GB Wood Sekita Large User manual

Model Sekita Large
Please retain product label (Attached to your building) for reference with all future contact
Retain Instructions for future reference
1
2
3
Door x2
Before
commencing assembly
make sure you have a
suitable base ready to
erect your building
Door Gable
Plain Gable
5
6
4
Floor
2290x1542mm
x2
7
Length - 3118mm
Width - 2336mm
Height - 2112mm
Roof OSB
1330x1042mm
x6
Window Side x2
This building should be erected by
two people.
For ease of assembly, it is advisable to
pilot drill all screw holes and ensure
all screw heads are countersunk.
Plain Side x2
BEFORE YOU START PLEASE READ INSTRUCTIONS CAREFULLY
- Check the pack and make sure you have all the parts listed.
- When you are ready to start, make sure you have the right tools at hand
(not supplied) including a Phillips screwdriver, Stanley knife, wood saw,
step ladder and drill with 2mm bit.
- Ensure there is plenty of space and a clean dry area for assembly.
x2
Fixing Kit
8
9
10
Center Cover Trim - 95x1566mm x2
Cover Trim - 45x1566mm x4
TIMBER
As with all natural materials, timber can be a ected during various weather
conditions. For the duration of heavy or extended periods of rain, swelling of the
wood panels may occur. Warping of the wood may also occur during excessive
dry spells due to an interior moisture loss. Unfortunately, these processes cannot
be avoided but can be helped. It is suggested that the outdoor building is
sprayed with water during extended periods of warm sunshine and sheltered as
much as possible during rain or snow.
Our buildings are delivered pre-treated with a water based timber treatment
however this only helps to protect during transit of your garden item. To
validate your guarantee and for better protection against weathering it is
ESSENTIAL that you treat the garden building with a wood preserver within 3
months of assembly. This will need to be re-applied annually to ensure longevity
of your building. Care must be taken when constructing the garden building
that it is not touching the ground and is on a suitable base.
2mm Drill bit
17
18
19
20
21
Roof Support
Block x4
Winter = High Moisture = Expansion
Summer = Low Moisture = Contraction
Ridge Bar -1515mm x2
Finial x2
Door Strip - 1050mm
11
12
13
14
Fascia - 1300mm x4
Door Strip - 560mm
Roof Support Bar - 1208mm x4
Roof Eaves - 1042mm x6
BUILDING A BASE
When thinking about where the building and base is going to be constructed: Ensure that there will be access to all sides for maintenance work and
annual treatment.
TYPES OF BASE
- Concrete 75mm laid on top of 75mm hard-core.
- Slabs laid on 50mm of sharp sand.
Ensure the base is level and is built on rm ground, to prevent distortion. Refer to diagrams for the base dimensions, The base should be slightly
smaller than the external measurement of the building, i.e. the cladding should overlap the base, creating a run o for water. It is also recommended
that the oor be at least 25mm above the surrounding ground level to avoid ooding.
Whilst all products manufactured at Walton Garden Buildings Limited are made to the highest standards of Safety and in the case of childrens products
independently tested to EN71 level, Walton Garden Buildings Limited cannot accept responsibility for your safety whilst erecting or using this product.
Styrene
610x485mm x6
Window Strip (External) - 570mm x8
Window Strip (Internal) - 465mm x6
15
16
Ridge Bar
Support block
Qty 2

Nail Bag & Ironmongery
22
L Bracket x2
24
T-Hinge x4
26
Felt
20mm Nails x 38
20mm Screw x6
30mm Black Screw x4
Step 3
Fix the hinge to the door using 30mm
screws ensuring that the screws go
throught to the door framing.
Fix door strips the right hand door
using 3x20mm screws per strip.
1
23
U Channel
25
Turn Button x3
30mm Screw x95
40mm Screw x90
50mm Screw x58
Felt Tacks x130
20
30mm
screw
Assembly
Step 1
Remove transportation blocks
from the bottom of each panel
before beginning assembly. Each
Panel should have two blocks.
20mm
screw
19
24
3
21
6 x 20mm Screws
28 x 30mm Screws
Step 4
For each window side, slide 3
pieces of 610 x 485mm
glazing into groove as shown
in diagram.
Place 3 x Internal window
strip behind the bottom of
glazing and fix using 2x25mm
pins
Place 4 x External window
strip against the glazing and
nail in between the sheet and
into the vertical framing using
3 x 25mm nails per strip.
Repeat this for both
window sides
15
x3
Step 2
Ensure floors are flush to each
other and fix using 8x50mm
screws. Alternate fixing positions
along the length of the floors.
4
14
Ensure protective
film on styrene is
removed before
positioning.
20mm
Nails
36x20mm Nails
50mm
screw
8x 50mm Screws

