Spirax Sarco SI 20 User manual

IM-P795-04 CH Issue 4 1
Type 20 and Type 40
Direct Steam Injection (SI) Humidifiers
Installation and Maintenance Instructions
1. Safety information
2. General
product information
3. Installation
4. Commissioning
5. Maintenance and
spare parts
6. Trouble shooting
Printed in the UK © Copyright 2005
IM-P795-04
CH Issue 4
7950050/4

IM-P795-04 CH Issue 4
2
Safe operation of these products can only be guaranteed if they are properly
installed, commissioned, used and maintained by qualified personnel (see
Section 1.11) in compliance with the operating instructions. General installation
and safety instructions for pipeline and plant construction, as well as the proper
use of tools and safety equipment must also be complied with.
1.1 Intended use
Referring to the Installation and Maintenance Instructions, name-plate and
Technical Information Sheet, check that the product is suitable for the intended
use/application. The products comply with the requirements of the European
Pressure Equipment Directive 97/23/EC and fall within category 'SEP'. It should
be noted that products within this category are required by the directive not to
carry the mark.
i) The products have been specifically designed for use on steam and water,
which are in Group 2 of the above mentioned Pressure Equipment Directive.
The products’ use on other fluids may be possible but, if this is contemplated,
Spirax Sarco should be contacted to confirm the suitability of the product for
the application being considered.
ii) Check material suitability, pressure and temperature and their maximum and
minimum values. If the maximum operating limits of the product are lower than
those of the system in which it is being fitted, or if malfunction of the product
could result in a dangerous overpressure or overtemperature occurrence,
ensure a safety device is included in the system to prevent such over-limit
situations.
iii) Determine the correct installation situation and direction of fluid flow.
iv) Spirax Sarco products are not intended to withstand external stresses that
may be induced by any system to which they are fitted. It is the responsibility
of the installer to consider these stresses and take adequate precautions to
minimise them.
v) Remove protection covers from all connections before installation.
1.2 Access
Ensure safe access and if necessary a safe working platform (suitably guarded)
before attempting to work on the product. Arrange suitable lifting gear if required.
1.3 Lighting
Ensure adequate lighting, particularly where detailed or intricate work is required.
1.4 Hazardous liquids or gases in the pipeline
Consider what is in the pipeline or what may have been in the pipeline at some
previous time. Consider: flammable materials, substances hazardous to health,
extremes of temperature.
1.5 Hazardous environment around the product
Consider: explosion risk areas, lack of oxygen (e.g. tanks, pits), dangerous gases,
extremes of temperature, hot surfaces, fire hazard (e.g. during welding), excessive
noise, moving machinery.
1. Safety information

IM-P795-04 CH Issue 4 3
1.6 The system
Consider the effect on the complete system of the work proposed. Will any proposed
action (e.g. closing isolation valves, electrical isolation) put any other part of the
system or any personnel at risk?
Dangers might include isolation of vents or protective devices or the rendering
ineffective of controls or alarms. Ensure isolation valves are turned on and off in
a gradual way to avoid system shocks.
1.7 Pressure systems
Ensure that any pressure is isolated and safely vented to atmospheric pressure.
Consider double isolation (double block and bleed) and the locking or labelling of
closed valves. Do not assume that the system has depressurised even when the
pressure gauge indicates zero.
1.8 Temperature
Allow time for temperature to normalise after isolation to avoid danger of burns.
1.9 Tools and consumables
Before starting work ensure that you have suitable tools and/or consumables
available. Use only genuine Spirax Sarco replacement parts.
1.10 Protective clothing
Consider whether you and/or others in the vicinity require any protective clothing
to protect against the hazards of, for example, chemicals, high/low temperature,
radiation, noise, falling objects, and dangers to eyes and face.
1.11 Permits to work
All work must be carried out or be supervised by a suitably competent person.
Installation and operating personnel should be trained in the correct use of the
product according to the Installation and Maintenance Instructions.
Where a formal 'permit to work' system is in force it must be complied with. Where
there is no such system, it is recommended that a responsible person should know
what work is going on and, where necessary, arrange to have an assistant whose
primary responsibility is safety.
Post 'warning notices' if necessary.
1.12 Handling
Manual handling of large and/or heavy products may present a risk of injury. Lifting,
pushing, pulling, carrying or supporting a load by bodily force can cause injury
particularly to the back. You are advised to assess the risks taking into account the
task, the individual, the load and the working environment and use the appropriate
handling method depending on the circumstances of the work being done.
1.13 Residual hazards
In normal use the external surface of the product may be very hot. If used at the
maximum permitted operating conditions the surface temperature of some products
may reach temperatures of 350°C (662°F).
Many products are not self-draining. Take due care when dismantling or removing
the product from an installation (refer to 'Maintenance instructions').

