In-Ground Trampolines IGT Site Preparation 15' User manual

Step 1: IGT Site Preparation 15’
Site Location
Several factors must be considered when choosing the site for your new In-Ground Trampoline (IGT) system. Since
local soil and weather conditions vary greatly from region to region, it is recommended that a local landscape expert be
consulted for placement of the system.
A minimum of 12 feet of overhead clearance and 5 feet of clearance from the trampoline to other objects on the ground
is recommended for the jumpers protection.
Using impact-absorbing ground cover such as grass, sand or bark chips is recommended for 4-6 feet around the
trampoline.
Drainage
Drainage is not a problem with our In-Ground Trampoline system.
It is recommended to leave 2-4 inches of the trampoline above the final grade and gradually berming the soil up to the edge
of the trampoline. This will keep water from flowing into the pit in the event of heavy rain. Depending on local soil
conditions you may consider adding 4 to 6 inches of rock into the bottom of the pit, creating a sump effect to prevent
standing water. You will need to excavate the center of the pit deeper at the same depth as the rock you intend to add.
Extreme conditions may require additional drainage methods or the use of a sump pump. It is always a good idea to consult a
local landscaper regarding local soil conditions and drainage for your area.
The Pit
The IGT system is designed to be installed partially or completely recessed in the ground.
Either way, the pit will need to be excavated to a diameter of at least 16 feet 4 inches. If the IGT system must be assembled
in the pit due to size constraints of the yard, a 17 foot pit is recommended for easier access to assembly hardware.
For a completely recessed system we recommend the excavation of the pit depth be 16-18 inches deep around the edges and
30 inches in the center. See below for Pit Dimensions. The system is a total of 20 inches tall so this allows for the
trampoline to remain at least 2-4 inches above the grade as recommended in the Drainage section.
For a partially recessed system, the dirt excavated from the pit can be used to build up the area around the installation.
Excavating the pit to a depth of 8 inches leaves 12 inches of the system exposed. This method eliminates the need for
removing excavated soil from the property.

Very Important Instruction Tips For Proper Installation
-The IGT system must be set above the grade of the yard to prevent water from collecting in the
trampoline pit.
-The IGT frame must be completely level and round before and during the backfilling process.
-Soil compaction must be done evenly during backfill process.
-Backfill to the top of the IGT frame. Do not allow wall panels to be exposed.

Details on Trampoline Installation Depth
The IGT system is a total of 20 inches tall. Excavation to a depth of 16-18 inches will leave the frame 2-4 inches above
the yard grade. This will keep water out of the IGT system. In order to have the trampoline appear to be flush in the
yard, simply use excavated soil to create a berm up to the edge of the frame. See diagram.


Step 2: Lay Out Parts
Parts list
Quantity
15 Foot __________________________Description_________
15 Top Frame Segments (with spring holes)
15 Bottom Frame Segments (without spring hole)
15 Wall Panels
15 Rubber Edge Protector Strips
1 Pad Set
1 Jumping Surface
120 Springs
60 Bolts
60 Nuts
120 Washers
30 Protective Plastic Bolt Caps
1 Tool Kit

Lay Out Parts for Easy Installation
Lay out parts as shown to simplify assembly of the frame. Use one of the shipping boxes to separate all the hardware.
Step 3: Frame Assembly
Tips
-Our parts are machine stamped and drilled and therefor can have burrs. We work hard to make sure all parts are
smooth but there is a chance there could be a sharp edge. We recommend using gloves during the assembly
process.
-Use the assembled lower frame ring as a template to help locate and mark for
pit excavation.
-Assembly should occur next to the excavated pit. If there is no room for assembly close to the pit, it can be
assembled in the pit however it is recommended to excavate the diameter of the pit to 14 feet for easier access
to the hardware.
-Be sure the spring holes on the top frame tube segments are facing up.
-Leave all bolts loose to allow movement of the components during assembly for easier bolt hole alignment.
-Unless you are on a perfectly level surface for assembly, some holes may be difficult to line up. Use a long
screwdriver to help locate and align holes

Step A: Assemble lower frame ring section.
Assemble lower ring (frame tubes without spring holes) using the 15 lower frame tube segments.
Step B: install rubber protective strips
Locate the 15 black rubber protective strips and apply them to the top edge of each wall panel.

Step B: Join the wall panels to the lower frame.
We recommend the assistance of a helper for this stage of the assembly, one person to hold the panels and another to
install the hardware. Use the supplied “T” handled hex key to help push the bolts through the wall and frame.
Using the center hole, attach one of the wall panels to the lower ring using a bolt with a washer on the wall side and a
washer and locking nut on the tube side. Then add a second panel, overlapping the first panel and bolt that onto the
lower ring. Add a third panel. Do not tighten the bolts at this time.
Step C: Join the upper frame segments to the wall panels.
Join one of the upper frame segments (with spring holes) to any wall panel using a bolt and washer on the panel side
and a nut and washer on the frame side. Continue adding upper frame segments and wall panels all the way around the
bottom ring.


