SUNON UFO3 BCEE1BA100A-01S User manual

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
1
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
UFO3
HVLS FAN
4.2 m/3.6 m/3.0 m/2.5 m
(14 ft/12 ft/10 ft/8 ft)
Original Instructions
BCEE1BA100A-01S
BCEE1BA120A-01S
BCEE1BA144A-01S
BCEE1BA168A-01S
BCNE1BA120A-01S
BCNE1BA144A-01S
BCNE1BA100A-01S
BCNE1BA168A-01S

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
2
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
CAUTION SAFETY
WARNING - TO REDUCE THE RISK OF ELECTRIC SHOCK OR INJURY TO PERSONS,
OBSERVE THE FOLLOWING
:
1. Installation work and electrical wiring must be done by qualified person(s) in
accordance with all applicable codes and standards.
2. Do not damage existing wiring and other hidden utilities/devices when cutting or
drilling into a wall or ceiling.
3. Use this unit only in the manner intended by the manufacturer. If you have
questions, contact the manufacturer.
4. Mounting of the suspension system and replacement of parts of the safety
suspension system shall be performed by the manufacturer, its service agent, or
suitably qualified persons.
5. Do not operate any fan with a damaged cord or plug. Please contact manufacturer
and qualified technician for examination and/or repair.
6. Before servicing or cleaning unit, turn off all the power switches to prevent power
from being switched on accidentally. When the circuit breaker cannot be locked,
securely fasten a prominent warning device, such as a tag, to the service panel.
7. SUNON provides installation guide for mounting fans; however, it is the sole
responsibility of the building owner and installer to ensure the safety of the
mounting system, that the building structure is sound and that the installation
complies with all federal, state, and local codes.
8. While turning on power to the fan, please use it with caution. DO NOT connect the
fan to a damaged/dangerous power source. DO NOT attempt to resolve electrical
problems by yourself. Please SEND the fan back to authorized service center for
examination and/or repair. If there is any question with installation, please
contact customer service.
9. When service or replacement of a fan component requires the removal or
disconnection of a safety device, the safety device is to be reinstalled or
remounted as previously installed.
10. Do not bend the airfoils when installing, servicing, or cleaning the fan. Do not
insert foreign objects between rotating airfoils.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
3
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
11. This appliance is not intended for use by persons (including children) with reduced
physical, sensory, or mental capabilities, or lack of experience and knowledge,
unless they have been given supervision or instruction concerning use of the
appliance by a person responsible for their safety. Children should be supervised
to ensure that they do not play with the appliance.
12. SUNON Fans product warranty will not cover equipment damage or failure that is
caused by improper installation or use.
13. If unusual oscillating movement is observed, immediately stop using the ceiling
fan and contact the manufacturer, its service agent, or suitably qualified persons.
14. UFO ceiling fan controller is equipped with a memory function. After
disconnecting power, it still remembers the previous operation mode. Once
turning on power to the fan, it also keeps previous operation mode.
15. Please use this unit only the manners specified by the company. Please contact
customer service if you have questions.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
4
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
Thank you for purchasing our products!
Please read this manual carefully before use, use the product accordingly and keep
the manual in safe place.
In order to protect your rights and interests, please make sure that the deals
records the purchase date, dealer’s name, etc. on the guarantee.
……………………………………………………………………………………………………………
Table of Contents
1. Introduction
2. Product Specifications
3. Installation Precautions
4. The Placement Clearance between fan and obstructions
5. Inside the Box
6. Tools Required for Installation
7. Pre-Installation Checklist
8. Installation Method
9. Wiring Diagram
10. Remote Control Operation Instruction
11. Troubleshooting
12. Maintenance
13. Warranty

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
5
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
Introduction
Thanks for choosing our products, UFO HVLS Fan is an efficient, economical and
stylish choice. It’s energy-saving, eco-friendly design brings excellent airflow to
space. We assure you this appliance will make your space cozier and occupant comfort
in the near future.
Fan Outline
D
H1
H2
H3
H4
Model D A B H1 H2 H3 H4
BCEE1BA100A-01S
BCNE1BA100A-01S
2.5 m(8 ft)
350 mm
/1.1 ft
200 mm
/0.65 ft
643 mm
/2.1 ft
840 mm
/2.8 ft
1000 mm
/3.3 ft
133 mm
/0.4 ft
BCEE1BA120A-01S
BCNE1BA120A-01S
3.0 m(10 ft)
BCEE1BA144A-01S
BCNE1BA144A-01S
3.6 m(12 ft)
BCEE1BA168A-01S
BCNE1BA168A-01S
4.2 m(14 ft)