IM-P795-04 CH Issue 4
4
1.14 Freezing
Provision must be made to protect products which are not self-draining against
frost damage in environments where they may be exposed to temperatures below
freezing point.
1.15 Disposal
Unless otherwise stated in the Installation and Maintenance Instructions, this
product is recyclable and no ecological hazard is anticipated with its disposal
providing due care is taken.
1.16 Returning products
Customers and stockists are reminded that under EC Health, Safety and
Environment Law, when returning products to Spirax Sarco they must provide
information on any hazards and the precautions to be taken due to contamination
residues or mechanical damage which may present a health, safety or
environmental risk. This information must be provided in writing including
Health and Safety data sheets relating to any substances identified as hazardous
or potentially hazardous.

IM-P795-04 CH Issue 4 5
16
2. General product information
2.1 Description
Spirax Sarco direct steam injection (SI) humidifiers are designed to inject dry steam into a
ducted air system in such a manner as to ensure efficient mixing of the steam and air, and to
raise the moisture content of the air stream with no condensate carryover.
Standard control options
Pneumatic 0.2 - 1.0 bar (2.9 - 14.5 psi)
Electric Valve motor drive; 230 V or 24 V
Electronic 0-10 V dc signal with 24 V power supply
2.2 Technical data
Separator body design conditions PN6
Maximum operating pressure 4 bar g (58 psi g)
Maximum operating temperature 152°C (305°F)
Maximum recommended tracer circuit operating pressure 4 bar g 58 psi g)
Minimum recommended tracer circuit operating pressure 1 bar g (14.5 psi g)
Note: The assembly can be operated down to: 0.35 bar g (5.07 psi g)
Fig. 1 Typical arrangement of separator, valve, actuator (pneumatic), lance,
lance pre-heating, condensate trapping and auxiliary piping
16 = Compression fitting
16
16
16
Lance
Separator
Steam trap
Alternative supply

IM-P795-04 CH Issue 4
6
2.3 Identification (see Figure 2)
The label on the separator indicates the system Type (20 or 40) and the maximum operating
pressure - 400 kPa (58 psi g).
The label on the Lance shows the Type (20 or 40) and the Model (1 - 12).
2.4 System
The Spirax Sarco SI humidifier system comprises 4 basic elements:
- The separator and pipework components (to suit valve type to be installed),
- Control valve and actuator (these may be of Spirax Sarco manufacture, or from other
proprietary producers. Spirax Sarco would supply the relevant Installation and Maintenance
Instructions).
- Lance(s).
- Ancillaries.
Note: Certain items of pipework and fittings are to be supplied by the customer or installer.
2.5 Supply and packaging
The packing method used with Spirax Sarco humidifiers will vary with the Type and Model
supplied. It is important to check the equipment against the order / acknowledgement.
Separators carry a label giving Type (20 or 40). The lance label will show Type (20 or 40)
and Model Code (1 - 12: see the Technical Information (TI) for the equivalent lance length).
Associated equipment, such as steam traps, strainers, pressure reducing stations etc.,
which may be part of the order, will be packed separately. Where Spirax Sarco supply the
valve (any make), it will be already connected to the separator outlet using the appropriate
fittings. Any additional piping components will be supplied separately packaged. There are
two compression fittings (16 - see Figure 1) supplied with the separator and a further two
with each lance. Lances are supplied in a rigid cardboard tube.
Typical date code
Fig. 2.

