manuals.online logo
Brands
  1. Home
  2. •
  3. Brands
  4. •
  5. Navien
  6. •
  7. Rack & Stand
  8. •
  9. Navien Ready-Link-Rack User manual

Navien Ready-Link-Rack User manual

1
2
3
4
Included Items
When you open the box, you will nd the following items. Check the box for each of the following items before assembling the Ready-
Link-Rack. The quantity of each item diers depending on the number of water heaters or boilers you want to install.
If any of these items are missing or damaged, please contact our customer service center at 1-800-519-8794.
Installation Guide Post bar 64.4 in Fixed bar 17.7 in Base frame 32 in Fixed bracket
(under)
Fixed bracket
(middle)
Fixed bracket
(upper)
1 EA * Single kit: 2 EA
** Extension kit: 1 EA
* Single kit: 2 EA
** Extension kit: 2 EA
* Single kit: 2 EA
** Extension kit: 1 EA
* Single kit: 4 EA
** Extension kit: 2 EA
*Single kit: 4 EA
**Extension kit: 4 EA
*Single kit: 2 EA
**Extension kit: 2 EA
Reinforcement
plate
Tapping screw 5x12
(washers set, stainless steel)†
Tapping screw 5x12
(stainless steel)†
M10 bolt
(3 in, stainless steel)
M10 bolt
(2.8 in, stainless steel)
5/32 in or
4 mm Allen wrench
* Single kit: 4 EA
** Extension kit: 2 EA
* Single kit: 20 EA
** Extension kit: 12 EA
* Single kit: 2 EA
** Extension kit: 2 EA
* Single kit: 22 EA
**
Extension kit: 14 EA †
* Single kit: 3 EA
** Extension kit: 3 EA
1 EA
† Spare tapping screws are provided in the product package for your convenience.
† All 14 M10 bolts (3 in) of the extension kit will be used for the NFC series when installed in combination with the NPE, NCB, and NFB series.
Other congurations will have one bolt left over.
† The 5x12 tapping screws without washers are only used for installing the NPN series.
* A single kit can be used to mount up to 2 water heater or boiler units. When mounting 2 units, the back-to-back conguration can be used.
** An extension kit is used to add more water heater or boiler units to the frame.
*** These kits can be installed both indoors and outdoors.
Note Although the oor mounting hardware is not included with this kit, you must x the Ready-Link-Rack securely to the oor to
complete installation. Use appropriate anchor bolts (3/8 in) to x the frame to the ground.
Installation Considerations
Refer to the following information to nd an adequate
installation location for the frame and prepare the appropriate
tools to assemble the frame.
Tools required
-5/32 in or 4 mm Allen wrench
-Adjustable wrench
-Level
Dimensions
The following diagram shows the dimensions of the frame.
Install the frame in an area that allows for service and
maintenance access to utility connections, piping, lters, and
traps.
Unistrut mount holes
(3/8 in diameter)
32 in
20 in
20 in
65.5 in
Additional
hole for
extra support
Parts Diagram
The following diagram allows you to correctly identify each part for easy assembly.
A
B
C
1
4
2
5
8
6
7
3
9
Part list
No. Descriptions of parts
1Fixed bar 17.7 in
2Post bar 64.4 in
3Base frame 32 in
4Fixed bracket (upper)
5Fixed bracket (middle)
6Fixed bracket (under)
7Reinforcement plate
8Tapping screw (washers set, 5x12)
9M10 bolts (3 in)
Ready-Link-Rack
Installation Guide(V3)
Model
NPE-A, NPE-S Series
NCB-E Series
NHB Series
NFB-175, 200
NFC-175, 200
NPN Series
WARNING
If the information in these instructions is not followed
exactly, a re or explosion may occur and potentially cause
property damage, personal injury, or death.
Keep this manual for future reference.
The water heater or boiler units can be mounted using the in-
line or back-to-back setup.
In-line Setup Back-to-back Setup
Note Depending on the number of the water heater
or boiler units, assemble the extension kits to the
rack to add more installation space.
5
6
7
8
Attaching an extension kit
Refer to the instructions on pages 5 to 8 to connect an
additional extension rack to the single frame with the xed
brackets and M10 bolts (3 in).
CAUTION
Check the surfaces of the water heater/boiler and rack
for any scratches or chipping paint. If any of the coating
is removed, rust may develop and possibly aect the
lifespan of the rack. Recoat any areas where the coating is
removed or scratched.
Attaching a water heater or boiler to the frame
For the NHB/NPE/NCB/NFB/NFC Series:
1. Align the grooves on the back of the water heater
or boiler with the tongues on the mounting bracket
and hang the water heater or boiler on the bracket.
2. Secure the water heater or boiler to the frame
with the M10 bolt set (2.8 in).
2
1
1
For the NPN Series:
2
3
1
1. Hang the NPN water
heater's upper mounting
bracket on the tapping
screw (5x12).
2. Ax the bracket using
two M10 bolts (2.8 in).
3. Secure the water heater to the
middle xed bar through the
NPN bracket at the bottom of
the water heater with one M10
bolt set (2.8 in).
Assembling the middle bar
CNHB/NPN series
NFC series
NFC series
NPE/NCB/
NFB series
NHB/NPE/NCB/
NFB/NPN series
Place a xed bar between the middle of the
2 post bars and 4 xed brackets (middle) with
6 M10 bolts (3 in) to attach the middle bar.
Note
Depending on the boiler or water heater
models, the screws and bolts are tightened
to the dierent holes of the post bar and
xed brackets (middle) dierently. Refer to
the following illustrations for the proper
hole locations used for each model.
●NHB/NPN
series
●NPE/NCB/
NFB series
●NFC series
Fixing the frame to the location
1. Ensure that all screws and bolts are tightened securely.
2. Fix the frame to the ground with appropriate anchor bolts.
WARNING
●Ensure that the oor is at and strong enough to support the
water heater or boiler and frame when all preparations for
operation are complete.
●Ensure that the frame is xed securely as property damage,
personal injury, or death may result if the frame falls.
Note Although the oor mounting hardware is not included with this kit, you must x the Ready-Link-Rack securely to the oor
to complete installation. Use appropriate anchor bolts (3/8 in) to x the frame to the ground. Before xing the frame to the
ground using anchor bolts, ensure that the anchor bolts protrude above the surface of the ground by at least 2 in (50 mm).
Assembling the upper bar
NPN Series
B
NHB, NPE, NCB, NFB, NFC Series
For the NHB, NPE, NCB, NFB, NFC Series:
1. Place a xed bar between the top of the 2
post bars and ax 2 xed brackets (upper)
with 6 M10 bolts (3 in) to attach the upper bar.
2. Ax the mounting bracket supplied with the
water heater or boiler to the middle of the
upper bar where the product will be attached
with 2 tapping screws (washers set, 5x12) and
2 M10 bolts (2.8 in).
3. Back-to-back Option: To mount water heaters
or boilers using the back-to-back setup, ax
the mounting bracket to the back side of the
upper bar.
For the NPN Series:
1. Place a xed bar between the top of the 2
post bars and ax 2 xed brackets (upper)
with 6 M10 bolts (3 in) to attach the upper bar.
2. Tighten the tapping screw (5x12) to the screw
hole in the middle of the upper xed bar.
Ensure that the screw is not fully tightened so
that the upper mounting bracket of the NPN
water heater can hang on the screw.
3. Back-to-back Option: Repeat step 2 on the
rear side of the xed bar.
Back-to-back
Option
Note The post bar may be damaged if excessive torque is applied when you tighten the M10 bolts. The maximum torque allowed
when tightening the M10 bolts is 10 N-m, or 7 ft-lb.
Installation Procedures
Assembling the foot bar
A
1. Place a base frame on the ground
and place a post bar upright in the
middle of a base frame.
2. Ax 2 xed bracket (under) with
8 tapping tapping screws
(washers set, 5x12).
3. Repeat steps 1 and 2 to make the
second foot bar.
4. Ax 2 reinforcement plates to the
inside and outside of a foot bar
with 5 M10 bolts (3 in).
5. Repeat step 4 for the other foot
bar.
Note The post bar may be damaged if excessive torque is applied when you tighten the M10 bolts. The maximum torque allowed
when tightening the M10 bolts is 10 N-m, or 7 ft-lb.
Navien Inc.
20 Goodyear lrvine, CA 92618
TEL +800-519-8794 FAX +949-420-0430
www.navien.com

