manuals.online logo
Brands
  1. Home
  2. •
  3. Brands
  4. •
  5. Seagate
  6. •
  7. Rack & Stand
  8. •
  9. Seagate Exos 2U User manual

Seagate Exos 2U User manual

This manual suits for next models

7

Other Seagate Rack & Stand manuals

Seagate Exos CORVAULT User manual

Seagate

Seagate Exos CORVAULT User manual

Seagate Lyve Mobile Array User manual

Seagate

Seagate Lyve Mobile Array User manual

Seagate Lyve Mobile Array User manual

Seagate

Seagate Lyve Mobile Array User manual

Seagate Lyve Mobile Array User manual

Seagate

Seagate Lyve Mobile Array User manual

Seagate Lyve Mobile Array User manual

Seagate

Seagate Lyve Mobile Array User manual

Seagate Lyve Mobile Array User manual

Seagate

Seagate Lyve Mobile Array User manual

Seagate Lyve Mobile Array User manual

Seagate

Seagate Lyve Mobile Array User manual

Popular Rack & Stand manuals by other brands

Dynex DX-MP3MT Quick setup guide

Dynex

Dynex DX-MP3MT Quick setup guide

Konig & Meyer 24185 manual

Konig & Meyer

Konig & Meyer 24185 manual

ECG LD 326501 instruction manual

ECG

ECG LD 326501 instruction manual

Philips SB7S19S/00 quick start guide

Philips

Philips SB7S19S/00 quick start guide

Woodline KIT-250 lb instructions

Woodline

Woodline KIT-250 lb instructions

ricoo S1222 installation instructions

ricoo

ricoo S1222 installation instructions

Kanto P301 user manual

Kanto

Kanto P301 user manual

VidaBox VB MNT FFS2 installation guide

VidaBox

VidaBox VB MNT FFS2 installation guide

PROEL PLWIN60C user manual

PROEL

PROEL PLWIN60C user manual

AllMounts PLB-43S instruction manual

AllMounts

AllMounts PLB-43S instruction manual

VMP VH-001 instruction sheet

VMP

VMP VH-001 instruction sheet

Nederman SYSTEM 920/400 instruction manual

Nederman

Nederman SYSTEM 920/400 instruction manual

Glasdon ORBIS POST MOUNTING KIT installation guide

Glasdon

Glasdon ORBIS POST MOUNTING KIT installation guide

Songmics LGR105 manual

Songmics

Songmics LGR105 manual

Grape GM401 user manual

Grape

Grape GM401 user manual

FourStarGroup 11225296 manual

FourStarGroup

FourStarGroup 11225296 manual

CHIEF FLR100 installation instructions

CHIEF

CHIEF FLR100 installation instructions

FEC XDCAM EX PMW-EX30 manual

FEC

FEC XDCAM EX PMW-EX30 manual

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.