IM-P795-04 CH Issue 4 7
3. Installation
3.1 Equipment provided
3.1.1 Unpack individual packages in the area where the installation is to take place. This
avoids the possible loss or damage to parts in transit over the site.
3.1.2 Items shown dotted are to be supplied by the installer.
3.1.3 Two ¼" BSP x 8 mm compression fittings (16 - see Figure 1) are supplied with each
separator, and two with each lance. These support the tracer heating pipework
between the steam supply (separator or separate source) and the lance(s), and the
discharge from the tracer heating circuit to the trap.
3.1.4 If escutcheon plates are to be used (see Figure 6, page 11).
3.1.5 The installer is responsible for the main lance steam supply / supporting pipework.
3.1.6 As the tracer heating circuit is parallel to, but independent from, the main lance steam
supply, it can be run in any acceptable material. Spirax Sarco are able to supply
8 mm annealed copper for this purpose.
3.2 Lance, tracer and pre-heating circuit
3.2.1 The main inlet connection on the lance is: Type 20 - ¾" screwed.
Type 40 - 1½" screwed.
The two tracer connections on each lance are ¼" BSP.
3.2.2 A single lance can be connected directly to the outlet of the valve using the piping
components provided (see Figures 7 to 10, page 12). These are supplied to match
the flanged or screwed connections of the valve to be installed, when the valve is
ordered.
3.2.3 The connection of the lance to the separator with these fittings, allows the correct
orientation of the lance to be achieved, i.e. nozzles facing into the air flow (except
for the installation shown in Figure 15, page 14). This is important to consider as
the lance(s) can be inserted from either the left hand side or the right hand side
of the duct.
3.2.4 If the tracer heating steam is taken from the top connection on the separator, then
the pressure / temperature of the tracer circuit will be as for the main humidifying
steam supply.
Where dry steam is sourced from a separate system for tracer heating, the top
connection on the separator (¼" BSP) should be plugged. The tracer heating circuit
can operate at up to 4 bar g (58 psi g) steam pressure.
3.2.5 Single lance systems should be assembled such that the lance is mid-height in the
duct.
3.2.6 On multi-lance systems, the lances should be assembled such that there is an even
distribution of steam over the duct, as shown in Figure 3, page 10. Particular attention
should be paid to the position of the main steam supply to the interconnecting
pipework - see Figures 5, 11, 12 and 13.
Generally up to 5 lances can be installed horizontally on an application.
Recommendations on lance numbers relative to duct height can be found in
Section 3.3.4.
3.2.7 The outer end of the lance can be supported utilising the M10 thread in the lance
end cap.

IM-P795-04 CH Issue 4
8
3.3 Installation and pipe sizing
3.3.1 Ensure that the main steam supply system, where pressure reduction is required,
is installed correctly to provide the driest possible steam. Details will be found
in Section 3.9. The maximum steam pressure to the separator must not exceed
4 bar g (58 psi g).
3.3.2 A section of the steam supply end of the lance will protrude through the side of
the duct. Sufficient length must be provided to allow for the tracer heating and
condensate pipe connections, and the required thickness of lagging.
To accept the lance, a hole to suit the lance diameters must be provided in the duct
wall, as follows:
Type 20 Lance - 38 mm diameter - minimum.
Type 40 Lance - 54 mm diameter - minimum.
The small clearance between the duct and the lance can be sealed either with a
proprietary high temperature mastic, or by use of the Type 20 or Type 40 escutcheon
plates - see Figure 6, page 11.
3.3.3 To assist in ensuring that there are no problems with steam condensing in the duct
and to obtain minimum absorption distance, the lance(s) should be positioned as
shown in Figure 3, page 10.
3.3.4 The recommendations on the number of lances for various duct heights are:
Duct height: Number of lances
Up to 1000 mm 1
1000 - 1700 mm 2
1700 - 2200 mm 3
2200 - 2600 mm 4
2600 mm and over 5
3.3.5 Figures 7 to 10, page 12 give details of the piping components supplied as standard
with Spirax Sarco humidifiers.
3.3.6 Table 1 indicates suitable pipe sizes to maintain the correct steam flow to the lance(s)
without creating excessive pipework pressure loss between the control valve outlet
and the lance inlet.
3.3.7 Wherever possible, all interconnecting pipework, valves, separators etc, should be
adequately lagged. This will reduce heat (energy) losses, and allow quicker warm-up
time, reduce the amount of condensate produced and generally improve the overall
efficiency of the installation.
3.3.8 Figures 11, 12 and 13, page 13, give recommendations for piping up the main steam
supply, trapping arrangements and manifolding for a variety of multi-lance and
vertical lance installations.
Table 1 Suitable pipe sizes
System Valve size
Number of lances
1 2 3 4 5
Nominal pipe diameter in mm
Type 20
DN15 15 20 20 25 25
DN20 20 20 25 25 32
DN25 25 25 25 32 32
Type 40
DN20 20 25 25 32 32
DN25 25 25 32 32 40
DN32 32 32 40 40 40
DN40 40 40 40 50 50

