1.Test Equipment Required
The following test equipment is required for calibration
and servicing of the Model LTC-905. The suggested
specifications are the minimum necessary for proper calib-
ration of this instrument.
Test Equipment Minimum Spec,
oMultimeter Accuracy <±1^
oOscilloscope lOmV sensitivity
1MHz band width
2. Calibration Procedure
»Calibration should be performed after a30 minute warm-up
period. It should also be confirmed that the unit is
connected to the rated power line voltage.
*All adjustment should be completed in the given order,
because some adjustments interact with others.
*During the adjustment procedure, remove the case only
when necessary and replace immediately after making an
adjustment. This will maintain all circuit at constant
operating temperature.
1) Initial Control Settings
The initial control settings to be used for each check and
adjustment are listed below. Any variations from these
settings sre stated in the applicable procedure.
oPOLARITY
oCURRENT LIMIT
BASE ,GATE
°CURRENT"^ VOLTAGE
COLLECTOR/DRAIN
°SWEEP VOLTAGE
oTRANS. -FET
oSELECTOR
NPN
SIGNAL
0.1mA
10V
TRANS.
A
-2-
LTC-901