Premier Tech Aqua 2/3 Installation guide –Flash Mix –PSA-240HD
Edition: 2019-01-09
1.3 Step 3 –Riser installation (if required)
When the pumping station installation requires extension risers, proceed as follows:
•Use PSR-060 (150 mm, 6") risers or PSR-140 (355 mm, 14")
risers if required. Maximum height of risers: 710 mm (28").
•Clean the access rim of the pumping station (where 4 holes
were perforated to insert the lag screws).
•Install the watertight seal on the pumping station’s access
rim.
•Align the holes of the riser with the holes of the pumping
station.
•Insert the washers in the lag screws provided with the riser
and screw them in place to firmly fix the riser.
1.4 Step 4 –Electrical connections
The electrical connections should be executed by an electrician. IF YOUR LOCAL ELECTRIC CODE
ALLOWS IT, remove the connector plugs from the float and pump wires by cutting the ends and perform
the electrical connections using the supplied waterproof screw-thread wire connectors in order to ensure
the water does not affect the electrical circuit. The use of waterproof screw-thread wire connectors is
mandatory with the electrical junction box. Note that the junction box must be installed outside of the
pumping station, on a post above the ground surface, to prevent the box from being submerged and also
to have access to the box at all times.
To wire the system, two (2) in-ground double strand supply cables are required. It is preferable to protect
the wires with the appropriate piping before burying them. To pass wires through the pumping station’s
wall, use watertight bulkhead union fittings.
Important: before the pumping station start-up, check if the float holding device for the transportation
has been removed. Also, check if the floats are ready and in the proper position for operation.
1.5 Step 5 –Final backfill
•Close the lid so nothing falls into the pumping station during
backfill.
•Isolate the pipes if required.
•Backfill the pumping station and the pipes with material void of
any organic matter, impervious soil, stones, debris, particles
larger the 20 mm (¾") in diameter or any other object that could
damage the pumping station.
•The backfill material must be placed with care and not dumped
(do not compact with bulldozer).
•Allow space for ground cover and make sure the lids are at least
50 mm (2") above the surface of the landscaped lot.
•Finalise the backfill with a layer of soil that encourages
vegetation growth.