IM-P795-04 CH Issue 4 9
3.4 Absorption
The design and installation of an efficient humidifier system will result in:
3.4.1 Thorough mixing of the steam and air across the full cross-sectional area of the duct.
3.4.2 Complete mixing to take place over the shortest possible distance.
3.4.3 No wetting out of condensate on the duct or other components; e.g. heating or cooling
batteries, filters, etc.
3.5
The absorption distance Z (see Figure 4, page 10) is generally considered to be that dimension
where the steam plume has become invisible. However, this does not infer that total absorption
has taken place.
To keep the absorption distance to a minimum, the Spirax Sarco SI direct injection humidifier
has been designed to project the steam initially against the air flow. Since no two systems are
identical, the characteristics of the particular installation will effect the design requirements
referred to above.
As a general guide, the lance should be installed such that the nozzles are 0.5 m (20") from
the nearest component upstream of the lance - see Figure 4, page 10.
3.6
Conditions which may result in this dimension being increased are:
3.6.1 Where the air velocity is below 3 m/s (9.84 ft/s).
3.6.2 High steam loads are involved.
3.6.3 Where there are long lengths of straight duct downstream of the lance - absorption
distance not critical.
3.6.4 Where the air temperature is low - below 18°C (64°F).
3.6.5 Variations in the temperature or velocity across the duct section.
3.6.6 Where steam pressures are below 0.5 bar g (7.25 psi g).
3.6.7 Where air inlet conditions have high Relative Humidity values.
3.7
Conditions where this dimension could be decreased:
3.7.1 Low steam loads.
3.7.2 Where the steam pressure (temperature) at the main control valve inlet is high.
3.7.3 With high air velocity.
3.7.4 If the air temperature off the heater battery is high - over 25°C (77°F).
3.7.5 Where a small amount of wetting out is permissible.
3.7.6 Where incoming air Relative Humidity levels are low.

IM-P795-04 CH Issue 4
10
3.8
Humidity and temperature sensors should be installed at a sufficient distance downstream
to ensure full mixing of the air and steam to obtain true readings (see Figure 4).
High limit humidistats, typical set at 90% Relative Humidity, would normally be installed
2 to 3 m (6.5 to 10 ft) downstream of the humidifier. This control is to prevent any over-
saturation of the system due to a failure or malfunction of the main control humidistat.
In open area humidification from a duct supply, the main control humidity sensor would be
fitted in the open area (see 'C' in Figure 17, page 15).
With installations incorporating return air systems, the main control humidity sensor would
generally be fitted in the return air duct (See Figure 17, page 15).
X
X
Y
H
2 lances X = H/4
Y = H/2
3 lances X = H/6
Y = H/3
4 lances X = H/8
Y = H/4
5 lances X = H/10
Y = H/5
Fig. 3
Fig. 4
Duct pressure stat
High
limit
humidistat
Absorption distance
0.5 m
Air
flow
Fan
Humidifier
lance
Heater battery
Z
Controlling
humidity
sensor
2Z - 3Z 5Z - 6Z
Lance
Lance
Duct

IM-P795-04 CH Issue 4 11
Fig. 5 Alternative separate steam supply for pre-heater - maximum 4 bar g (58 psi g)
Parts shown in dotted line - Customer to supply.
115 mm
100 mm
R
65 mm
50 mm
2 holes
5 mm
Escutcheon plate - galvanised Type 20 R = 18 mm
Type 40 R = 25 mm
Fig. 6
2 slots
5 mm
Duct wall
Insulation
Escutcheun plate

IM-P795-04 CH Issue 4
12
Fig. 7 Type 20 screwed Fig. 8 Flanged PN16 EN 1092
The appropriate piping components will be supplied with each humidifier to match the
valve supplied, or valve to be fitted. Where a valve is not supplied the pipe fittings used
between the separator and the valve will be fitted to the separator outlet pipe. Flanged sets
are supplied complete with gaskets, nuts and bolts. Any components not supplied fitted
will be supplied bagged.
Fig. 10 Flanged PN16 EN 1092Fig. 9 Type 40 screwed
DN20
DN25
DN15
DN40
DN32
DN25
DN20
DN40
DN32
DN25
DN20
DN15
DN20
DN25