Popular Rack & Stand manuals by other brands

Aigis Mechtronics IND6 Series Installation and operating instructions

Aigis Mechtronics

Aigis Mechtronics IND6 Series Installation and operating instructions

skyvoe NXG-46 Assembly manual

skyvoe

skyvoe NXG-46 Assembly manual

Delfield F2000 Series Service, installation and care manual

Delfield

Delfield F2000 Series Service, installation and care manual

BiGDUG BiG400 Guide to Assembly & Usage

BiGDUG

BiGDUG BiG400 Guide to Assembly & Usage

Roland KSC-62 Assembling & installation instructions

Roland

Roland KSC-62 Assembling & installation instructions

TOOLCRAFT 2865850 operating instructions

TOOLCRAFT

TOOLCRAFT 2865850 operating instructions

ENS 367-5472 instruction sheet

ENS

ENS 367-5472 instruction sheet

Westinghouse MT80 THIN Installation and assembly

Westinghouse

Westinghouse MT80 THIN Installation and assembly

Supero M34T user guide

Supero

Supero M34T user guide

Sony SU-PF2 instructions

Sony

Sony SU-PF2 instructions

Westell 28MK2QBK manual

Westell

Westell 28MK2QBK manual

Panasonic ET-JPF200BU operating instructions

Panasonic

Panasonic ET-JPF200BU operating instructions

MSW MSW-EMS-200 user manual

MSW

MSW MSW-EMS-200 user manual

RedNeck RD-STD67BR Assembly instructions

RedNeck

RedNeck RD-STD67BR Assembly instructions

Posture balance Clover Freestand instructions

Posture balance

Posture balance Clover Freestand instructions

Sony XBR-46HX909 - Lcd Panel For Kdl-42xbr950 Tv manual

Sony

Sony XBR-46HX909 - Lcd Panel For Kdl-42xbr950 Tv manual

Premier Mounts Convergent A-A27 Series installation guide

Premier Mounts

Premier Mounts Convergent A-A27 Series installation guide

BGS technic 8380 quick start guide

BGS technic

BGS technic 8380 quick start guide

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.