CT & WiFi Connection
614.00742.04
Installation Steps
STEP 6: Insert the prepared communication cable through the waterproof connector in sequence as shown below (If the cable is self-made, also
insert the wires into the RJ45 terminals and then use crimping pliers to press them tightly).
STEP 7: Strip the outer sheath of the input cable for a length of 60-70 mm, ensuring all the wires can reach the terminal blocks with a little
excessive length. Use the stripping pliers to strip approx. 12 mm of insulation from the end of all the coloured wires as below. Then crimp the
European terminal with the wire crimper.
STEP 8: Insert the input cable through the waterproof connector in sequence as shown below.
①
③
②
strip length
L1 L2 L3
60-70 mm
60-70 mm
Ou t er Shea t h
12 mm
STEP 9: Insert the wires into the appropriate holes of the terminal
blocks, traight screwdriver then block the terminals with the s .
STEP 10: Press the spring upward and push the base plate of
communication board in. Then screw the countersunk screw.
Diagram:
-Steady the CT on the public grid.
-Insert the other end of the communication cable and the terminal
of CT on each side of the RJ45 terminal adapter.
STEP 11: Push the rear cover to appropriate position of the cables and screw the self tapping screws with the cross screwdriver. Then tighten the
waterproof fastening head.
STEP 12: Hang the EV-Charger up carefully and steady the EV-Charger with the self tapping screw and the cross screwdriver.
For Plug Type, connect the charging connector with the
EV-Charger and hang the connecting cable on the hook.
► CT Connection ► WiFi Connection
Step 1: Use your smart phone to scan below QR code or search
for the keyword “SolaXCloud” in browser to download the
Monitoring App.
Step 2: Create a new account on the Monitoring App.
Step 3: Login and turn to Account page in the app. Then click “Wi-Fi
Connection” and follow the instructions to complete the process.
IOS Google
• Do not place the CT on the N Wire or the PE wire.
• Do not place the CT on the N and L wire
simultaneously.
• Do not place the CT on the non-insulated wires.
• When using the three-phase CT, please clip the CT
clamps on the corresponding phases.
NOTE!
1 2 3456 7 8
1) White with orange stripes
2) Orange
3) White with green stripes
4) Blue
5) White with blue stripes
6) Green
7) White with brown stripes
8) Brown
①
③
②
PIN
Definition
1 2 3 4 5 6 7 8
A1
L1_CT+ B1
L1_CT- L3_CT+ L3_CT-L2_CT+ L2_CT-
* PIN 3, 6, 7, 8 is null for single-phase.
<4 mm
(torque:1.5~1.8 N·m)
L1
L2
L3
N
PE
grid EV- Charger
(torque: 2~2.5 N·m)
L line
CT
Public grid
electricity
Notice: The arrow on the CT
must point at the public grid.
Electrical
grid
other home Load
PV array
AC distribution box
Inverter
CT
Electricity meter,
bidirectional
XXX
Ver s i on:Vx x x x.xx.x x
(torque:0.8~1.5 N·m)
(torque: 2~2.5 N·m)