
2
INSTALLATION—MATERIAL, TOOLS, AND EQUIPMENT
INSTALLATION
MATERIAL, TOOLS, AND EQUIPMENT
1. Threaded rod (¹₂-in. diameter) and other various
wall anchor hardware and material. Concrete
anchor bolts (¹₂-in. diameter).
(See “ANCHORING METHODS” on page 3.)
2. Assorted shim stock.
3. Double-sided tape (to temporarily hold shims).
4. Carpenter’s or spirit level (4-ft. minimum length).
5. Carpenter’s square.
6. Hammer drill.
7. Masonry drill bit (for ¹₂-in. diameter anchors).
8. Three or four bar clamps (48-in. long).
9. Hammer or mallet, and block of wood.
10. Crowbar or pry bar.
11. Assorted hand tools (pliers, tape measure, etc.).
12. Socket and wrench sets.
13. Water level, line level, or transit.
14. Two ladders (taller than height of door opening).
15. Forklift (see “Forklift Requirements” below).
ADDITIONAL REQUIREMENTS
Labor and Site Requirements
1. Two installers.
2. An electrician is required for making all electrical
connections. (See “Electrician’s Responsibilities”
on page 2.)
NOTE: All electrical work must be performed in
accordance with local and state building
codes.
3. 100% accessibility to the door opening during the
entire installation process. No traffic should be
allowed to pass through the opening while the door
is being installed.
Forklift Requirements
A forklift supplied by the customer, dealer, or installer is
mandatory for the safe and proper installation of this
door. The forklift should have:
• 2,000-pound lift capacity
• Minimum height ability — door height, plus 12 in.
• Side-shift capability (desired)
Electrician’s Responsibilities
For complete details on the responsibilities of the elec-
trician, refer to the Rytec System 4 Drive & Control
Installation & Owner’s Manual.
Floor-Loop Activator Requirements
If a floor-loop activator was ordered and shipped with
your Rytec door, the following additional items will be
required to install the activator.
NOTE: For complete floor-loop installation instruc-
tions, refer to the manual that was shipped
with the activator.
1. Concrete saw (with water cooling attachment).
2. Water supply and garden hose.
3. Wet/dry shop vacuum.
4. 200–500 feet of 16-gauge, 19-strand, type XLPE,
copper, crosslink polyethylene jacket wire (or equiv-
alent). The size of the floor loop will determine the
length of wire required.
5. Bondo P606 Flexible Embedding Sealer (or equiva-
lent) — required to fill saw cuts in floor after the acti-
vator is installed. For cold temperature applications,
Bondo P610 Speed Set must be added to the P606
to ensure the sealer cures properly.
Fill-In Material Requirements
Some applications may require the use of a door pullout
(extension) to gain clearance of an existing obstruction
between the door and the door opening. The following
materials can be used to fill the space or gap between
the door and the door opening.
1. 16-gauge hot-rolled sheet steel.
2. 2-in. x 2-in. x ³₁₆-in. angle iron.