GENERAL
CONTENTS
Air Supply........................................................................8
Boiler Clearances...........................................................4
Boiler Exploded Diagram ..............................................7
Electrical Connections ................................................18
Electrical Supply.............................................................6
Fault Finding .................................................................29
Flow Wiring Diagram ...................................................18
Flue Installation ..............................................................9
Gas Safety (Installation & Use)
Regulations, 1994 or 1996 .............................................2
Gas Supply......................................................................6
Health & Safety Document No 635...............................3
Installation ......................................................................9
Mandatory Requirements..............................................2
Pump .............................................................................16
Servicing .......................................................................23
Short List of Parts ........................................................34
Water Connections ........................................................4
Water and Systems ........................................................5
Wiring Diagrams...........................................................18
INTRODUCTION
OPTIONAL EXTRA KITS
Roof Flue Kit 80/125 For vertical flue connection.
Roof Flue Kit 100/150 For vertical flue connection.
Pitched and flat roof tiles 125 & 150
For all vertical flue options’.
Vertical Twin Pipe Roof Kit 80/125
For vertical flue connection.
Vertical Twin Pipe Roof Kit 100/150
For vertical flue connection.
Horizontal Wall Flue Kit 80/125
For horizontal flue connection.
Horizontal Wall Flue Kit 100/150
For horizontal flue connection.
Sequence Control MBC 5 For control of more than one boiler.
Remote Indication alarm kit
For volt free contacts
2 Boiler Frame Kit For double boiler application.
3 Boiler Frame Kit For triple boiler application.
GAS SAFETY (INSTALLATION AND USE)
REGULATIONS, 1994 OR 1996 (AS AMENDED)
It is law that all gas appliances are installed and serviced by a
CORGI registered installer in accordance with the above
regulations. Failure to install appliances correctly could lead to
prosecution. It is in your own interest, and that of safety, to
ensure the law is complied with.
The installation of the boiler MUST also be in accordance with
the latest l.E.E Wiring Regulations, local building regulations,
bye-laws of the local water authority, the building regulations
and the Building Standards (Scotland) and any relevant requi-
rements of the local authority.
Detailed recommendations are contained in the following
British Standard Codes of Practice:
BS. 6891 Low pressure installation pipes.
BS. 6798 Installation of gas fired hot water boilers of rated
input not exceeding 60 kW.
BS. 5449 Forced circulation hot water systems.
BS. 5546 Installation of gas hot water supplies for
domestic purposes (2nd Family Gases)
BS. 6644 Ventilation (for gas appliances of rated input
exceeding 60 kW)
BS. 5440:2 Ventilation (for gas appliances of rated input not
exceeding 70 kW net.)
BS. 5440:1 Flues (for gas appliances of rated input not
exeeding 60 kW)
BS. 4814 Specifications for expansion vessels
Health & Safety document no 635
The Electricity at Work Regulations, 1989
Maximiser SE - Installation 2
Maximiser SE boilers are fully automatically controlled, wall
mounted, low water content, balanced flue, fanned super
efficient condensing gas boiler.
The Maximiser SE condensing boilers can be installed either
on the wall or into a prefabricated floor mounted frame.
The boilers are suitable for use with a room sealed flue or
open flued application.
Through a sophisticated control system combined with premix
burner arrangement the boilers are capable of high operating
efficiencies of 94% and low emissions.
The heat exchanger is manufactured from extruded aluminium
finned tubes sealed into aluminium end plates.
Note. These boilers cannot be used on systems which include
gravity circulation.
The boilers are suitable for connection to fully pumped, open
vented or sealed water systems. Adequate arrangements for
completely draining the system by provision of drain cocks
MUST be provided in the installation pipework.