Bull ESCALA Series Reference guide

Bull ESCALA EPC
1200 Rack (32U) and T00 Rack (36U)
Installation Procedures for Drawers
86 A1 29PX 06
ORDER REFERENCE


Bull ESCALA EPC
1200 Rack (32U) and T00 Rack (36U)
Installation Procedures for Drawers
Hardware
January 2001
BULL CEDOC
357 AVENUE PATTON
B.P.20845
49008 ANGERS CEDEX 01
FRANCE
86 A1 29PX 06
ORDER REFERENCE

The following copyright notice protects this book under the Copyright laws of the United States of America
and other countries which prohibit such actions as, but not limited to, copying, distributing, modifying, and
making derivative works.
Copyright Bull S.A. 1992, 2001
Printed in France
Suggestions and criticisms concerning the form, content, and presentation of
this book are invited. A form is provided at the end of this book for this purpose.
To order additional copies of this book or other Bull Technical Publications, you
are invited to use the Ordering Form also provided at the end of this book.
Trademarks and Acknowledgements
We acknowledge the right of proprietors of trademarks mentioned in this book.
AIXRis a registered trademark of International Business Machines Corporation, and is being used under
licence.
UNIX is a registered trademark in the United States of America and other countries licensed exclusively through
the Open Group.
The information in this document is subject to change without notice. Groupe Bull will not be liable for errors
contained herein, or for incidental or consequential damages in connection with the use of this material.

iii
About This Book
About This Book
About This Book
This document explains how to configure hardware components in the racks 1200 and T00
of the ESCALA Series. It gives the philosophy behind the configuration rules of the drawers
and explains how to install physically the drawers in the rack.
This document does not apply to the EPC400 rack model. If you need to install hardware
component in such a rack, please refer to the Escala EPC400 Rack Service Guide,
reference 86 A1 20PX.
Audience
This manual is aimed at people responsible for the installation of the drawers in the
ESCALA 1200 and T00 racks.
The procedures described in this guide must be performed by people trained to perform
service tasks on the system.
Document Overview
Chapter 1 Drawer Configuration
Describes the configuration rules needed to plan the installation of the
drawers in the rack.
Chapter 2 Installing Drawers in the 1200 or T00 Rack
Explains how to install physically the drawers in the rack.
Related Publications
Supplementary information on the installation of drawers is given in the manuals listed
below. You should also consult the documents provided with the equipment.
•ESCALA Site Preparation for Rack Systems
Reference: 86 A1 30PX
•T00 Rack Installation and Service Guide
Reference: 86 A1 94KX

iv Installation Procedures for Drawers

v
Table of Contents
Table of Contents
About This Book iii. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Chapter 1. Drawer Configuration 1-1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Introduction 1-1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1200 (32U) Rack Configuration 1-2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Rack Description 1-3. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Configuration Rules 1-4. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
T00 Rack (36U) Configuration 1-9. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Drawer Location in T00 Rack 1-9. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Chapter 2. Installing Drawers in the 1200 or T00 Rack 2-1. . . . . . . . . . . . . . . . . . . . .
Introduction 2-1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing DAS 5700/4500 (Disk-Array Processor Enclosure) Drawers 2-2. . . . . . . . . . .
General Installation Procedure 2-2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Emptying the Drawer 2-3. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fixing the Rails to the Rack 2-6. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Positioning the DAS 5700/4500 Drawer inside the Rack 2-6. . . . . . . . . . . . . . . . . . . .
Securing the DAS 5700/4500 Drawer to the Rack 2-7. . . . . . . . . . . . . . . . . . . . . . . . . .
Replacing the Elements Taken Out of the Drawer 2-8. . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a Standby Power Supply (SPS) 2-11. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Positioning the SPS Support Plate 2-11. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing one SPS 2-12. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing two SPS 2-14. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing DAS 5300 (Disk-Array Subsystem) Drawers 2-16. . . . . . . . . . . . . . . . . . . . . . . .
General Installation Procedure 2-16. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Emptying the Drawer 2-17. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fixing the Rails to the Rack 2-19. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Positioning the DAS 5300 Drawer inside the Rack 2-19. . . . . . . . . . . . . . . . . . . . . . . . .
Securing the DAS 5300 Drawer to the Rack 2-21. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Replacing the Elements Taken Out of the Drawer 2-22. . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a Direct Current Standby Power Supply (DC SPS) 2-25. . . . . . . . . . . . . . . . . . .
Positioning the DC SPS Support Plate 2-25. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Securing the Spacer Tray to the DC SPS 2-26. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing one DC SPS 2-27. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing two DC SPS 2-28. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing DAE5000 Series (Disk-Array Enclosure) Drawers 2-31. . . . . . . . . . . . . . . . . . . .
General Installation Procedure 2-31. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Emptying the DAE5000 Drawer 2-32. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fixing the Rails to the Rack 2-34. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Positioning the DAE5000 Drawer inside the Rack 2-34. . . . . . . . . . . . . . . . . . . . . . . . . .
Securing the DAE5000 Drawer to the Rack 2-35. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Replacing the Elements Taken Out of the Drawer 2-36. . . . . . . . . . . . . . . . . . . . . . . . . .
Installing DAS 3500 and DAS 3200 Drawers 2-39. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a DAS 2900 Drawer 2-45. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a FC-AL Hub 2-50. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a Vixel 1000 Fibre Channel Hub 2-52. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing an Overland LBX Tape Library drawer 2-54. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing the Slides 2-54. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing the Drawer in the Slides 2-55. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