Step D: Complete the frame assembly.
The final wall panel and upper segment installation may require lifting and/or shifting the frame. This is why the bolts
should be left loose until the frame is completed. Be sure all edge protectors are properly seated then tighten the
hardware. Place the protective plastic caps onto the top ring exposed bolt threads.
The Frame is now complete

Step 4: Position Frame Assembly into Pit
Install
The frame can now be placed into the excavated hole. The completed frame weighs 335 lbs. (15’) and will require 3 to
4 adults to position the frame into the pit. Do not force the frame into a pit that is not excavated to spec. This could
cause the frame to take on an oblong shape. If the frame does not fit into the pit without touching the pit walls the
frame must be removed and the pit must be reshaped to allow the frame to be placed into the pit without force. Be sure
that the portion of the pit where the trampoline will be placed is completely flat and as level as possible. This will make
final leveling much easier.
Level Frame and Check for Roundness

Very Important!
A level and round frame is important for best performance and safe trampoline use. The best way to level the frame is
with a laser level or transit. A string level can be used as well. We recommend you using at least 4 strings to get the
frame as level as possible. Shims can be used under the edge of the frame to help level the trampoline until backfill
process is compete. You can use scraps of wood, tile or bricks as shims. Small squares of plywood work great. It is
critical that the frame is round. Measure the diameter at every other bolt to make sure it is as round as possible. Make
sure there is no more that 1 ½inches of variance. You can push and pull on the frame to adjust the shape.
Backfill and Compact
Backfill the outside of the frame assembly using the excavated soil. It is not necessary to backfill the inside of the
frame. Try to use loose dirt free of large clumps. It is critical to back fill evenly to avoid pushing the frame out of
round. For best results add 6-8 inches of dirt all the way around the frame and compact. Check for roundness during the
backfill process to make sure the frame stays good and true. Keep evenly adding layers of dirt and compacting until the
dirt is flush with the top of the frame. The final landscape can be finished at this point if desired or later. It is important
to have the final surface, whether it is grass or mulch etc, at the same level as the top of the frame. The wall panels
should not be exposed. For a good flush look, you may need to start the backfill up to the edge of the frame from 2-3
feet away from the trampoline gradually sloping up from the existing yard grade up to the top of the frame.

Step 5: Install Jumping Surface
Attach Every 4th Spring
Start at any point attaching every 8th spring from the frame to the rings on the jump mat, skipping 7 holes on the frame
and 7 D-rings on the mat. Hook the spring onto the jump mat D-ring first and then into the hole on the frame. You can
use another spring as a spring tool to help stretch the springs into place.
It is very important to attach springs in the correct pattern. Be sure the D- ring on the jump mat is oriented properly.
NO!


Next, attach every 4th spring.

Next, attach every 2nd spring.

Make sure the springs already attached are correct. There will be a frame hole and mat ring for each spring. After the
pattern is confirmed correct, attach the rest of the springs to the frame and mat.

Step 6: Attach pad
Edge protector
Before installing pads, make sure the Edge Protector is properly in place
Install pad
It is important to make sure the pad is properly attached so that the springs and frame components are always covered.
Correct bungee placement is critical to make sure the pad is centered properly on the frame.
The Next Gen frame has gaps built into the wall panels that allow the bungees to be secured to the frame. Start at any
of these gaps for the first attachment. The next attachment point will be 10 springs away where there will be another
gap. See the diagram below. The red markers indicate where the pad bungees should be placed.

Start with the pad folded on top of the IGT frame. Locate the small fabric strap loop on the bottom seam of the pad.
Slide one of the bungees through the loop from the inside to the outside. Push the bungee between the wall panel
and the frame tube and wrap it around the frame tube and over the ball on the end of the bungee securing it in place.

Install IGT Silencers
Your IGT system comes with a set of foam cylinders install on the springs that are designed to prop up the pad slightly
increasing airflow and decreasing the noise from the pad as you bounce.
Once the first pad bungee has been placed you can now add the Silencers. Remove the 3rd spring away from the bungee,
slide that spring through the center hole in the Silencer. Use another spring to help grab the spring hook inside the
Silencer and stretch the spring back into place.
Table of contents
Other In-Ground Trampolines Sport & Outdoor manuals
Popular Sport & Outdoor manuals by other brands

Tour Links
Tour Links Backyard Golf Prestwick owner's manual

Air Structures International
Air Structures International IGOAL Step-By-Step Instructions

Avyna
Avyna Model 08 quick start guide

SKLZ
SKLZ PRACTICE PLAY WIN QUICKSTER Setup instructions

BAT
BAT LOGIC QuickRelease System Fitment Guide

Premier Kites
Premier Kites Skeleton 13 ft Assembly instructions