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
Product Specifications
UFO3 HVLS Fan 2.5 m (8 ft)
Model
:
BCEE1BA100A-01S/ BCNE1BA100A-01S
Input Voltage
(VAC)
Input
Frequency (Hz)
Rated
Power
(W)
Rated
Current
(A)
Maximum RPM
(RPM) Noise(dB(A))
200-240 50/60 335 2.04 150 <40
Button 1 2 3 4 5 6
Speed(RPM) 75 90 105 120 135 150
Power Consumption (W) 46 77 114 166 245 335
UFO3 HVLS Fan 3 m (10 ft)
Model
:
BCEE1BA120A-01S/ BCNE1BA120A-01S
Input Voltage
(VAC)
Input
Frequency (Hz)
Rated
Power
(W)
Rated
Current
(A)
Maximum RPM
(RPM) Noise(dB(A))
200-240 50/60 232 1.44 100 <40
Button 1 2 3 4 5 6
Speed(RPM) 50 60 70 80 90 100
Power Consumption (W) 34 53 83 115 164 232
UFO3 HVLS Fan 3.6 m (12 ft)
Model
:
BCEE1BA144A-01S/ BCNE1BA144A-01S
Input Voltage
(VAC)
Input
Frequency (Hz)
Rated
Power
(W)
Rated
Current
(A)
Maximum RPM
(RPM) Noise(dB(A))
200-240 50/60 176 1.12 70 <40
Button 1 2 3 4 5 6
Speed(RPM) 35 42 49 56 63 70
Power Consumption (W) 26.5 40.4 59 87 120 176

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
7
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
UFO3 HVLS Fan 4.2 m (14 ft)
Model
:
BCEE1BA168A-01S/ BCNE1BA168A-01S
Input Voltage
(VAC)
Input
Frequency(Hz)
Rated
Power
(W)
Rated
Current
(A)
Maximum RPM
(RPM) Noise(dB(A))
200-240 50/60 171 1.1 56 <40
Button 1 2 3 4 5 6
Speed(RPM) 30 35 40 45 50 56
Power Consumption (W) 27 43 64 90 120 171
* Forward
:
The ceiling fan should rotate counterclockwise (Looking up from the
ground).
* Reverse
:
The ceiling fan should rotate clockwise (Looking up from the ground).

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
8
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
Installation Precautions
1. This HVLS fan need a proper device which can support its weight such as aerial
work platform and at least two installation persons.
2. Please switch off all the power supply before installation to avoid the risk of
electric shock or lighting shock.
3. All wiring construction must comply with the national electrical codes, standards
and the local electrical law, then must be installed by professional technicians or
personnel.
4. An earth leakage circuit breaker (<30 mA) should be installed between the
appliance and the power switch.
5. The power switch must be fitted with a fuse (≥20 A).
6. Do not damage electrical wiring and other hidden utilities/devices when
installation.
7. To avoid fire or other hazards, make sure that the wires are completely inside, no
any wire exposed outside the fan appearance or other parts.
8. Do not bend the airfoils when installing the fan.
9. The HVLS fan model covered by the installation instructions must comply with this
installation manual and all national/local electrical codes to avoid personal injury
or property damage.
10. Please ensure that this application is equipped with AC single phase 200-240 V
before installation.
11. All fan parts must be ≥ 0.6 m(2 ft) from all obstructions. The fan installation area
must be free of obstructions such as lights, cables, sprinklers, or other building
structure components.
12. The distance should be at least 0.84m (2.8 ft) from the top of the winglet to the
ceiling and no obstructions in this area.
13. The fan must be installed so that it is at least 3.05 m(10 ft) above the finished
floor.
14. Multiple fans must be spaced at a center-to-center distance that is no less than
2.5x the fan diameter.
15. The fan should not be located near to air supply outlets or exhausting inlets of
other HVAC equipment. Air supply outlets/inlets can be configured to deliver air
away from the fan and outside the swept area of the fan.
16. If the fan is mounted at the same level or higher than an HVAC diffuser, the
winglets must be at a distance that is at least 1.5x the measure of the fan’s

