1. Fit ring handle to the door inline with the
centre door framework using 4 x 25 mm black
screws.
2. Fit the false hinges to the outside of the door
at the top and bottom. Each is to fit as far as
possible onto the framework at the back of the
door. Secure using 2 x 10 mm black screws per
hinge.
3. Lay front panel on a flat clean surface. Re-
move protective film from door glazing and lay
over the diamond shaped cut out in the door.
Position the 4 angled rebated pieces of wood on
top of the glazing and secure using 8 x 20mm
screws, 2 per piece.
Remove all travel protection blocks from bottom
edge of panels.
1. Ensure that your base is firm and absolutely
level.
2. Lay floor of building on base.
3. Place back panel onto the floor ensuring the
cladding has overhung the floor. Place side
panel next to this and join together from the
inside using 2 x 60 mm screws.
4. Place remaining side panel in position. Join
together from the inside using 2 x 60mm screws.
5. The front door panel is now ready to be
placed. Join to side panels using 2 x 60 mm
screws.
1. The bunk floor will sit on the framework above
the window and on the back wall opposite.
2. Place floor on top of the supports. Mark the
required position of 2 drill holes to enable screws
to be placed into the side wall uprights. Also
mark the required position of drill holes on the
support joist to enable a screw to be placed up
through the support joist and into the framework
of floor, one on each support joist.
3. Remove floor and drill guide holes as marked.
Replace floor and screw to side wall using 2 x 60
mm screws and up through support joists using
2 x 60 mm screws.
4. Place balustrade railing so the post is against
the back wall. Mark a line on the post at an
angle level with the top of the cladding and cut
off the excess.
5. Place balustrade railing in position. Secure
through bottom rail into floor using 2 x 60 mm
screws and 2 x 60 mm screw along the edge
against the door frame.
6. Secure upright of balustrade railing to roof
using an ‘L’ shaped bracket and 2 x 25 mm
screws.
7. Place ladder in position. Secure from the back
of the floor joist into ladder using 3 x 60 mm
screws. Secure each side of the ladder to the
floor using 2 x 60 mm screws.
1. Slide the small roof panel into position using
the cut-out of the ridge as a guide. Repeat for
the other panel. Please note that a small amount
of planning may be necessary to the tops of the
walls to ensure a snug fit.
2. Nail both roof pieces together at the ridge
using 4 x 40 mm nails.
3. Once in position secure down from the inside
using ‘L’ shaped brackets and 25 mm screws
fixing from the framework of the roof to
framework of the gable walls, 2 per wall.
5. Fix along the length of the building using 2 x
40 mm nails per side.
1. Measure and cut 3 x 2100 mm length strips.
2. Lay one piece of felt along the lowest edge of
the large roof panel allowing an overhang of
approx. 50 mm on all sides.
2. Repeat process for the smaller roof panel.
3.Place another piece of felt next to and
overlapping both pieces already laid going over
the ridge of the building,
4. Secure felt to roof using felt nails at approx.
100 mm intervals.
1. Fix the corner strips in position where the
panels meet using 3 x 40 mm nails per strip
1, Secure wall panels to the floor on the inside of
the building through framework into floor bearers
using 2 x 60 mm screws per panel.
1, Nail the 4 fascia boards to gable ends using 3
x 40 mm nails per piece.
2. Nail diamonds on top of and in the centre of
the fascia board using 2 x 40 mm nails per
diamond.
1. Drill 2 holes into the wood block and secure to
inside of door opening flush with the aperture
using 2 x 60 mm screws.
2. Secure door catch to inside of door approx.
centrally along side the wood block and secure
using 2 x 25 mm screws.
3. Close the door and attach the door catch
together and mark the required position of the
door catch housing. Secure using 2 x 25 mm
screws.
1. Remove protective film. Place glazing material
into the aperture of each window.
2. Hold into position with four pieces of beading.
Secure into position using 2 x 15 mm panel pins
per piece of beading.
1 Fit shutters (B1).
One person to hold in
place and another to
secure from the inside
using 4x 25 mm screws,
into each block.
2 Secure window boxes
to building from inside
using 2x25mm screws
each
3. Push the vents into
the holes in the gable.
E Felt Roof
F Corner strips
G Secure Walls to Floor
H Fascia & Diamonds
I Door Catch
J Glazing
. Assembly Completion Checklist
E Roof Assembly
A Front Panel
B Floor & Walls
C Upstairs K Shutters & Window Box
1 Check and ensure that no raised grain or splinters
are evident on timber components. Sand down any
raised grain or splinters using fine grade sandpaper.
2 Check that all screw, nail and pin heads are properly
tapped home and are not proud of the timber surface.
3 Check and ensure that no screws, nails or pins
protrude through any panel.
4Check and ensure that all parts are properly secured
against reasonable force.
5 Do not apply decorative wood finish/treatments to wet
or damp timber. Please observe the instructions of
the wood finish/treatment manufacturer.
6 Adults need to check the playhouse regularly and
maintain the playhouse in good condition to provide a
safe environment. Do not use if damaged. If damaged
the playhouse should be properly and safely repaired
before further use by children.