Preparingthearea forinstallation
B
(1) Depth from the back of the machine to the hole.
(2) Length from the side of the machine to the hole.
(3) Hole in counter:2'' Diameter
Work out the location of the coee machine on the bar or counter and nd the position.
Drill a 2’’hole using the measurements below as a guide.All the coee machines power
and waste connections feed from the bottom at the centre of the coee machine.These
connections then feed down through the 2’’hole in the bar or counter.
Note: The power connections for the coee machine and grinder must be within 1 metre
behind or beneath the machine.The power point and method of isolation must be easily
accessible at all times.
The water and waste connections for the coee machine must be directly beneath it.
All services, including hole in bar counter, must be in place prior to engineer arriving to install
the coee machine.
Ensure that the surface the coee machine is to be placed on is suciently strong and stable
enough to carry the weight of the coee machine.
Plan view for drilling counter for Coee Machine Area for Grinder
110mm
300mm 450mm
240mm
Note: The appliance must be installed in a location where it can be over seen by trained
personnel and its use and maintenance is restricted to trained personnel.
(1)
(2)
(3)
Note: Remove all packaging before working on / installing the machine and remove plastic
any glue is left on use a solvent like WD40 to remove it – DO NOT use abrasives to remove
1) Remove the top tray of the machine by locating and unscrewing the two M4 screws at
2)
for quick and easy access.
3) Remove the drip tray to reveal the waste funnel. This is done by lifting it upwards at the
front as it simply rests in place again for easy access and cleaning.
Preparing the machine for installation
E
2
3
1
2