IM-P795-04 CH Issue 4 13
Fig. 11 Multi-lance installation where
lances are of reasonable length
and where a single tracer trap is
appropriate.
Fig. 12 Multi-Lance installation with
long lances such that a split tracer is
required.
Fig. 13 Vertical multi-lance system where separate steam supply
and condensate headers, suitably trapped, are needed. For more
detailed information or assistance with this type of installation,
please contact your local Spirax Sarco engineer, or Spirax Sarco
branch office.
For sizing
see Table 1,
page 8
➤
➤

IM-P795-04 CH Issue 4
14
Fig. 14 Horizontal duct - Horizontal lance
Air flow
Plan
Fig. 15 Horizontal duct - Vertical lance
Air flow
Plan

IM-P795-04 CH Issue 4 15
Air flow
Plan
Fig. 17
Fig. 16 Vertical duct - Horizontal lance
Air handling unit
Exhaust
air
Outside
air
Return air
Absorption
distance
Control humidity
sensor 'C'
Temperature sensor
High limit humidistat
'C' control humidity sensor
0.5 metre injection distance

IM-P795-04 CH Issue 4
16
3.9 Steam and condensate connections
3.9.1 It is important that the steam supply to the humidifier is as dry as possible, and that
the system is adequately drained of condensate. The pipework immediately upstream
of the humidifier should be free of any low points where condensate could collect.
Take offs should always be from the top of the main - see Figure 18.
3.9.2 The steam supply to the humidifier should be maintained at a constant pressure to
ensure that the design conditions are met. This may require the fitting of a pressure
reduction set, as typically shown in Figure 18 and Figure 19.
3.9.3 The supply line strainer should be provided with a 100 mesh stainless steel screen.
3.9.4 To ensure proper draining of the humidifier separator - see Figure 1, page 5, the steam
trap should always be fitted below the base level of the separator.
3.9.5 There should be no backpressure on the trap due to either:
- a lift in the condensate discharge to atmosphere,
- a pressurised condensate return main caused by flash steam or any other reason.
3.9.6 It is recommended that all condensate be returned by gravity to a vented receiver, and
then be returned by a Spirax Sarco automatic condensate pump to the boiler house.
Fig. 19 Pressure reducing valve set up including mains separator, isolating valves,
condensate trap sets and safety valve. The arrangement is based upon the use of a
Spirax Sarco DP pressure reducing valve.
To humidifier
Fig. 18 Pressure reducing station where the mains steam is dry, steam flows are low
and for less critical pressure applications. The arrangement is based upon the use of a
Spirax Sarco BRV2 pressure reducing valve.
To humidifier

IM-P795-04 CH Issue 4 17
3.10 Control air for pneumatic actuators
When valves and actuators are supplied, full manufacturer’s installation and commissioning
instructions are included. Purchasers must ensure that these specialist products are fully
compatible with any other control elements supplied by others.
3.10.1 The air supply must be dry, clean and free from oil contamination. This is particularly
important where a pneumatic positioner is used.
3.10.2 The humidity sensor must be installed in accordance with the manufacturers
recommendations.
3.10.3 Interlocks for system shutdown are recommended between the humidifier, fans,
humidistat, duct pressure stat or high limit humidistat.
3.10.4 Figure 20 shows a typical pneumatic control system, incorporating a positioner.
Fig. 20 Typical pneumatic control valve with positioner
Air supply
2 to 6 bar
Filter
regulator
EP positioner
4 to 20 mA
Controller
4 to 20 mA
Relative Humidity
duct sensor
24 V

IM-P795-04 CH Issue 4
18
3.11 Electrical supply for electric actuators
When valves and actuators are supplied separately, full manufacturer’s installation and
commissioning instructions are included. Purchasers must ensure that these specialist
products are fully compatible with any other control elements supplied by others.
3.11.1 All electrical wiring and connections should be carried out in accordance with
national or local regulations and standards.
3.11.2 The humidity sensor must be installed in accordance with the manufacturers
recommendations.
3.11.3 Interlocks for system shutdown are recommended between the humidifier, fans,
humidistat, duct pressure stat or high limit humidistat.
3.11.4 Figure 21 shows a typical electric control system.
Fig. 21 Typical electrical control system
2 to 10 V
Controller
24V
1 to 10 V
Mains
power
Relative Humidity
duct sensor

