Display Rotation
If the view is not in the desired orientation, press this sequence on the side of the display
using the volume selection buttons and it will rotate the view ().
Note: Do not perform the button-press sequence at the top of the minute.
EverAlert®Dynamic Display Quick Start Installation Guide
INST-EADD Rev 6
1
2
Pre-Installation
1. Verify with your IT Staff:
• Dynamic Host Conguration Protocol (DHCP) is enabled.
Note: Currently, EverAlert Dynamic Display does not support static IP address conguration.
• Ports 83, 123, and 443 are open.
• Internet Connection via Wi-Fi or Ethernet 10/100Base-T is available.
• Verify SSID, Password & Security Type (if using Wi-Fi)
2. Choose a location that is near an AC power receptacle.
Unpack the box
• Remove the content from the box. Save packing materials in case you need them later.
Check the contents
1. EverAlert Dynamic Display Box
i. Quick Start Guide
ii. EverAlert Dynamic Display
iii. 12vdc Power Supply (if 120VAC version)
iv. Port Cover with screws
v. Desktop Stand with thumb screw
(Note that the 12vdc Power Supply may be
removed if devices were ordered with PoE+ or
Battery Backup Kit.)
2. Mounting Bracket Kit Box
(optional)
A. Four M4 X 6mm screws
B. Two M6 x 37mm screws
C. Two bracket thumb screws
D. Two adjustable display hanging brackets
E. One wall mount bracket
F. One power supply bracket
G. Bracket nuts
H. Two plastic anchors
Conrm Installation and Name New Device
1. On inCloud, click on Devices in the site menu, then click on Dynamic Display in the menu bar at the
top of the page. The New Device will display as shown below in the portal.
2. Click on the New Device name and change the display title to a descriptive name which will allow the
device's location to be easily identied (i.e."English - Room 101"). Click Save on the bottom left.
Display Removal
1. Loosen the bracket thumb screws until
they can clear the wall mount bracket
2. Rotate the display away from the wall at
the bottom until the hanging brackets
are clear of the wall mount bracket.
3. Lift the display up and away from the
wall mount bracket.
Please read this rst!
If you have questions at any time during this process, please call American Time toll free at
800-328-8996.
3
6
7
8
phone: 800-328-8996 online: american-time.com fax: 800-789-1882
mail: 140 3rd St. So.; PO Box 707, Dassel, MN 55325-0707

Assigning an EverAlert Dynamic Display to
the inCloud Portal
There are two simple ways to provision the displays to connect to
the management portal. Option 1 uses a wired LAN ethernet cable
on a DHCP enabled network with internet access. Option 2 uses a
USB key that is created from the management portal and contains
the encrypted Wi-Fi credentials for connecting the device to your
network and Site.
NOTE: If you will be using a Wi-Fi connection for your display and
have not already created a security key on the inCloud Management
Portal, please reference your welcome e-mail for instructions on
generating a security key.
1. Option 1 – Conguration using wired LAN on a DHCP Network All
displays have been precongured to a specic Site using their MAC
address.
a. Make sure the Ethernet cable is plugged into the display
(if using the Dynamic Display PoE Kit, use the Ethernet patch
cable from the PoE Splitter).
b. Go to Step 3.
Position the display in the desired orientation (landscape or
portrait) before beginning the provisioning process. Once the
display is provisioned, it will be locked
into this orientation.
DYNAMIC DISPLAY QUICK START INSTALLATION GUIDE
Assigning an EverAlert Dynamic Display to
the inCloud Portal (continued)
2. Option 2 – Conguration using USB Key
a. Login to https://incloud.american-time.com
b. If you have more than one site established, select the Site on
which the new display(s) will be installed. Note that displays
are assigned to a specic site by American Time and cannot be
installed to a different site.
c. In the side menu, click Admin. In the dropdown, click on EverAlert
Congs, followed by Default Cong.
d. Make sure the desired wireless credentials have been entered.
If they are blank and the intention is to use a Wi-Fi network to
connect, enter them now and click Save Only.
e. Click Create Key. The encrypted le will download to your
computer.
f. Go to the default download location on your computer and copy
the SecurityKey.txt le to a USB ash drive.
Note: If this process has been done before on your computer,
there might be more than one security le in this directory with
a number sufx like SecurityKey(1).txt. Be sure to identify the
correct le and rename it to SecurityKey.txt if it is numbered.
3. Power up the display by plugging into an AC wall receptacle.
(If using the Dynamic Display PoE Kit, connect the DC power cable to
the power jack on the back of the Display; if using Battery Backup,
see kit instructions.)
4. If using wired Ethernet, skip to Step 8.
5. Once the Display has fully loaded, the screen will display the
provisioning screen that says Plug in your Security Key.
6. Insert the USB ash drive with security key into one of the two USB
ports on the bottom of the EverAlert Display. Once the key is read,
the screen will show Security Key Found and update the Wi-Fi
credentials on the display and connect to the Portal.
7. After the device has established an internet connection, it will
connect to inCloud and download any necessary updates.
8. Once updates are complete, the display will load its predened
default clock layout and the display is ready for use.
EverAler t®
emergency communication platform
5
4
Wall Mounting (if applicable)
(Note: If installing Battery Backup Kit, see kit instructions for wall
mount process)
1. Preassemble the wall mount base to the power supply bracket.
a. Lay the power supply bracket (F) on a at surface.
b. Position the bracket base (E) over the studs as illustrated
in gure 1.
c. Using the two nuts (G) supplied, tighten the wall mount base
to the power supply bracket.
2. Attach the adjustable brackets to the EverAlert Display
a. Remove the Display from the styrofoam wrap and lay it face
down on the styrofoam wrap it came in.
b. Determine whether the display will hang in Portrait or
Landscape orientation
Note: Illustration shown below is in Landscape orientation.
If mounting the display in Portrait orientation, the brackets will
need to rotate 90 degrees in either direction from the position
shown in the picture. Orientation will be xed after provisioning.
c. Line up the two adjustable brackets (D) with the four holes on
the back of the display as shown in gure 2. Secure with 4
M4X6mm (A) screws.
d. Adjust the brackets to the desired position and tighten the
bolts down. Brackets can adjust to a maximum of 10 degrees
up or 10 degrees down.
+ –
B
D
A
Figure 2
F
E
G
Figure 1
Mounting (continued)
3. Mounting EverAlert Display to the wall
a. Using the wall mount assembly from Section 4-1,
install two M6 screws (B) directly into a stud or into
provided cement anchors (H). Make sure that the power
supply mount is facing upwards.
b. Insert the power supply into the top slot of the
power supply bracket.
NOTE: If using the Dynamic Display PoE Kit (EAPOEKIT), reference the
included instructions for installation.
c. Take the display and insert the top of the adjustable brackets
onto the top of the wall mount base and pivot display down.
d. Insert and tighten the bracket screws (C) on the bottom of the
bracket until the display is secure.
C