vi Installation Procedures for Drawers
Installing a DLT 4000/7000 2-56. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a PortServer Console Concentrator 2-59. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a Cluster Hub 2-61. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a Console Concentrator and a Cluster Hub in the Same Unit of a Rack 2-63.
Installing a Fast or Gigabit Ethernet Switch 2-67. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a Fibre Channel Switch 16 Ports 2-69. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a Fibre Channel Switch 8 Ports 2-71. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing an External Modem 2-72. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Connecting the Modem to the Power Source 2-72. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Connecting the Modem to the I/O Drawer 2-73. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Physical Installation of the Modem 2-73. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing a PDU 450 in a T00 Rack 2-74. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing the Rails 2-74. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing the PDU in the Slides 2-75. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing an EPC450 in a T00 Rack 2-76. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installing the Rails 2-76. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Glossary G-1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

1-1
Drawer Configuration
Chapter 1. Drawer Configuration
Introduction
This chapter describes the basic rules needed to plan the configuration of the drawers
inside either a 1200 or a T00 rack.
Depending on the rack model where you need to install new hardware components, refer to
one of the following sections:
•1200 Rack (32U) Configuration on page 1-2
•T00 Rack (36U) Configuration on page 1-9

1-2 Installation Procedures for Drawers
1200 (32U) Rack Configuration
The 1200 Rack configuration includes the following hardware components.
•I/O Drawer
•DAS Drawers
•SSA Drawer
•Overland LBX Tape Library Drawer
•DLT 4000/7000
•FC-AL Hub
•Vixel 1000 Fibre Channel Hub
•Cluster Hub
•Console Concentrator
•Fast or Gigabit Ethernet Switch
The number of drawers is limited per system and per rack.
Maximum number of drawers per system:
–I/O Drawer 4
–DAS Drawer 8
–SSA Drawer 16
–Overland LBX Tape Library Drawer 1
–FC-AL Hub 4
Maximum number of drawers per I/O rack:
–I/O Drawer 2
–DAS Drawer 2
–SSA Drawer 4
–Overland LBX Tape Library Drawer 1
–FC-AL Hub 1
Maximum number of drawers per storage rack (rack that has no I/O drawer):
–DAS Drawer 2
–SSA Drawer 4
–Overland LBX Tape Library Drawer 1
–FC-AL Hub 1

1-3
Drawer Configuration
Rack Description
The rack is divided into 32 Units (U).
1U = 44.45 mm
The units are numbered from bottom to top as shown below. The unit numbering is
punched on the inside edge of one of the side panels both at the front and at the rear of the
cabinet.
32
31
30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
32
31
30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
PDU*
REAR VIEW
*Power Distribution Unit
Figure 1. Position of the 32 Units in a rack.

