installation when installing the boiler. Before starting the installation of the
boiler, check that the set is complete and undamaged. The data on the boiler's rating plate
must agree with the data in the boiler's documentation.
☝CAUTION:
All work related to setting the boiler, boiler room equipment, connecting the boiler to the installation
and possible repairs should be entrusted to an installer with appropriate knowledge, qualifications and
experience. Proper performance of the above-mentioned works is essential for the safe operation of the
boiler, correct operation of the boiler and central heating system, and user satisfaction
The boiler installation should be performed in accordance with the assembly manual, and the
installations to which the boiler will be connected should be efficient and made in accordance with the
relevant designs.
It is recommended that the installation of the boiler is entrusted to a qualified installer.
4.1 Boiler transport
The AGRO V2 and AGRO V2S boiler is transported on a wooden pallet and packed with
plastic foil. The boiler should be transported in an upright position in a manner that
protects it against mechanical damage. The boiler must be protected against the harmful
effects of weather conditions.
The boilers must not be stacked during transport and storage. Loading and unloading
should be performed with due care. In order to move the boiler in the warehouse and in its
destination, forklifts must be used. Moving should be done carefully and slowly to prevent
the boiler from tipping over. It is forbidden to hit the boiler, overturn or subject it to violent
shocks. Unpacking the boiler may only be performed at the place of destination,
immediately prior to assembly into the system.
4.2 Place of installation of the boiler
According to NormPN-87 / B-02411 "Built-in solid fuel boiler rooms" and in accordance
with the Regulation of the Minister of Infrastructure of April 12, 2002 (Journal of Laws of
2002 No. 75, item 690) on technical conditions to be met by buildings - boiler for solid fuel
should be installed in a separate room, boiler room (e.g. basement, room on the ground
level or the level of heated rooms - rooms in the latter case only up to 25 kW).
The boiler should be placed on a fireproof base, the dimensions of which must exceed the
boiler base by at least 500 mm on the front side of the boiler and 100 mm on the other
sides.
It should be located in such a way that there is free access to the boiler, which is
necessary for proper operation and cleaning of the boiler. The bearing capacity should be
appropriate to the weight of the boiler together with water. The immediate surroundings of
the boiler, i.e. walls and ceiling of the room, should be made of non-flammable materials.