19
P/N 42-9471 11/12 Copyright 2012 Mestek, Inc.
Cast iron condensing boiler
Cast iron condensing boiler — Vent/air manual
Vent and air piped through a side wall (separate terminations) (cont.)5
❑Slope horizontal runs toward the boiler. All horizontal runs of vent pipe
must slope continuously at least ¼ inch per foot (21 mm per meter) to ensure
condensate drains completely back to the boiler. DO NOT install the vent piping
with any sections that could trap condensate.
2 — Vent piping components
❑See Table 5 for acceptable vent components. NO OTHER vent materials are
acceptable.
❑Carefully follow the instructions supplied by the vent piping manufacturer.
❑Install the sidewall vent termination before installing the vent piping.
❑e vent joints seal with elastomer rings in the pipe and ings. Avoid damaging
these seals.
❑Adjustable lengths of EZ-Seal pipe —Lengthadjustmentswith EZ-Seal piping
are done with slip-t adjustable length sections, not by cuing the pipe. Make sure
the adjustable length does not jut into elbows or terminations. is could block
ue gas and condensate ow.
❑Maximum vent piping length — See the table in Figure 14 for the maximum
allowable length. Each elbow causes the same pressure drop as 10 feet of vent pipe,
so the allowable length reduces 10 feet for each elbow used in the piping. When
45° elbows are used, two 45° elbows are equivalent to one 90° elbow.
❑Insulate the vent piping where it passes through unheated areas to prevent
condensate freeze-up. If the vent terminates through a combustible wall, leave the
last 18 inches of vent pipe uninsulated.
❑If the pipe passes through an occupied space, install a chase around the pipe,
following the vent pipe instructions and applicable codes.
❑Clearance from combustible materials — Provide minimum clearance to all
combustible materials of at least 2 inches (51 mm).
3 & 4 — Support the vent piping completely
❑DO NOT use the boiler vent connection to support the vent piping. Provide
support straps from the ceiling and pedestal supports from the oor; utilize non-
combustible saddle. is is required on ALL installations, regardless of the length
of the horizontal piping connected to the boiler.
❑Install at least one support on every horizontal run. For horizontal runs
longer than 5 feet (1.5 m), install a support every 3 feet (0.9 m).
❑Vent piping cannot be supported from above (such as relying on roof jack
sections). You must install supports on the horizontal piping before the vent turns
upward. Provide a support on the horizontal piping within 6 inches of every up-
turned elbow to support the vertical run.
❑Follow the vent pipe manufacturer’s instructions for placement and installation of
supports.
❑Followapplicablecodesand the ventpipe instructionstoinstallrestops,thimbles
or other devices at all oor and wall penetrations.
❑Provide minimum 2 inches (51 mm) clearance to all combustible construction. continued on next page
5 — Air pipe connection
❑Before installing the air piping, install the air pipe sidewall
termination assembly (item 7, Figure 14). See instructions
on next page.
❑Construct the air piping from 3 inch PVC, CPVC or ABS
plastic, or 3 inch galvanized or aluminum metallic pipe
(including exible aluminum duct if desired).
When using metallic piping — seal all of the
longitudinal seam joints in addition to the
component joints.
❑Aach the air piping to the boiler air connection, requiring
use of silicone RTV to seal the connection. If the boiler
room air is free of contaminants you can use metallic duct
tape to seal the joints. With age, however, duct tape
adhesives can loosen, so duct tape is not as reliable as
siliconeRTV.
❑If the installation is required to meet direct vent (sealed
combustion) requirements, seal all joints with silicone RTV.
e air pipe installation must be air-tight and water-tight.
❑Maximum air piping length — See the table in Figure 14
for the maximum allowable length. Each elbow causes the
same pressure drop as 10 feet of vent pipe, so the allowable
length reduces 10 feet for each elbow used in the piping.
When 45° elbows are used, two 45° elbows are equivalent
to one 90° elbow.
6 — Supporting air piping
❑DO NOT use the boiler air connection to support the
air piping. Provide support straps from the ceiling or install
wall brackets.
❑Provide at least one support on all air pipe installations.
❑Provide a support every 3 feet for air pipe lengths greater
than 5 feet horizontally.
❑Provide a support on the horizontal piping within 6 inches
of every upturned elbow to support the vertical run.
7 — Sidewall termination assemblies
❑See next page.