1
Exos® 2U and 5U Rackmount Guide
Part Number 204757000-00, B • November 2022
Complete installation prerequisites
The rackmount rails are designed to bear the maximum weight of the storage enclosure when it is properly mounted in a
standard rack cabinet. You can install multiple storage enclosures in a single rack cabinet.
CAUTION You must use only the supplied rail kit and related mounting hardware.
To complete installation prerequisites:
1. Prepare the host system for the installation by obtaining access to the following items:
a. A host computer with the correct firmware, BIOS, and drivers
b. A functioning host bus adapter installed in the host computer, or a switch connected to a host computer
c. Tested, good cables for host connection that meet storage enclosure requirements
d. The provided power cords, which meet power specifications
2. Familiarize yourself with system configuration requirements and the storage enclosure components.
3. Obtain the following:
a. An anti-static wrist or ankle strap for handling static-sensitive components
b. A static-protected environment for temporary storage of the storage enclosure and the FRUs
c. A Torx screwdriver, 6-in length, with T10 and T20 bits
d. A flat-bladed screwdriver, 6-in length
e. A Philips screwdriver, 6-in length
f. A mechanical lift with sufficient clearance and capable of safely lifting the storage enclosure without drive modules
4. Ensure the rack cabinet is suitable for use with the storage enclosure.
a. A rack cabinet capable of holding 2U or 5U form factors that meets all UL and IEC safety requirements, leveled in all
planes with respect to each other
b. Adequate clearance in front of the rack cabinet to install the provided rail kit
c. A maximum depth of 884mm (34.81 inches) from back of front post to maximum extremity, excluding cabling and door
closure considerations
d. A rack cabinet that causes a maximum back air pressure of 5 pascals (0.5mm water gauge)
e. A rack cabinet constructed to meet the installed weight capacity for the total number of storage enclosures in the rack
cabinet, based on the related maximum weight per enclosure
2U12 2U24 5U84
A maximum of 32kg (71 lb) A maximum of 30kg (60 lb) A maximum of 130kg (287 lb)
f. A maximum operating ambient temperature of 35°C (95°F)
5. Secure sufficient staff to assist with the installation. Minimum staff:
a. One qualified service technician for the complete installation procedure
b. One spotter to assist with the lift and to assist with the installation from the rear of the rack cabinet
c. A total of two people (2U) or three people (5U) to unpack the storage enclosure and move it onto the mechanical lift
Installation of 2U enclosures
Sequentially follow the installation checklist in the shipkit's Getting Started sheet to install your 2U storage enclosure.
Unpack and prepare the 2U enclosure
CAUTION Do not operate a storage enclosure outside the manufacturer's intended use.
lStorage enclosures are suitable for connection to intra-building or non-exposed wiring or cabling only.
lStorage enclosures are suitable for installation in locations where the National Electrical Code (NEC) applies but are not
suitable for Outside Plant (OSP) installations.
lCustomer facilities must provide for voltages with not more than ± 5% fluctuation. Customer facilities must also provide
suitable surge protection.
To unpack and prepare the 2U enclosure:
1. Prepare the site for the storage enclosure installation. This includes meeting all product specifications and providing a
clean, clear, static-protected environment prior to unpacking the enclosure.
2. Complete the following actions to complete inspection of the 2U enclosure:
a. Examine packaging for damage. This includes cuts, water damage, or shipment mishandling.
b. If there is damage, photograph and document it, but do not proceed. Retain original packaging for returns.
c. Cut open the package lid to remove all items above the chassis, such as the rails and protective foam, and set aside to
gain access the chassis.
3. Locate two people to assist in moving the storage enclosure chassis in its plastic bag onto the mechanical lift.
a. Position a person on each side of the storage enclosure, grasping the chassis sides, not the front or rear panel.
IMPORTANT Almost all the weight of the storage enclosure is to the rear, so prepare to lift more from the side
of the chassis to the rear than the chassis side to the front.
b. Simultaneously lift the storage enclosure, using appropriate safe lifting technique while moving it to the mechanical lift.
Figure 1 2U12 and 2U24 storage enclosure packaging, shown without plastic for clarity
2
3
4. Slide off the plastic bag to access the chassis while making sure the chassis is centered on the lift.