1-4 Installation Procedures for Drawers
Configuration Rules
Each type of drawer installed inside the rack has a height given in number of units and has
a priority which determines its position inside the rack.
Priority is determined by drawer function, its height and its weight.
When installing the drawers in the rack, plan configuration according to the following
considerations:
•Start by installing the drawer with the highest priority (refer to the table below).
•If a drawer can be positioned in more than one place, start with position 1. If this position
is not free, use position 2 and so on (refer to the tables below).
Table 1. Drawer priority and positions in the rack (positions 1 to 10)
Prior-
ity
Drawer Height 1st
Pos.
2nd
pos.
3rd
Pos.
4th
Pos.
5th
pos.
6th
pos.
7th
pos.
8th
pos.
9th
pos.
10th
pos.
1I/O Drawer 10U
(2400)
10U 23-32 13-22
2I/O Drawer 10U
(rackless)
10U 23-32 13-22
3I/O Drawer 10U
(1200A)
10U 23-32 13-22
4I/O Drawer 10U
(rackless)
10U 23-32 13-22
5I/O Drawer 7U (1200) 7U 26-32 19-25
6
610 CEC + I/O Dr
10U
23-32
13-22
10-19
7
810 CEC +I/O Dr
13U
20-32
10-22
7-19
8
810 sec +I/O Dr
5U
28-32
23-27
18-22
15-19
13-17
10-14
8-12
5-9
3-7
2-6
9
Disk Drawer
3U
30-32
29-31
28-30
27-29
26-28
25-27
24-26
23-25
22-24
21-23
10
Upgrade 610 – 810
3U
20-22
19-21
18-20
17-19
16-18
15-17
14-16
13-15
12-14
11-13
11
EPC 440 add’l
8U
25-32
17-24
13-20
9-16
5-12
12 DAS 3500 12U 1-12 13-24
13 DAS 3200 12U 1-12 13-24
14 DAS 2900 8U 1-8 9-16 17-24 25-32
15
SPS/DAS 5300/
2DAE 5000
13U
1-13
17-29
16
SPS/DAS 5300/
1DAE 5000
9U
1-9
13-21
17
SPS/DAS 5300
5U
1-5
9-13
17-21
25-29
18 SSA 4U 25-28 21-24 17-20 13-16 9-12 5-8
19 Overland Library
(LBX4000/LBX7000)
4U 1-4 5-8 9-12 13-16 17-20 21-24
20 DLT 4000/7000 4U 9-12 5-8 1-4 13-16 17-20 21-24
21 SPS/DPE5700/4500
5 DAE5000
28U 1-28
22 SPS/DPE5700/4500
4 DAE5000
24U 1-24
23 SPS/DPE5700/4500
3 DAE5000
20U 1-20
24 SPS/DPE5700/4500
2 DAE5000
16U priority #24 is the application of priorities #25 and #27

