SpaceKeeper Console (SKC) –Installation Operation Maintenance Manual 6
© Copyright 2013 CGC Group Inc. Installation Operation Maintenance Manual is Subject to Change without Notice Last Revised Nov 15, 2019
6. Slide Console cabinet lip over the hanging strip. Hanging strip ensures console unit is
held flush against the wall and to prevent the unit from tipping. It is not meant to carry
the weight of the unit. It is the responsibility of the installers to make sure the unit
weight is supported by the floor. See Drawing 2
7. The electrical receptacle outlet that may be included as part of the optional Piping-and-
Receptacle Plate must be preinstalled in the designated cavity. See Figure 1 Piping and
Receptacle Plate (optional). Note the electrician must take out the outlet and reinstall
after wiring. For receptacle and box supplied by others, the installer must ensure the
electrical box is installed within reach of the console unit’s power plug. See Drawing 3
8. Firmly grasp the front panel cover of the console and remove it by lifting it up and away
from the heat pump unit.
9. For the console to be properly connected to the supply, return and condensate pipes
the unit must be located in a position where these pipes are easily accessible through
the black mounting base with the front panel removed.
10. With the front panel cover removed, locate the three fluid hoses that are attached to
the unit’s supply, return, and condensate connections. Carefully remove these hoses.
The heat pump end of the supply and return hoses have swivel connectors. The
condensate hose has a hose clamp.
11. Permanently affix the threaded end of the supply and return hoses (NOT the swivel
connector) to the building’s supply and return lines which protrude through the back
mounting base. Ensure that the supply and return pipes have isolation valves.
12. The three hoses that have been affixed to the building’s supply, return, and
condensate piping should at this point be accessible through the bottom of the heat
pump unit. Using the swivel connectors, re-connect the supply and return hoses to the
appropriate locations on the heat pump unit. Attach condensate hose to drain pan of
unit and attach with hose clamp provided.
13. Ensure that the condensate drain connection is positioned so that there is adequate
Stem height to generate a water seal when the fan is operating on high speed. This
should be approximately 2”. See below. Slide condensate hose over condensate line
and attach with hose clamp supplied.
14. Connect the room thermostat to the electrical panel as indicated on the wiring
diagram. For thermostat wiring, see Drawing 4. Plug the unit’s electrical cord into
the supply outlet that is located behind the unit.