NOTE:
The chase must be properly
sealed at the ceiling level or
between oors in a multilevel
installation.
See "Ceiling Firestop" section.
12”
28 1/4”
47 3/8”
47 3/8”
40 3/8”
5056.429D
Note: The replace should be in place
and venting installed before framing in
or building an enclosure around the unit.
TheTown & Country replace must be framed
in as described below or totally enclosed
with non-combustible material, such as
facing brick.
Determine the total thickness of facing
material to be used. A thickness of 3/4" will
allow the nishing surface to be ush with
the front of the unit. If preferred, additional
masonry type non-combustible material can
be installed above and to the sides up to 6
inches proud of the appliance.
The nishing material must not interfere
with glass frame access or movement.
A Steel Stud Framing Kit is supplied with the
replace and must be used unless the
replace is totally enclosed with
non-combustible material. Assemble the
framing kit as per the instructions on pages 10
& 11 of this manual. Attach the steel frame to
the replace once the replace is in its nal
position.Secure the steel frame to the framing
brackets on each side of the unit.Ensure that
the studs are set back far enough to allow for
thickness of nishing surface.
The sides, back and top of the replace can
be framed in up to the steel studs and the
replace standoffs using conventional
lumber. Consult local building codes for
specic requirements.
Due to high temperatures,non-combustible
backer board, such as cement board or it’s
equivalent must be used to sheet in the front
of the replace, extending 12" above and
5 7/8" to the side of the framing edge bars.
(Fig #11) Standard sheet rock (dry wall) may
be used beyond this.
If the backer board is not to be nished with
other non-combustible material such as tiles,
it is recommended that the instructions in
Fig.#11a be followed closely.
Chase Insulation: When installing this
replace against a non-insulated exterior wall
or chase, it is recommended that the outer
walls be insulated to same degree as other
exterior walls. Do not place replace directly
against the insulation. Cover the insulation
and plastic vapour barrier with a solid surface,
such as dry wall (sheet rock). Consult local
codes. Do not insulate or use plastic vapour
barrier within the framing kit.
CAUTION: SEE FIGURE #11a BEFORE
PROCEEDING.
Fig. #10
NON-COMBUSTIBLE ZONE. DO NOT INSTALL ANY
COMBUSTIBLE MATERIAL, ELECTRICAL WIRING, INSU-
LATION, PLASTIC VAPOR BARRIER OR GAS PLUMBING
WITHIN THE STEEL STUD FRAMING ALL OTHER FRAMING CAN BE
DONE WITH CONVENTIONAL
LUMBER
STEEL STUD FRAMING KIT DIMENSIONS
(Supplied with replace)
8
TC30_D 180315-48
Framing and Finishing