1-5
Drawer Configuration
Prior-
ity
10th
pos.
9th
pos.
8th
pos.
7th
pos.
6th
pos.
5th
pos.
4th
Pos.
3rd
Pos.
2nd
pos.
1st
Pos.
HeightDrawer
25 SPS/DPE5700/4500
1 DAE5000
12U 1-12 13-24
26 SPS/DPE5700/4500 8U 1-8 9-16 17-24 25-32
27 DAE5000 4U 1-4 5-8 9-12 13-16 17-20 21-24 25-28 29-32
28
FC–AL Hub / vixel
1U
1-1
5-5
9-9
13-13
17-17
19-19
21-21
25-25
26-26
29-29
29 Console Concent. &
ClusterHub
4U 1-4 5-8 9-12 13-16 17-20 21-24 25-28 29-32
30 Console Concent. 4U 1-4 5-8 9-12 13-16 17-20 21-24 25-28 29-32
31 Switch 8–port 1U anywhere from 1–1 to 32–32
32
Switch FC 16–port
2U rear
17-18
19-20
21-22
25-26
26-27
29-30
13-14
9-10
5-6
1-2
33 Switch Fast Ethernet 2U rear 1-2 5-6 9-10 13-14 17-18 19-20 21-22 25-26 26-27 29-30
34 Switch Gbit Ethernet 2U rear 1-2 5-6 9-10 13-14 17-18 19-20 21-22 25-26 26-27 29-30
35 Cluster Hub 2U rear 1-2 5-6 9-10 13-14 17-18 19-20 21-22 25-26 26-27 29-30
36 Cons Conc 16–port 2U 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10 10-11
37 Cons Conc 16–port &
Cluster Hub
2U 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10 10-11
38 Bridge FC 1U rear 1-1 5-5 9-9 13-13 17-17 19-19 21-21 25-25 26-26 29-29
39 Rack Content Specify 7U 1-7 2-8 3-9 4-10 5-11 6-12 7-13 8-14 9-15 10-16
40 Rack Content Specify 4U 1-4 5-8 9-12 13-16 17-20 21-24 25-28 29-32
41 Rack Content Specify 3U 1-3 2-4 3-5 4-6 5-7 6-8 7-9 8-10 9-11 10-12
42 Rack Content Specify 2U 1-2 5-6 9-10 13-14 17-18 19-20 21-22 25-26 26-27 29-30
43 Rack Content Specify 1U 1-1 5-5 9-9 13-13 17-17 19-19 21-21 25-25 26-26 29-29
Table 2. Drawer priority and positions in the rack (positions 11 to 20)
Prior-
ity
Drawer Height 11th
Pos.
12th
pos.
13th
Pos.
14th
Pos.
15th
pos.
16th
pos.
17th
pos.
18th
pos.
19th
pos.
20th
pos.
1I/O Drawer 10U
(2400)
10U
2I/O Drawer 10U
(rackless)
10U
3I/O Drawer 10U
(1200A)
10U
4I/O Drawer 10U
(rackless)
10U
5I/O Drawer 7U (1200) 7U
6
610 CEC + I/O Dr
10U
7
810 CEC +I/O Dr
13U
8
810 sec +I/O Dr
5U
9
Disk Drawer
3U
20-22
19-21
18-20
17-19
16-18
15-17
14-16
13-15
12-14
11-13
10
Upgrade 610 – 810
3U
10-12
9-11
8-10
7-9
6-8
5-7
4-6
3-5
2-4
1-3
11
EPC 440 add’l
8U
12 DAS 3500 12U
13 DAS 3200 12U
14 DAS 2900 8U
15
SPS/DAS 5300/
2DAE 5000
13U

1-6 Installation Procedures for Drawers
Prior-
ity
20th
pos.
19th
pos.
18th
pos.
17th
pos.
16th
pos.
15th
pos.
14th
Pos.
13th
Pos.
12th
pos.
11th
Pos.
HeightDrawer
16
SPS/DAS 5300/
1DAE 5000
9U
17
SPS/DAS 5300
5U
18 SSA 4U
19 Overland Library
(LBX4000/LBX7000)
4U
20 DLT 4000/7000 4U
21 SPS/DPE5700/4500
5 DAE5000
28U
22 SPS/DPE5700/4500
4 DAE5000
24U
23 SPS/DPE5700/4500
3 DAE5000
20U
24 SPS/DPE5700/4500
2 DAE5000
16U priority #24 is the application of priorities #25 and #27
25 SPS/DPE5700/4500
1DAE5000
12U
26 SPS/DPE5700/4500 8U
27 DAE5000 4U
28
FC–AL Hub / vixel
1U
29 Console Concent. &
ClusterHub
4U
30 Console Concent. 4U
31 Switch 8–port 1U anywhere from 1–1 to 32–32
32
Switch FC 16–port
2U rear
33 Switch Fast Ethernet 2U rear
34 Switch Gbit Ethernet 2U rear
35 Cluster Hub 2U rear
36 Cons Conc 16–port 2U 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21
37 Cons Conc 16–port &
Cluster Hub
2U 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21
38 Bridge FC 1U rear
39 Rack Content Specify 7U 11-17 12-18 13-19 14-20 15-21 16-22 17-23 18-24 19-25 20-26
40 Rack Content Specify 4U
41 Rack Content Specify 3U 11-13 12-14 13-15 14-16 15-17 16-18 17-19 18-20 19-21 20-22
42 Rack Content Specify 2U
43 Rack Content Specify 1U
Table 3. Drawer priority and positions in the rack (positions 21 to 30)
Prior-
ity
Drawer Height 21th
Pos.
22th
pos.
23th
Pos.
24th
Pos.
25th
pos.
26th
pos.
27th
pos.
28th
pos.
29th
pos.
30th
pos.
1I/O Drawer 10U
(2400)
10U
2I/O Drawer 10U
(rackless)
10U
3I/O Drawer 10U
(1200A)
10U

