9910045 RevG April 2021
Introduction
The clawFR 10 Degree flat roof mounting system is comprised of
four major components that intuitively assemble into a support
structure for photovoltaic (PV) modules.
This installation manual explains how to build a PV array using
clawFR 10 Degree.
PAGE 2
A CORROSION INSPECTION ONE YEAR AFTER INSTALLATION
AND ONCE EVERY THREE YEARS THEREAFTER IS REQUIRED
TO MAINTAIN THE PRODUCT WARRANTY. VISIBLE SURFACE
RED RUST ON STEEL COMPONENTS MUST BE LOCALLY
COATED WITH A COMMERCIALLY AVAILABLE GALVANIZED
PAINT OR COATING TO MAINTAIN PRODUCT WARRANTY.
EXCEPT FOR DEFLECTORS, ALL RACKING COMPONENTS IN
EACH SUBARRAY AND THEIR CONNECTIONS, BALLAST, AND
MECHANICAL ATTACHMENTS (IF ANY IN DESIGN) MUST BE
INSTALLED BEFORE MOUNTING MODULES. WHEN
FORECASTED WIND GUSTS EXCEED 25%OF THE WIND
SPEED LISTED IN THE SITE CRITERIA TABLE OF THE RACKING
CONSTRUCTION SET, DEFLECTORS MUST BE INSTALLED ON
ALL MOUNTED MODULES TO AVOID POSSIBLE SYSTEM
DAMAGE.
Safety Overview
Safety is an essential part of every PV installation and every
construction site. It is imperative to plan ahead for any safety
concerns and hazards to promote safe work practices during
installation. This section does not claim to address or support all
safety concerns that may arise during the installation of PanelClaw
mounting systems or any other aspect of the work being
performed. Before beginning work, installers should refer to all
local and federal safety, health, and regulatory requirements to
assure compliance. Refer to OSHA Part 1926 and its related
Subparts for federal construction related regulations and
standards.
Appendix J: Safety outlines some of the major hazards to be aware
of during the installation of PanelClaw products.
PRIOR TO INSTALLATION, READ THE SAFETY PROVISIONS
ATTACHED IN Appendix J: Safety AND REVIEW THIS
INSTALLATION MANUAL IN ITS ENTIRETY.