The PICV valve should be setup to the design owrate of the unit. Please see table below.
PICV Valve Commissioning
Pressetting
%
Max
Flowrate
l/h
Flowrate
l/s
100 780 0.217
90 702 0.195
80 624 0.173
70 546 0.152
60 468 0.130
50 390 0.108
40 312 0.087
30 234 0.065
20 156 0.043
10 78 0.022
Step 1
Remove Velcro lined insulation
around the Pressure Independent
Control Valve to access binder
points .
Step 2
Using the binder points , measure the
differential pressure across the valve .
If the measured differential pressure is
higher than the start-up pressure (>20kPa),
the valve is keeping the ow stable at the
preset value.
Item Description
Lined Insulation with Velcro xings
Pressure Independent Control Valve (PICV)
Binder Insertion Points
Pressure Gauge (supplied by others)
PICV Binder Points
Commissioning Plug
Return Air Sensor Socket
Red Plug - Heating Mode
Blue Plug - Cooling Mode
Heating Mode (valves energised)Cooling Mode (valves de-energised)
Commissioning Mode
Thermic Valve Positions
Always use the electrical connection tool when inserting/removing temperature sensors
and commissioning plugs to reduce the risk of damage to the retaining clip.
The commissioning plugs are used to force actuator operation.
Push Push
Filter Installation / Removal
Network Setup
Air Bleed
Bleeding the Coil
Airedale International Air Conditioning Ltd. Leeds Road, Rawdon, Leeds, LS19 6JY.
T
el:
+44
(0)
1
13
2391000
Fax:+44
(0)
1
13
2507219
E-mail:
[email protected] Web:
www
.airedale.com
Airedale do not offer any commissioning services for the Artus. Mechanical commissioning, including
water side balancing, must be completed by others before Airedale or other third party Siemens Solution
Partners congure the Artus(s) for master/slave operation, room operator units, BMS integration etc.
The serial number shown on the barcode on the inside of the lid must be recorded along with installed
location prior to arranging network setup.
Push
Required for water balancing.
Note: Power must be ON.