1-7
Drawer Configuration
Prior-
ity
30th
pos.
29th
pos.
28th
pos.
27th
pos.
26th
pos.
25th
pos.
24th
Pos.
23th
Pos.
22th
pos.
21th
Pos.
HeightDrawer
4I/O Drawer 10U
(rackless)
10U
5I/O Drawer 7U (1200) 7U
6
610 CEC + I/O Dr
10U
7
810 CEC +I/O Dr
13U
8
810 sec +I/O Dr
5U
9
Disk Drawer
3U
10-12
9-11
8-10
7-9
6-8
5-7
4-6
3-5
2-4
1-3
10
Upgrade 610 – 810
3U
11
EPC 440 add’l
8U
12 DAS 3500 12U
13 DAS 3200 12U
14 DAS 2900 8U
15
SPS/DAS 5300/
2DAE 5000
13U
16
SPS/DAS 5300/
1DAE 5000
9U
17
SPS/DAS 5300
5U
18 SSA 4U
19 Overland Library
(LBX4000/LBX7000)
4U
20 DLT 4000/7000 4U
21 SPS/DPE5700/4500
5 DAE5000
28U
22 SPS/DPE5700/4500
4 DAE5000
24U
23 SPS/DPE5700/4500
3 DAE5000
20U
24 SPS/DPE5700/4500
2 DAE5000
16U priority #24 is the application of priorities #25 and #27
25 SPS/DPE5700/4500
1DAE5000
12U
26 SPS/DPE5700/4500 8U
27 DAE5000 4U
28
FC–AL Hub / vixel
1U
29 Console Concent. &
ClusterHub
4U
30 Console Concent. 4U
31 Switch 8–port 1U anywhere from 1–1 to 32–32
32
Switch FC 16–port
2U rear
33 Switch Fast Ethernet 2U rear
34 Switch Gbit Ethernet 2U rear
35 Cluster Hub 2U rear
36 Cons Conc 16–port 2U 21-22 22-23 23-24 24-25 25-26 26-27 27-28 28-29 29-30 30-31
37 Cons Conc 16–port &
Cluster Hub
2U 21-22 22-23 23-24 24-25 25-26 26-27 27-28 28-29 29-30 30-31
38 Bridge FC 1U rear
39 Rack Content Specify 7U 21-27 22-28 23-29 24-30 25-31 26-32

1-8 Installation Procedures for Drawers
Prior-
ity
30th
pos.
29th
pos.
28th
pos.
27th
pos.
26th
pos.
25th
pos.
24th
Pos.
23th
Pos.
22th
pos.
21th
Pos.
HeightDrawer
40 Rack Content Specify 4U
41 Rack Content Specify 3U 21-23 22-24 23-25 24-26 25-27 26-28 27-29 28-30 29-31 30-32
42 Rack Content Specify 2U
43 Rack Content Specify 1U
The procedure for installing the EPC440 drawer inside a rack can be found in the ESCALA
EPC440 Series Installation and Service Guide – 86 A1 84 KX.
Special Requirements for Drawers
•The I/O drawer(s) must be positioned at the top of the rack.
•The I/O drawer(s) and the SSA drawer(s) are already pre-installed in the rack and
therefore their physical installation in the rack is not documented here.
•In the case of the DAS 3500 and the DAS 3200, the DAS drawer is 11 units high but a
12th unit must be kept for the support plate.
•If additional Overland Library drawers are part of the configuration, these must be placed
just above or just under the first Overland Library drawer.