Step 5
Fix the corners with 2x 50mm
screw as shown in diagram.
Do not secure the building to the
floor until the roof is fitted. Fix
the panels onto the floor using
50mm screws in alignment with
the floor joists
2
6
6
Step 7
ASSEMBLE RIDGE BAR
Position the two parts of the ridge bar within the ‘U’
channel and secure from either side with 3 x 30mm
screws and 4 x 30mm screws from underneath.
Secure an ‘L’ bracket to either end of the ridge bar
using 2 x 30mm screws per bracket.
10
22
23
30mm
screw
10
22
50mm
screw
4
16 x 50mm screws
Place the roof support bar in
between the front and back panels.
Ensure the top corners of the
support bar are ush with each top
point. Secure in place using the L
Bracket on each end with 4x30mm
screws.
Step 6
Fix door gable and Plain sides
using same method shown in
step 5.
Position the panels so there is
equal spacing between the oor
and cladding on all four sides.
2
50mm
screw
1
30mm
screw
22
15 x 30mm screws
5
5
22 x 50mm screws

Step 8
ATTACH SUPPORT BARS
i)Position the rst support
bar to the ridge bar sloping
down to the building side,
x with a 50mm screw. Fix
where the roof sheets meet.
ii)Align the second
support bar with the rst
on the opposite side of
the ridge bar and x with
a 50mm screw put in at an
angle
Do this twice for both
support assemblies
ENSURE SUPPORT BARS
ARE MANUALLY SUP-
PORTED UNTIL FIXED AT
BOTH ENDS
Step 10
12
12
12
Fix a roof eave to each sheet
using 4x30mm screws per
eave.
Position a roof sheet on the
building and x using 40mm
screws.
12
12
50mm
screw
15mm
screw
40mm
screw
7
12
12
i
ii
4 x 50mm screws
15mm
screw
40mm
screw
Step 9
FIX ROOF SUPPORT BLOCK
i) Fix the angled block to
the side panel framing with
2 x 50mm screws. Position
the block at the top of the
framing with the angle
pointing upwards into the
building, aligning the block
centrally along the join
between the side panels
with one screw in each
panel.
i
ii
17
17
16
16
17
17
Continue the process from
above and x the roof sheets to
the building aswell as the roof
joining support.
15mm
screw
RIDGE BAR SUPPORT
BLOCK
Fix roof support
block with
2x50mm screws
Do this twice for
both support
assemblies
50mm
screw
40mm
screw
Use the same process with
both sides of the roof.
24 x 30mm screws
66x 40mm screws
16 x 50mm screws

Step11
Cut felt into 3 sheets and lay onto roof as
shown in diagram ensuring there is a
50mm overhang around the sides.
Fix using felt tacks at 100mm intervals
24
Step 12
Use 3x30mm screws to fix each
cover trim. For center trim use
6x30mm screws, two screws for
each position.
*
9
8
9
24x30mm screws
*Use 6x30mm screws
for center cover trim
Felt
tacks
Step 13
130 x felt tacks
Fix fascias and nials using
40mm screws. Pre drill holes to
avoid splitting. Ensure to trap
the felt between the fascia and
building.
11
11
18
40mm
screw
16x 40mm screws

Step 15
Internal
Fix a support block on the inside of
the left hand door at the top and
bottom door using 2x 40mm screws,
screwing through the cladding into
the blocks. Attach a turn button to
each block using 1x 30mm Black
Screw per turn button.
25
18
It is ESSENTIAL that you apply wood treat-
ment immediately after the building has
been assembled.
External
Attach another turn button using a
30mm black screws through the door
into the framing of the left hand door.
18
25
25
3x30mm Black Screws
4x40mm Screws
18
25
Other GB Wood Garden House manuals
Popular Garden House manuals by other brands

Mercia Garden Products
Mercia Garden Products 01DTSHRAX1006SDFW-V1 General instructions

Palmako
Palmako FRM44-4444FSC installation manual

Mercia Garden Products
Mercia Garden Products 01COR0707-V1 General instructions

Palmako
Palmako FR40-5345 installation manual

OLT
OLT 12x16 SunShed Assembly manual

Décor et Jardin
Décor et Jardin Massif 72650S900 Assembly Notice

Lemeks
Lemeks Palmako FR28-4529 Assembly, installation and maintenance manual

Bear County
Bear County Infinity CI4020 manual

Hornbach
Hornbach EcoStar RAL5014 Instructions For Fitting

ABSCO SHEDS
ABSCO SHEDS J30232GECOK manual

Palmako
Palmako Anna PM70-7942 Operation and maintenance manual

Palmako
Palmako FRJ34-4040 installation manual