6. Preparing for Operation and Operation Order
6.1 TSEFB wall installation, connection to the heating system and testing should be performed by qualified personnel
in compliance with the requirements of the project and all the installation and operation rules. Before connecting TSEFB,
thoroughly rinse away any dirt from the heating system.
ATTENTION!
Protective connection to Earth required.
Check all wiring connections including factory connections before switching on.
Water must be treated with the correct concentration of inhibitor.
Failure to follow these instructions will void the product warranty.
Forced circulation of water through TSEFB provides a circulation pump.
The heating system (see Figure 1) must have the pressure relief valve (Pmax = 1.5 Pnom = 3 bar).
ATTENTION! Lack of pressure relief valve and damage during installation can lead to failure of the boiler
under abnormal operating conditions.
6.2 Remove the front panel by unscrewing the mounting screws, place TSEFB on the wall vertically in the prepared
place and outline two metal mounting anchor bolts (mounting holes shown in Fig. 2).
Pushing TSEFB aside, drill in the wall 8 mm holes per marking to a depth of at least 35 mm, put into the holes anchor
bolts and secure them by spreading out the metal collet (tightening the nut).
Before final installation, check the load bearing capacity of bolts and wall (taking into account the weight of TSEFB
with water). Set TSEFB on anchor bolts and secure with lock nuts M6 through spring washers.
Connect TSEFB to the heating system, connect the power cable with the grounding conductor in accordance with the
marking (F, N, PE/A, B, C, PE). Conduct an external inspection of parts to identify and resolve problems.
6.3 After verifying that the heat carrier is in the heating system and the integrity of the system, turn TSEFB on in the
following order: Set the thermostat handle to the position that corresponds to the maximum temperature (turn fully
clockwise), check voltage and turn on the opening line circuit breaker supplying power to TSEFB (the housing network
lamp lights up) and consistently (at intervals of 3-5 s) push key of heating mode switches: 1, 2, 3. This enables THE,
and the water warms up. Check the heating and circulation of the carrier.
6.4 The flow temperature on the thermometer is set by a handle of thermo-controller and corresponding heating stage
key. Subsequent operation of TSEFB is in automatic mode, and the desired temperature is maintained constant with
possible deviations within the band (4 - 8) °C.
6.5 To turn TSEFB off, it is necessary to turn the thermostat knob counter-clockwise until it stops (position
corresponding to tmin), disable "Heating" keys and in (3 - 5) min the automatic circuit breaker in the fixed wiring.
7. Maintenance
7.1 Prior to commissioning, as well as two hours after the start and periodically, at least once a month, you need to
check the reliability of fastening of wires, cables, tightening of threaded connections. If necessary, tighten
connections, avoiding damage that affect the subsequent use of TSEFB.
7.2 A company that performs installation and maintenance of TSEFB must be experienced, trained or licensed to
perform this work.
7.3 Servicing TSEFB is allowed to persons who have studied the operating principle, structure, mode of operation,
and have been instructed in safety and got admission to perform this type of work.
7.4 For the operation of apparatus and components of a heated system without damage due to deposits of scale and
sludge or corrosion of metal, the circulating water and feed water used should be suitably treated. Indicators of water
quality must meet the following requirements: the total hardness less than 20 uEg/kg, the contents of mechanical
impurities and suspended particles in the water are not allowed. Ways to treat water, which guarantees the fulfilment
of these requirements must be selected by the owner or specialised organization (project or maintenance).
7.5 Periodically check the operation of the safety valve, i.e., check water drain at least 1 time in 6 months.