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
9
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
diameter. If the fan is mounted below an HVAC diffuser, the winglets must be at a
distance that is at least 2x the measure of the fan’s diameter.
17. Pleases see the manufacturer’s requirements for the minimum clearance to
combustibles.
18. The fan inlet or other return air point that produces negative pressure should be
bigger than 1 times the diameter of the ceiling fan. This system will reduce the
airflow of the HVLS fan.
19. Proper systems orientation will provide an enhancement to the Indoor Air Quality
and occupant comfort. Please refer to the illustration below.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
10
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
The Placement Clearance between
fan and obstructions
space from the lights
at least 0.6 m away
spacing between fans
at least 2.5x diameter of the fans apart
The tip of the airfoil need at least
0.84 m away from beam/ceiling
and no obstacles
space from wall
at least 0.6 m away
≥3.05
m
≥0.84
m
≥0.6 m
≥0.6
m

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
11
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
The Placement Clearance between fan
and HVAC diffuser
The distance between the center of the ceiling
fan and HVAC equipment need to at least ≥2x
diameter.
The HVLS fan position need to below the HVAC outlet
The distance between the center of the ceiling
fan and HVAC equipment need to at least
≥1.5x diameter
The HVLS fan position need to above the HVAC outlet
HVAC
Diffuser
HVAC
Diffuser

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
12
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
Installation Conditions
I-beam
The yoke to I-beam for this HVLS fan is attached in our product. The yoke only can be
used within the width of 100-300 mm (B) and thickness of 20 mm I-beam. Within the
thickness of 14 mm (t), the yoke only need to use 1 yoke washer. The thickness of
14-20 mm (t), the yoke need 2 washers. We do NOT suggest to install the HVLS Fan on
the fabricated I-beam, please consult with structural engineer to make sure your
building is approved for fan installation.
I-beam shim

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
13
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
Inside the box
Main Box
Yoke*1
Fixed angle mound
bracket*1
Motor*1
Remote
Control*1
Extension Tube*1 Extension Tube
Shield*2
Safety Cable*1
Wire Rope
Clamp*20
Hardware and Bolt Kits
Fixed angle
mount bracket
shim*2
I beam shim
*4
I beam clamp
*2
Winglet*7
Extension
Tube clamp
*2
Guy wire
bracket *2
Turn buckle
*4
Beam Clamp
Set*4
Ferrite Bead Clamp*1 Earth Wire*1
Airfoil Box/ Anodized Aluminum Airfoils /
Airfoils*7

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
14
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
Tools Required for Installation
Fan Diagram
Mechanical Installation Electrical Installation
Standard wrench/socket set Phillips screwdriver
Standard Allen wrench set Flat head screwdriver
Hydraulic cutter Multimeter
Galvanized wire Ø4 mm (Trim the wire
length according to the situation)
Pair if #10 to #14 AWG strippers
Torque wrench 50~300 kgf.cm (For
inspection purpose)
Electronic level

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
15
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
Pre-Installation Checklist
Equipped with appropriate mounting kit for roof pitch.
The fan can only be mounted to the I-beam. DO NOT mount the
fan directly to a single stringer, truss shelf or light steel shelf. For
installation methods not included in this manual, please consult a
structural engineer.
The mounting structure approved by structural engineers.
The mounting system must be able to withstand the torque generated by
the fan.
Having been familiar with the functions of the safety cable.
。
For the fan installation, the fan blades should be at least 10 feet (3.05
meters) above the ground. (Please refer to “The Placement Clearance
between fan and obstructions ” Page 9)
For the fan installation, the distance between the blades and other
objects/building structure should be at least 2 feet (0.6 meters).
(Please refer to “The Placement Clearance between fan and obstructions ”
Page 9)
The distance between the fan and other objects means the distance
between the blade tips and the objects. The center-to-center distance
between two fans should be at least 2.5 times the diameter of the fans.
(Please refer to “The Placement Clearance between fan and obstructions ”
Page 9)
When installing the fan, make sure the fan is not affected by high winds
from HVAC systems or large garage doors. Please refer to “The Placement
Clearance between fan and obstructions ” Page 9)
The yoke kit size should match the I-beam. (Please refer to “I-Beam” Page
11)
The power supply unit complies with the specification of the frequency
converter, and the wires pass through the fan installation position.
For power requirements, please refer to voltage sticker on the fan
The airfoil should not be mix up with other airfoil boxes.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
1
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
Installation Method
1. Secure the yoke to the I-beam
with 4 sets of yoke M10x50L
4 bolt kit.
(Recommended Tightening
Torque
:
24 N.m(240 Kgf.cm))
2. Attach the fixed angle mount
bracket to the yoke
horizontally, and tighten with
4 sets of Fixed angle mount
bracket M10x35L 4 bolt kit.
(Recommended Tightening
Torque
:
24 N.m(240 Kgf.cm))
3. Attach the Fixed angle mount
bracket shims to the Fixed
angle mount bracket, and
fixed them by Extension tube
M10x70L 3 bolt kit on the top
position as picture shows.
(Recommended Tightening
Torque: 24 N.m(240 Kgf.cm))