1-9
Drawer Configuration
T00 Rack (36U) Configuration
The following provides you with the rules involved with drawer mounting inside the 19 ” 36U
T00 rack.
•Each drawer is characterized by its own U height.
Note: Each drawer is affected by a priority. This attribute is useful during the configuration
phase.
•The criteria used to assign a priority to a drawer are:
–Drawer height
–Drawer weight
So, a 12U, 20Kg drawer will have a higher priority than a 8U, 30kg one.
•CPU drawer is an exception to this. Its priority, especially for the first CPU drawer, is
based on its media accessibility: floppy, disk, tape, CD–Rom, and operator panel.
Therefore a CPU drawer is always placed at a convenient height.
•An additional rack is generated when there is no room left that suits to the remaining
drawers.
•For mechanical stability, it is advised to start loading from the bottom, if possible.
•The list of all available drawers that can be put inside the rack is specified in the following
section.
To establish location of drawers inside a rack, follow location rules given in the following
table. Then, in compliance with priorities, assign for each drawer its own location. It is
important to recall that more than one rack may compose a Powercluster.
Drawer Location in T00 Rack
To establish location of drawers inside a rack, follow location rules given in the following
table. Then, in compliance with priorities, assign for each drawer its own location. It is
important to recall that more than one rack may compose a Powercluster.
Note: Even if an area is not fully filled, the remaining space must be kept free.
Table 4. Drawer priority and positions in the rack 1 to 9
Prior-
ity
Drawer Height 1st
Pos.
2nd
pos.
3rd
Pos.
4th
Pos.
5th
pos.
6th
pos.
7th
pos.
8th
pos.
9th
pos.
1PDU 450 2U 1-2
2I/O Drawer 10U 27-36 17-26 7-16
3EPC610 CEC+I/O 10U 23-32 17-26 13-22 10-19 7-16 4-13
4EPC810 CEC+I/O 13U 20-32 14-26 10-22 7-19 4-16 1-13
5Secondary I/O Drawer 5U 28-32 27-31 26-30 25-29 24-28 23-27 22-26 21-25 20-24
6Disk Drawer 3U 33-35 34-36 32-34 31-33 30-32 29-31 28-30 27-29 26-28
7
upgrade 610–810
3U
20-22
19-21
18-20
17-19
16-18
15-17
14-16
13-15
12-14
8EPC 450 + Exp Draw
Add’l
10U 23-32 13-22 10-19 3-12
9EPC 450 Add’l 5U 28-32 23-27 18-22 15-19 13-17 10-14 8-12 5-9 3-7
10 Exp Drawer 450 Add’l 5U 28-32 23-27 18-22 15-19 13-17 10-14 8-12 5-9 3-7
11 EPC440 Add’l 8U 25-32 17-24 13-22 12-19 9-16 5-12 4-11 2-9
12
SPS/DAS 5300/ 2DAE
5000
13U
1-13
3-15
14-26
16-28