IM-P795-04 CH Issue 4 19
4. Commissioning
Ensure the humidifier has been correctly installed as recommended in Section 3, and all
pipework is free of dirt.
4.1 If an electric actuator is supplied then all electrical wiring and connections should be
carried out in accordance with national or local regulations and standards.
Note: In the event of a pneumatic actuator being supplied then the motive air supply
must be dry, clean and free from all oil contamination.
4.2 Slowly open the upstream isolation valve allowing the steam to heat the lance and
condensate to drain from the separator.
4.3 Check all connections for any leaks.
4.4 After 5 minutes the control signal can be supplied to the actuator.
5. Maintenance and spares
Warning:
Before attempting any maintenance on this equipment, ensure that the assembly is fully
isolated from the main steam supply. All electrical circuits must be isolated (fuses removed)
or disonnected. Pneumatic control systems must be completely isolated or disconnected.
Allow sufficient time for the whole unit to cool down.
5.1 Periodic maintenance
After 24 hours of operation
After 24 hours of operation check the flange bolts for tightness.
On valves with graphite stem seal packing compress the gland seal packing by tightening
the gland nut by ¼ of a turn. Care should be taken not to overtighten as this may cause the
spindle to lock-up.
Annually
Inspect the valve, checking for wear or scale deposits. Worn or damaged parts, like the plug
or seat may need to be replaced, as well as the gland seal packing.
The graphite packing is normally subject to wear. Therefore it is recommended to renew the
packing rings annually.
5.2 Product spares
Please refer to the individual Installation and Maintenance instructions supplied with each
product for detailed maintenance and available spares.

IM-P795-04 CH Issue 4
20
6. Trouble shooting
Fault Probable cause Remedy
Fails to discharge Defective humidistat. Repair or replace humidistat.
steam. Defective control valve. Check control valve for internal
damage or jamming.
Repair if necessary.
Defective control valve actuator. Check correct signal is present.
Service actuator.
Defective control system. Correct or repair.
Blocked screen in main Clean screen and replace.
steam supply strainer
Main steam supply valve closed. Open valve.
Mains pressure reducing Repair if necessary, or set to
valve not set, or faulty. correct operating pressure
for particular installation.
Discharges steam Dirt particles between seat Check valve and clean
continuously after and control valve plug. as necessary.
reaching desired Defective humidistat. Repair or replace humidistat.
humidity. Humidistat not set correctly. Reset.
Lance discharges Incorrect draining of steam Check and rectify mains
water droplets. supply to humidifier separator. supply.
Boiler carryover. Check with boiler house
supervisor to correct condition.
Defective steam trap on Trap should be float type, (with
humidifier separator. integral automatic air vent).
Check for dirt and other foreign
material, clean as necessary.
Alternatively replace trap.
Condensate return line If pressure in the return line
pressure higher than steam cannot be reduced, connect
pressure to separator. trap discharge to separate
return line or drain.
Humidifier traps have vertical lift. Discharge trap to drain or
collecting tank and pump
condensate to overhead
return main.
Inoperative trap on tracer- Trap should be Spirax Sarco
or insufficient lance heating. trap circuit. Type MST18 or
MST21 with 'E' fill balanced
pressure capsule.
Main control valve activated Refer to humidifier start-up
before tracer circuit up to instructions.
operating temperature. Additional pre-heating
of the lance can be achieved by
supplying the tracer system
with dry steam, from a separate
higher pressure supply,
up to 4 bar g (58 psi g).
This manual suits for next models
3
Table of contents
Popular Humidifier manuals by other brands

Zelmer
Zelmer AH1001 user manual

DriSteem
DriSteem VAPORFAN Installation instructions & maintenance operations manual

TCS
TCS HE360A - Whole House Powered Humidifier owner's guide

Boneco
Boneco U300 Quick manual

Devatec
Devatec ElectroVap MC Series instruction & operation manual

Carel
Carel HumiSonic UU0 R 0001 Series user manual