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
17
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
4. Insert the extension tube into
the upper screw on fixed angle
mount bracket ,and tighten
with the 2 sets of Extension
tube M10x 70L 3 bolt kit.
(Recommended Tightening
Torque
:
24 N.m(240 Kgf.cm))
5. Insert the extension tube
clamp into the extension tube,
make sure the chamfer as
picture shows is downward,
and tighten with 6 sets of
extension tube clamp M8x 15L
6 bolt kit.
(Recommended Tightening
Torque: 12 N.m(120 kgf.cm)
6. Insert the motor tube in the
extension tube clamp, then
take out the earth wire and guy
wire bracket as picture shows
to tighten with motor tube
with 3 sets of M8x 55L 3 bolt
kit.
(Recommended Tightening
Torque
:
12 N.m(120 Kgf.cm))
Upper Screw
Earth Wire Guy Wire Bracket

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
18
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
7-1 Route safety cable and wrap it
around the I-beam, securely
lock the wire rope clamp.
7-2 The end of the safety cable
must be tighten as picture
shows, make sure the
U-shaped inside the wire
rope clamp is tighten to the
short side.
a. Wire Rope Clamp*4
b. Safety Cable*1
8-1 Through Earth, Live and
neutral wires into ferrite bead
clamp, and wrap a circle.
8-2 Connecting the Earth, Live
and neutral wires with motor
and mains power.
(Please refer to “Wiring Diagram”
Page 15)
L
:
Live wire
N
:
Neutral wire
E
:
Earth wire
U-Shaped
Short side Long side
Mains
Power
Safety Cable
Ferrite
Bead
Clamp
(N) (L) (E)

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
19
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
9. Secure the extension tube shied
with extension tube shield
M6x16L 4 bolt kit after fasten
the all the safety cables and
wires. Be careful and do not
damage the wiring.
Notes
:
Fasten one side first with 4
sets of extension tube shied blot
kit while installing on extension
tube.
(Recommended Tightening
Torque
:
5 N.m(50 Kgf.cm))
10-1 Prepare 4 guy wires with
Ø4mm when installation. (The
technician needs to prepare
guy wire ,and tailor it
according to the situation)
10-2 Looking up from the bottom
of ceiling fan, the angle
between each cable and
I-beam is recommended to be
45-degrees.
10-3 The angle of the cables
should be 45 degrees angle
from horizontal surface.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
20
SUNONWEALTH ELECTRIC MACHINE INDUSTRY CO., LTD.
UFO 3 INSTALLATION (2019.12.23) V1
11-1 To speed up the process,
you can proceed 4 sets of the
beam clamp as picture shows
on the ground, secure the
beam clamp tightly.
11-2 Tailor the guy wire according
to the situation.
Guy Wire Bracket
:
(Recommended Tightening
Torque
:
5 N.m(50 Kgf.cm))
Beam Clamp Set, Guy Wire
Bracket
4 8
12-1 Attach the beam clamps to
the I-beam and securely fasten
to the proper position based
on step 11.
12-2 Pass the safety cable
through the ring and secure
with guy wire bracket.
Beam Clamp Set
:
(Recommended Tightening Torque
:
12 N.m(120 Kgf.cm))
This manual suits for next models
7