5. Complete the following actions to prepare the 2U chassis for installation:
a. If drives are present in the chassis, grasp the latch of the first drive in its carrier (DDIC) between thumb and forefinger
and squeeze together to release the latch, then pivot outward to release the DDIC from the midplane.
b. Temporarily remove and store each DDIC in a static-protected environment.
c. Facing the chassis front, grasp the right rack flange cover, work the cover free, and set it aside in a safe location.
d. Grasp the left rack flange cover, gently work the cover free, and set it aside in a safe location.
Install the 2U rackmount rail kit
The storage enclosure requires rackmount hardware for installation into a standard 1.2m rack and occupies 2 EIA units of rack
space (8.9cm or 3.50 inches) per unit. The rail kit contains a left and right rail designed to handle the 2U storage enclosure and
provide for installation of multiple enclosures without loss of rack space. Product function and user safety hinge on proper
installation. This task assumes square mounting holes but pertains to other rack types.
You must take all appropriate rack cabinet safety precautions before mounting a storage enclosure into a rack.
CAUTION Observe all the following directives:
lAlways place the rack cabinet on a flat, leveled surface. Do not install a storage enclosure into a rack cabinet until you
verify the rack cabinet is level.
lFollow prescribed leveling procedures from the rack cabinet manufacturer.
lNever install or remove from the rack cabinet more than one storage enclosure at a time. This helps prevent the rack
cabinet from tipping or falling.
lVerify the rack cabinet meets all safety requirements when configured with storage enclosures.
lVerify connections comply with all electrical requirements.
lVerify the system complies with all temperature and exhaust requirements.
To adhere to safety precautions when mounting a storage enclosure into a rack cabinet:
1. Read and observe all warning and caution labels on the storage enclosure.
2. Verify the rack cabinet is on a flat, leveled surface because any incline or unevenness stresses the rack cabinet and
storage enclosure. A storage enclosure in an uneven rack cabinet resists smooth rail movement and may distort the
chassis.
3. Verify the rack cabinet design supports the total weight of storage enclosures and has stabilizing features to prevent the
rack cabinet from tipping or being pushed over during installation or normal use.
4. Do not lift the storage enclosure without a mechanical lift. No single person should lift an enclosure without help.
5. Mount storage enclosures into the rack cabinet from the bottom to the top during installation.
6. Locate lighter storage enclosures above heavier ones to maximize stability.
7. Remove storage enclosures from the top of the rack cabinet to the bottom when emptying it.
Required equipment Qty Identification
Outer rails, properly oriented 2 N/A
#2 Phillips-head screwdriver, 6-in length 1 N/A
Required equipment Qty Identification
(Optional) 8mm nut driver, 6-in length 1 N/A
Phillips-head screw, M5 x 15, 8mm hex flange 8
To install the 2U rackmount rail kit:
1. Remove both outer rail assemblies from their packaging.
123456
Item Description Item Description
1 Left front mount bracket 4 Set screw, front
2 Left front outer rail 5 Set screw, rear
3 Left rail slides 6 Left rear mount bracket
Figure 2 2U enclosure outer rail components
2. Orient the outer rail with the LH FRONT embossed on it to your left, the other with the RH FRONT embossed on it to your
right, and each emboss toward you, facing inward.
3. Loosen, but do not remove, the 2 set screws on each outer rail with a Philips screwdriver.
4. Facing the left side of the rack cabinet, slide the left front mount bracket pins into holes in the front rack post.
5. Bias the left rack mount bracket as far inward as possible, then verify the entirety of the lower rail tab is visible just beyond
the inner edge of the front rack mount bracket. This step is crucial to safety and proper storage enclosure operation.
6. Hold the biased mount bracket in that position.
7. Insert a Phillips-head M5 x 15 screw into the center hole of the front mount bracket and barely tighten against the front
rack post using a Philips screwdriver or 8mm nut driver.
4
5
Figure 3 Attachment of front mount bracket to front rack cabinet posts
8. Extend the length of the rail until fully mating the rear mount bracket pins in the mirror location on the rear rack post.
Figure 4 Adjustment of rail length to fit rack cabinet
9. Verify that the rails are level at the same height on both rack posts, and that all mount bracket location pins fully seat in
identical locations in the rack posts.