1-10 Installation Procedures for Drawers
13
SPS/DAS 5300/ 1DAE
5000
9U
1-9
3-11
10-18
12-20
19-27
21-29
28-36
14
SPS/DAS 5300
5U
1-5
3-7
6-10
8-12
11-15
13-17
16-20
18-22
21-25
15 LXB 4000/7000 4U 33-36 32-35 31-34 30-33 29-32 28-31 27-30 26-29 25-28
16 DLT 4000/7000 4U 33-36 32-35 31-34 30-33 29-32 28-31 27-30 26-29 25-28
17 VDAT Mammoth 3U 34-36 33-35 32-34 31-33 30-32 29-31 28-30 27-29 26-28
18 SPS/DPE5700/4500
7DAE5000
36U 1-36
19 SPS/DPE5700/4500
6DAE5000
32U 1-32
20 SPS/DPE5700/4500
5DAE5000
28U 1-28
21 SPS/DPE5700/4500
4DAE5000
24U 1-24 3-26
22 SPS/DPE5700/4500
3DAE5000
20U 1-20 3-22
23 SPS/DPE5700/4500
2DAE5000
16U 1-16 3-18 17-32 19-34
24 SPS/DPE5700//4500
1DAE5000
12U 1-12 3-14 13-24 15-26 25-36
25 SPS/DPE5700/4500 8U 1-8 3-10 9-16 11-18 17-24 19-26 25-32 27-34
26 DAE5000 4U 1-4 2-5 3-6 4-7 5-8 6-9 7-10 8-11 9-12
27 FC–AL Hub/ Vixel 1U positions 1–1 to 36–36
28 Console Concent. &
ClusterHub
4U 1-4 2-5 3-6 4-7 5-8 6-9 7-10 8-11 9-12
29 Console Concent. 4U 1-4 2-5 3-6 4-7 5-8 6-9 7-10 8-11 9-12
30 Switch FC 8–Port 1U positions 1–1 to 36–36
31
Switch FC 16–Port
2U
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
32 Switch Fast Ethernet 2U 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10
33 Switch Gbit Ethernet 2U 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10
34 Cluster Hub 2U 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10
35 Cons. Conc 16–Port 2U 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10
36 Cons. Conc & Cluster
Hub
2U 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10
37 Bridge FC 1U positions 1–1 to 36–36
38 Rack Content Specify 7U 1-7 2-8 3-9 4-10 5-11 6-12 7-13 8-14 9-15
39 Rack Content Specify 4U 1-4 2-5 3-6 4-7 5-8 6-9 7-10 8-11 9-12
40 Rack Content Specify 3U 1-3 2-4 3-5 4-6 5-7 6-8 7-9 8-10 9-11
41 Rack Content Specify 2U 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10
42 Rack Content Specify 1U positions 1–1 to 36–36
Table 5. Drawer priority and positions in the rack 10 to 18
Prior-
ity
Drawer Height 10th
Pos.
11th
pos.
12th
Pos.
13th
Pos.
14th
pos.
15th
pos.
16th
pos.
17th
pos.
18th
pos.
1PDU 450 2U
2I/O Drawer 10U
3EPC610 CEC+I/O 10U
4EPC810 CEC+I/O 13U
5Secondary I/O Drawer 5U 19-23 18-22 17-21 16-20 15-19 14-18 13-17 12-16 11-15

1-11
Drawer Configuration
6Disk Drawer 3U 25-27 24-26 23-25 22-24 21-23 20-22 19-21 18-20 17-19
7
upgrade 610–810
3U
11-13
10-12
9-11
8-10
7-9
6-8
5-7
4-6
3-5
8EPC 450 + Exp Draw. 10U
9EPC 450 5U
10 Exp Drawer 450 5U
11 EPC 440 Add’l 8U
12
SPS/DAS 5300/ 2DAE
5000
13U
13
SPS/DAS 5300/ 1DAE
5000
9U
14
SPS/DAS 5300
5U
23-27
26-30
28-32
31-35
15 LXB 4000/7000 4U 24-27 23-26 22-25 21-24 20-23 19-22 18-21 17-20 16-19
16 DLT 4000/7000 4U 24-27 23-26 22-25 21-24 20-23 19-22 18-21 17-20 16-19
17 VDAT Mammoth 3U 25-27 24-26 23-25 22-24 21-23 20-22 19-21 18-20 17-19
18 SPS/DPE5700/4500
7DAE5000
36U
19 SPS/DPE5700/4500
6DAE5000
32U
20 SPS/DPE5700/4500
5DAE5000
28U
21 SPS/DPE5700/4500
4DAE5000
24U
22 SPS/DPE5700/4500
3DAE5000
20U
23 SPS/DPE5700/4500
2DAE5000
16U
24 SPS/DPE5700/4500
1DAE5000
12U
25 SPS/DPE5700 8U
26 DAE5000 4U 10-13 11-14 12-15 13-16 14-17 15-18 16-19 17-20 18-21
27 FC–AL Hub/ Vixel 1U positions 1–1 to 36–36
28 Console Concent. &
ClusterHub
4U 10-13 11-14 12-15 13-16 14-17 15-18 16-19 17-20 18-21
29 Console Concent. 4U 10-13 11-14 12-15 13-16 14-17 15-18 16-19 17-20 18-21
30 Switch FC 8–Port 1U positions 1–1 to 36–36
31 Switch FC16–Port 2U 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10
32
Switch Fast Ethernet
2U
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
33
Switch Gbit Ethernet
2U
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
34
Cluster Hub
2U
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
35
Cons. Conc 16–Port
2U
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
36
Cons. Conc & Cluster
Hub
2U
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
37 Bridge FC 1U positions 1–1 to 36–36
38 Rack Content Specify 7U 10-16 11-17 12-18 13-19 14-20 15-21 16-22 17-23 18-24
39 Rack Content Specify 4U 10-13 11-14 12-15 13-16 14-17 15-18 16-19 17-20 18-21
40 Rack Content Specify 3U 10-12 11-13 12-14 13-15 14-16 15-17 16-18 17-19 18-20
41
Rack Content Specify
2U
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
42 Rack Content Specify 1U positions 1–1 to 36–36
Table 6. Drawer priority and positions in the rack 19 to 27

