
10
TEMPORARY HEATING ORCOOLING
Iftheunitistobeusedfortemporaryheatingorcooling,a“Startup,
Adjustments, and Checks” must first be performed in accordance
withthismanual.Failuretocomplywiththisrequirementwillvoid
the warranty. After the machines are used for temporary heating
or cooling, inspect the coils, fans, and motors for unacceptable
levels of construction dust and dirt and install new filters.
CONTRACTOR RESPONSIBILITY
The installing contractor must be certain that:
• All supply and return air ductwork is in place, properly
sealed and corresponds with installation instructions.
• All thermostats are mounted and wired in accordance
with installation instructions.
• All electric power, all gas, hot water or steam line
connections, and the condensate drain installation have
been made to each unit on the job. These main supply
linesmustbefunctionalandcapableofoperatingallunits
simultaneously.
• All filters are in place.
ROOF CURB INSTALLATION CHECK
Inspect the roof curb for correct installation. The unit and curb
assembly should be level. Inspect the flashing of the roof mount-
ing curb to the roof, especially at the corners, for good workman-
ship. Also check for leaks around gaskets. Note any deficiencies in
a separate report and forward to the contractor.
OBSTRUCTIONS, FAN CLEARANCE AND WIRING
Remove any extraneous construction and shipping materials that
may be found during this procedure. Rotate all fans manually to
check for proper clearances and that they rotate freely. Check for
bolts and screws that may have jarred loose during shipment to
the job site. Retighten if necessary. Re-tighten all electrical con-
nections.
FIELD DUCT CONNECTIONS
Verify that all duct connections are tight and that there is no air
bypass between supply and return.
FILTER SECTION CHECK
Removefiltersectionaccesspanelsandcheckthatfiltersareprop-
erly installed. Note airflow arrows on filter frames.
PRE-STARTUP PRECAUTIONS
It is important to your safety that the unit has been properly
groundedduringinstallation.Check groundlugconnectioninmain
control box for tightness prior to closing circuit breaker or discon-
nect switch. Verify that supply voltage on line side of disconnect
agrees with voltage on unit identification plate and is within the
utilizationvoltagerangeasindicatedinAppendixCElectricalData.
System Voltage - That nominal voltage value assigned to a circuit
or system for the purpose of designating its voltage class.
Nameplate Voltage - That voltage assigned to a piece of equip-
ment for the purpose of designating its voltage class and for the
purposeof defining the minimumand maximumvoltageatwhich
the equipment will operate.
UtilizationVoltage-Thevoltageofthelineterminalsoftheequip-
ment at which the equipment must give fully satisfactory perfor-
mance. Once it is established that supply voltage will be main-
tained within the utilization range under all system conditions,
check and calculate if an unbalanced condition exists between
phases. Calculate percent voltage unbalance as follows:
Three Phase Models Only
3) PERCENT VOLTAGE
UNBALANCE
2) MAXIMUM VOLTAGE DEVIATIONS
FROM AVERAGE VOLTAGE
1) AVERAGE VOLTAGE
HOW TO USE THE FORMULA:
EXAMPLE: With voltage of 220, 216, and 213
1) Average Voltage = 220+216+213=649 / 3 = 216
2) Maximum Voltage Deviations from Average Voltage = 220 - 216 = 4
3) Percent Voltage Unbalance = 100 x = = 1.8%
Percent voltage unbalance MUST NOT exceed 2%.
4
216 400
216
= 100 X
AIRFLOWADJUSTMENTS
NOTE:For2 SpeedModels,airflowadjustmentsmustbemadeon
high speed, i.e., 2nd stage cooling or in heat mode.
The drive on the supply fan is typically set in the middle of the
RPM range. The drive motor sheave pitch diameter is field adjust-
able for the required airflow. Refer to the following “Drive
Adjustments” section.
Whenthefinaladjustmentsarecomplete,thecurrentdrawofthe
motor should be checked and compared to the full load current
rating of the motor. The amperage must not exceed the service
factor stamped on the motor nameplate. The total airflow must
notbeless than thatrequired foroperationoftheelectric heaters
or the furnace.
Ifaneconomizerisinstalled,checktheunitoperatingbalancewith
theeconomizeratfulloutsideairandatminimumoutsideair. Upon
completion of the air flow balancing, we recommend replacing
the variable pitched motor sheave with a properly-sized fixed
sheave.Amatchingfixedsheavewillprovidelongerbeltandbear-
ing life and vibration free operation. Initially, it is best to have a
variable pitched motor sheave for the purpose of airflow balanc-
ing, but once the balance has been achieved, fixed sheaves main-
tain alignment and minimize vibration more effectively. For direct
drive units, move green wire for fan.
NOTE:On“non-twospeedmodels”(two-speedmodelshavea“V”
in the eleventh character of the model number), never run CFM
below 300 CFM per ton. Evaporator freezing or poor unit perfor-
mance is possible.
SET EVAPORATOR FAN RPM
ActualRPM’smustbesetandverifiedwithatachometerorstrobe
light. Refer to Appendices A and B for basic unit fan RPM. Refer
also to “Airflow” section of this manual. With disconnect switch
open, disconnect thermostat wires from terminals Y and W. This