10. Facing the rear of the rack cabinet, insert a Phillips-head M5 x 15 screw into the center hole of the rear mount bracket.
Figure 5 Attachment of rear mount bracket to rear rack cabinet posts
11. Hand tighten firmly against the rack post using an 8mm nut driver or a Philips screwdriver.
12. Facing the front of the rack cabinet, hand tighten the Phillips-head M5 x 15 screw using an 8mm nut driver or a Philips
screwdriver so that the hex head flange is flush with the front rack post.
13. Fix the adjusted length of the left outer rail by hand tightening both rail slide set screws using a Phillips screwdriver.
14. Repeat the process for the right outer rail.
Mount the 2U enclosure into the rack cabinet
WARNING! Serious injury and mechanical failure can result if you do not adhere to rack cabinet safety precautions.
lTo avoid risk of death or injury from tipping the rack, follow all rack installation guidelines, securing the rack cabinet to the
floor with a concrete anchor kit.
lTo avoid catastrophic failure of the rack assembly, never exceed rack cabinet weight limits.
lEntirely support the storage enclosure with the mechanical lift until the enclosure is in the storage position.
lFollow local occupational health and safety guidelines and meet all requirements for manual material handling.
Mounting the storage enclosure into the rack cabinet is the most critical of installation procedures and requires your full
attention. Safety and hardware longevity depend on the rail's smooth function and correct implementation of this task.
lMake sure there is sufficient clearance for a technician and the storage enclosure in front of the rack cabinet.
lObserve rack cabinet weight limits.
lFill the rack cabinet from the bottom to the top, with the heaviest equipment at the bottom.
lMake your approach with the mechanical lift level, straight, and parallel to the rack cabinet. Any skew, warp, or tilt prevents
the inner rails attached to the storage enclosure from properly engaging the outer rails in the rack cabinet.
6
7
Required equipment Qty Identification
Mechanical lift 1 N/A
Storage enclosure with attached inner rails 1 N/A
Rack cabinet with installed outer rails 1 N/A
#2 Phillips-head screwdriver, 6-in length 1 N/A
Panhead screw, M5 x 8, #2 2
Phillips-head screw, M5 x 15, 8mm hex flange 2
To mount the 2U enclosure into the rack cabinet:
1. Confirm that the outer rails are properly and securely installed in the rack cabinet.
2. Complete the following actions to position the mechanical lift and the 2U chassis:
a. Using proper safety precautions, position the 2U chassis on the mechanical lift perpendicular to the lift wheels.
b. Move the mechanical lift into position perpendicular to the rack cabinet so that the 2U chassis is parallel to the opening
and is a minimum of 12.7cm to 17.8cm (5 to 7 inches)away from the rack cabinet.
c. Adjust the mechanical lift height to be as close as possible to the allocated 2U location.
d. Moving only the 2U chassis, position it so the attached inner rails align with the outer rails in the rack.
Figure 6 Alignment between 2U chassis and rails (removed rear components for clarity)
3. Complete the following actions to properly secure the 2U chassis on the outer rails:
a. Keep the 2U chassis stationary on the lift.
b. Verify that both outer rails fully engage the 2U chassis inner rails.
c. Guide the chassis inward with the leading edge of each inner rail inside the top and bottom lip of the outer rail.
d. Conduct a visual inspection of both sides to verify both inner rails are an equal distance along the outer rail and that
the direction is straight in, not at an angle.
4. Complete the following actions to insert the 2U chassis into the rack cabinet:
a. Facing the front of the enclosure, carefully exert even pressure on both sides of the storage enclosure front, inserting
the storage enclosure until the rack ear flanges are flush with the front rack posts.
b. Carefully lower the mechanical lift.
c. Thoroughly examine the rack rails for issues such as bowing, scraping, resistance, or indicators of misalignment.
5. Complete the following actions to secure the 2U chassis:
a. Facing the rear of the enclosure, insert and tighten a Panhead M5 x 8 screw into the tail of each outer rail and through
the 2U chassis to secure the rear of the chassis.
Figure 7 Installation of 2U rear screw near sample 580W fan cooling module
b. Facing the front of the 2U chassis, insert a Panhead M5 x 8 screw into the operator's (ops)panel with an 8mm nut
driver or a Philips screwdriver.
Figure 8 Installation of 2U operator's panel screw and cover
8
9
c. Hand tighten firmly against front rack post at the center of the rack ear flange.
