Period of warrantee is 60 and 12 months, it starts from the date of sale.
The warrantee is on:
water block of boiler - 60 months;
durable and efficient working mechanical devices, electric and electronic fireplace - 12 months.
Seller confirms warrantee for boiler by stamp, date of sale as well as signature, and also by report of
first boiler start of operation that should be correctly filled, signed and sent to Producer.
The manufacturer is obliged to fulfil warrantee repair in 14 days deadline from date of notification by
Buyer that boiler needs to be repaired.
Buyer can claim warrantee rights in court in case when Producer will not fulfil their warrantee
obligations.
The warrantee authorization in order to fulfil warrantee repair is a free document. Warrantee is not
valid without stamp, person's signature and selling dates as well as without stamp, Producer’s
signature and date. In case of loss of warrantee document, the duplicates will be given –are to be
paid for.
Warrantee stops to be valid in case of not proper installation of the boiler and application of safety
means non-complying with local and state law regulations and standards described in PN -91 / B -
02413, PN -99 / B -02414.
Regarding complaints Producer is to be notified by sending a full reclamation report to Producer’s
address, stamped by sales department, responsible for service. If complaint will turn out to be
groundless, all costs connected with arrival of manufacturer's representative should be covered by
person that placed claim.
Please remember, before cleaning smoke tubes, remove upper plate of burner
(building of burner).
Cast iron grate which is the balton of the burner isn’t subject of the guarantee.
Any alterations, and change of constructional modifications of Boiler cause
immediate loss of the manufacturer's warrantee.
Alteration and starting of Boiler should be fulfilled with suitable authorizations in
this range.
Chamolte brick and heat resisting plate located on the burner aren’t subject of the
guarantee
page 22
Central heating boiler FUWI on Pellets is ready for independent work after loading of tank by
granulate fuel - Pellets and after temperature of boiler is displayed on control panel. While
granulate fuel-pellets from tank dose to burner, it lights automatically, and then according to
demand ( the achievement or maintenance of set temperature) it doses for burner the next
portion of solid fuel from tank.
You should periodically load reservoir with pellets and clean up from dust gathered during work.
There is possibility of placing additional container of granulate fuel but in considerable distance from
boiler also, which requires modernization in the way of installation of additional device for pellets
passing.
Automatic burning process of pellets as well as state of hearth are controlled by photodiode (probe
of clearness), airs as well as burner spark are equipped buy regulated electric blower for automatic
lighting of pellets simultaneously.
The exploitation of Boiler, standard version:
During exploitation of boiler you should remember about cleaning the burner and chamber of burning
from chamber of ash-pan, that are in bottom unit of boiler, at least once a week, and fill up boiler
tank with fuel. Cleaning should be made while removal of covering as well as cleaning around. Using
arm placed on the boiler exhaust vanes are cleaned. By multiple, energetically pulling the arm down
, is followed the movement of the steering wheel, thereby pollutants are discharged into the furnace
chamber. You should remember about cleaning of smoking pipes that are in upper unit of boiler at
least once a month. Cleaning is made by removal dust covering with help of steel brush (rifle
cleaning-brush). Below burning chamber there is chamber of ash-pan to which after burning solid
fuel goes as accompanied ash. Chamber of ash-pan should be periodically emptied from dust and
ash with help of furnace rake.
Making any work in range of cleaning as following: burner, ash-pan as well as
smoke pipes, remember to make sure that there is no access to open fire.
Minimal temperature of heating factor return: 50oC.