The periodical controls of the boiler and the burner must be done. If not, the boiler may lose efficiency and the fuel amount
used may increase.
In this manual you will find informations only for the boilers. Please do not forget to get the instruction manual of the burner
that you purchase from the manufacturer of it. Burner is not delivered with the boiler. In this case we do not give any
guarantee for the burner that you purchase. Please get the guarantee certificate for the burner from your supplier.
In the assembling of the boiler; there must be a proper and safe concrete platform for to put the boiler on.
RS series boilers are delivered without burners. For suitable burner selection please get in touch with Rima technicians.
Suitable burners must be selected for taking high efficiency.
If the boiler is stopped automatically because of overheating do not add cold water to the boiler for re-starting. In this case
wait for the boiler to cool down and re- try starting.If it does not start ,please get in contact with technical services.
RS series cast iron boilers are designed for working with hot water heating and/or hot water plumbing and produced with
the proper technology and materials suitable for this design.This design is restricted to use out of it's aim of use.
RS series boilers are delivered as sections and services assemble the boilers in the operation area.The assembling of the
boiler must be made by Rima technical services . Removing or re - assembling of the boiler should also be made by
licensed Rima services, if not the risk of damage is high.
Starting and first operation of the boiler must be made by authorized Rima technicians.
Please be sure that the front door (burner door) for the boiler is strictly closed and burner connections are properly made as
the boiler is working.
The periodical and yearly controls of the boiler must be done properly and on time.Natural gas is a clean fuel and doesn't
make a lot of dirt in the boiler.But the boilers that liquid fuels are used as fuels are much more easily get dirt. Controls and
care operations of the boiler is needed for keeping high efficiency and long life of the boiler.
RS series boilers are produced for heating only. For heating the sanitary water another equipment such as water heater or
heat exchanger is needed.For proper efficiency in this operation,correct water heater or heat exchanger must be selected.
The electricity of the burner and boiler is supplied by city electric network.In this case the electric and lighting systems of the
boiler room, burner and boiler electrical connections, grounding line of control panel and boiler must be made by
professionals under the required and related standards.
In the assembling of the boiler,an empty space must be left from sides for safety requirements and for future repairing
operations.
In summer months, when the boiler is off for a long term, for preventing probable problems with circulation pumps, must
be started 1 -2 times per month for 5 minutes. (The water with chalk can cause problems , if the pump is not used for long
time period.)
Repairing and periodical controls of RS series boilers requires profession.In this manual the responsibilities and required
information for users of the boiler is declared. Besides these declared operations, boiler must not be started by a person
rather than the user or one of our technicians.Please do not try to make adjustment or do not touch any parts of the boilers.
In cleaning, repair and other care operations the original spare parts which approved and manufactured by Rima , must be
used.
The capacity choice of the boiler must be made according to the projects that prepared properly in the terms of related
standards.If not , the boiler efficiency will be low.
Do not add or pump water to the boiler or plumbing system as it is working and hot . For adding water to the boiler or to the
system please wait for water temperature to reach 40ºC. Circulation pump must surely be started while adding water to the
system . If not , the sections may crack.
If the boiler will be kept off for a long time the electric system must be shut down from the main fuse.The electric must be
cut off from the main shelter/fuse as the boiler is in repair,service or cleaning.