d. Slide the ops panel cover over the left rack ear flange until flush with the rack post.
e. Repeat the process for the right rack ear flange and cover.
Populate the 2U enclosure
After successfully mounting the 2U chassis into the rack cabinet, populate the storage enclosure.
To populate the 2U enclosure:
1. Examine drive carriers for damage. If you installed a new drive in the carrier, verify drive connector pins are not bent.
2. Orient a drive in its carrier (DDIC) so the release latch is to the left for the 2U12 or to the top for the 2U24.
3. Insert it into the first available left-hand slot and press inward until fully seated against the midplane and the latch locks.
4. For the 2U12 storage enclosure, take the following actions until all slots hold either a DDIC or an optional blank carrier.
a. Insert the next DDIC and move across the row to the next slot in the sequence, repeating until the top row is full.
b. Repeat until the middle row is full.
c. Repeat until the bottom row is full.
5. For the 2U24 storage enclosure, insert the next DDIC and move across the row to the next slot in the sequence, repeating
until all slots hold either a DDIC or an optional blank carrier.
CAUTION If you partially populate the storage enclosure with drives in their carriers (DDICs), you must install a
minimum of one DDIC. For proper air flow, all drive slots must hold either a DDIC or an optional blank carrier. You may not
leave any empty slots.
Follow the remainder of the installation checklist sequence on the Getting Started sheet using the Hardware Installation and
Maintenance Guide.
Installation of 5U enclosures
Sequentially follow the installation checklist in the Getting Started sheet to install your 5U storage enclosure.
Unpack and prepare the 5U enclosure
CAUTION Do not operate a storage enclosure outside the manufacturer's intended use.
lStorage enclosures are suitable for connection to intra-building or non-exposed wiring or cabling only.
lStorage enclosures are suitable for installation in locations where the National Electrical Code (NEC) applies but are not
suitable for Outside Plant (OSP) installations.
lCustomer facilities must provide for voltages with not more than ± 5% fluctuation. Customer facilities must also provide
suitable surge protection.
To unpack and prepare the 5U enclosure:
1. Prepare the site for the storage enclosure installation. This includes meeting all product specifications and providing a
clean, clear, static-protected environment prior to unpacking the storage enclosure.
2. Complete the following actions to complete inspection of the 5U enclosure:
a. Examine packaging for damage. This includes cuts, water damage, or evidence of mishandling during shipment.
b. If there is damage, photograph and document it, but do not proceed. Retain all original packaging for returns.
c. Remove pallet strapping and all protective foam above the storage enclosure to access it.
3. Slide the plastic bag aside to allow access to the chassis.
WARNING! The box is deep, and the chassis is very heavy. Do not attempt to lift by yourself.
>128kg (282.2 lbs.)
Figure 9 Default belt straps already around the 5U storage enclosure
4. Locate three people to assist in moving the storage enclosure onto the mechanical lift, using an appropriate safe lifting
technique to perform the following actions:
a. Position one person at the front to grip the front belt strap securely by both loops, not by any portion of the front or
rear panel areas.
b. Position one person at each rear corner to grip both rear belt straps by the loops on that side.
c. Simultaneously lift the storage enclosure, using appropriate safe lifting technique while moving it to a static-protected
location, and then to the mechanical lift for mounting to the rack cabinet.
5. Facing the front of the chassis, grasp the right rack flange cover, gently work the cover free, and set it aside in a safe
location.
6. Grasp the left rack flange cover, gently work the cover free, and set it aside in a safe location.
Install the 5U rackmount rail kit
The storage enclosure requires rackmount hardware for installation into a standard 1.0m or 1.2m rack and occupies 5 EIA units
of rack space (22.22cm or 8.75 inches) per unit. The rail kit contains a left and right rail designed and tested to handle the 5U
storage enclosure and provide for installation of multiple enclosures without loss of rack space. Product function and user
safety hinge on their proper installation. The following task assumes your rack posts have square mounting holes.
Required equipment Qty Identification
Outer rails, properly oriented 2 N/A
#2 Phillips-head screwdriver, 6-in length 1 N/A
(Optional) 8mm nut driver, 6-in length 1 N/A
Phillips-head screw, M5 x 15, 8mm hex flange 8
10