1-12 Installation Procedures for Drawers
Prior-
ity
Drawer Height 19th
Pos.
20th
pos.
21th
Pos.
22nd
Pos.
23rd
pos.
24th
pos.
25th
pos.
26th
pos.
27th
pos.
1PDU 450 2U
2I/O Drawer 10U
3EPC610 CEC+I/O 10U
4EPC810 CEC+I/O 13U
5Secondary I/O Drawer 5U 10-14 9-13 8-12 7-11 6-10 5-9 4-8 3-7 2-6
6Disk Drawer 3U 16-18 15-17 14-16 13-15 12-14 11-13 10-12 9-11 8-10
7
upgrade 610–810
3U
2-4
1-3
8EPC 450 + Exp Draw 10U
9EPC 450 5U
10 Exp Drawer 450 5U
11 EPC 440 Add’l 8U
12
SPS/DAS 5300/ 2DAE
5000
13U
13
SPS/DAS 5300/ 1DAE
5000
9U
14
SPS/DAS 5300
5U
15 LXB 4000/7000 4U 15-18 14-17 13-16 12-15 11-14 10-13 9-12 8-11 7-10
16 DLT 4000/7000 4U 15-18 14-17 13-16 12-15 11-14 10-13 9-12 8-11 7-10
17 VDAT Mammoth 3U 16-18 15-17 14-16 13-15 12-14 11-13 10-12 9-11 8-10
18 SPS/DPE5700/4500
7DAE5000
36U
19 SPS/DPE5700/4500
6DAE5000
32U
20 SPS/DPE5700/4500
5DAE5000
28U
21 SPS/DPE5700/4500
4DAE5000
24U
22 SPS/DPE5700/4500
3DAE5000
20U
23 SPS/DPE5700/4500
2DAE5000
16U
24 SPS/DPE5700/4500
1DAE5000
12U
25 SPS/DPE5700/4500 8U
26 DAE5000 4U 19-22 20-23 21-24 22-25 23-26 24-27 25-28 26-29 27-30
27 FC–AL Hub/ Vixel 1U positions 1–1 to 36–36
28 Console Concent. &
ClusterHub
4U 19-22 20-23 21-24 22-25 23-26 24-27 25-28 26-29 27-30
29 Console Concent. 4U 19-22 20-23 21-24 22-25 23-26 24-27 25-28 26-29 27-30
30 Switch FC 8–Port 1U positions 1–1 to 36–36
31 Switch FC 16–Port 2U 19-20 20-21 21-22 22-23 23-24 24-25 25-26 26-27 27-28
32 Switch Fast Ethernet 2U 19-20 20-21 21-22 22-23 23-24 24-25 25-26 26-27 27-28
33 Switch Gbit Ethernet 2U 19-20 20-21 21-22 22-23 23-24 24-25 25-26 26-27 27-28
34 Cluster Hub 2U 19-20 20-21 21-22 22-23 23-24 24-25 25-26 26-27 27-28
35 Cons. Conc 16–Port 2U 19-20 20-21 21-22 22-23 23-24 24-25 25-26 26-27 27-28
36 Cons. Conc & clust.
Hub
2U 19-20 20-21 21-22 22-23 23-24 24-25 25-26 26-27 27-28
Other manuals for ESCALA Series
1
This manual suits for next models
2
Table of contents
Popular Rack & Stand manuals by other brands

Factoryfurniture
Factoryfurniture Murton Operation & maintenance manual

VOGELS
VOGELS PFA 9033 Mounting instructions

Rack Solutions
Rack Solutions 122-3491 installation instructions

CORAB
CORAB WS-004M installation manual

Omnimount
Omnimount OMNI 25.0C instruction manual

VOGELS
VOGELS W5208 Series Mounting instructions