1. Index
DoorLIFT DL-6
Remote door system
Installaon guide
Index
1Index 3
2 Pre-installaon requirements 4
2.1 General review 4
2.2 Ensure adequate clearance above door 5
2.3 Change the top roller brackets 5
2.4 Body specic requirements 6
3Electrical planning 7
4Track installaon 8
4.1 Posioning the rail on the roof 8
4.2 Fastening the rail to the roof 9
5Installing the door connector plate 10
6Installing turnbuckle connecng rod 11
6.1 Installing the turnbuckle connecng rod 11
6.2 Checking the turnbuckle connecng rod 13
7Installing the emergency release cable system 14
7.1 Drilling the holes 14
7.2 Installing the lock 14
7.3 Installing the release cable 15
8Installing the control box 18
8.1 Mounng the control box 18
8.2 Feeding the cable through the box 18
8.3 Connect the cable to the control box 19
8.4 Connect the cable to the track 19
8.5 Oponal funcons 20
8.6 Connect to the baery 21
9Adjusng the sensors 22
9.1 Adjusng the door closed sensor 22
9.2 Adjusng the door open sensor 24
10 Programming remote controls 25
11 First operaon of the system 26
12 Overview of electronic indicators 28
13 Appendix A - Push buons (DL-8000810) 30

4
DoorLIFT DL-6
Remote door system
2. Pre-installaon requirements
The DoorLIFT is intened as an auxiliary system for a manually operated shuer door. The DoorLIFT is a heavy duty
cycle drive system which requires consistent, reliable power. To secure a good working operaon, please follow
the below quesons before starng the installaon.
As well as ensuring the body and vehicle can accept the DoorLIFT, it’s important that the door is compable. Use
the following checklist to ensure the door is in good working condion.
1. Has the correct balancer been installed on your Roll-Up door?
2. Is the radius of the track suitable for DoorLIFT operaon? The DoorLIFT might have diculty with ght radius
tracks during the closing cycle.
3. Is the Roll-Up door balanced properly? Does it work easily, UP or DOWN by hand?
4. Is the door in good working condion? Make sure there are no broken panels, hinges or rollers etc.
5. Is the top panel of the door strong enough, or will it require reinforcement to prevent it from “exing” during
the closing cycle?
6. Is the power supply adequate? The system requires a 12 or 24 volt, 65 amp source. Has the baery and charging
system been well maintained? Baeries that are poorly maintained or highly discharged may not be able to
operate the system. The “Low voltage” indicator will shut system down when the power supply in not sucient.
7. Will a proper power supply always be available? In a trailer applicaon a secondary power supply may be
required when the tractor is absent.
8. The DoorLIFT is oponally supplied with two remote transmiers. Will that be adequate or will alternave
acvaon devices be required? Addional remote transmier, remote switches, etc. These items might be
useful for dock workers or others who may need access to the cargo area of the truck or trailer.
If any of the above answers are "no", do not connue with the DoorLIFT installaon and contact your
dealer for installaon support.
2.1 General review
Installaon guide

5
DoorLIFT DL-6
Remote door system
2.2 Ensure adequate clearance above door
Check to ensure you have enough clearance above the open door to
allow the top edge of the door to go through the radius. Make sure
there is a minimum of 45mm between the door and the ceiling.
Check if you are using the right type of top closure arm for you door
(see secon 2.3 below).
If there isn’t enough clearance contact your shuer door supplier to
enquire whether the track can be modied to allow installaon of
the DoorLIFT.
2.3 Checking the top roller brackets
Make sure that the right type of top closure arm is installed on your
door to be sure that the door closes in the right way. You will need
an adjustable type with two rollers to give the best result.
This also will give you a beer clearance between the door and the
ceiling.
If you have any doubts, please contact your shuer door supplier
for assistance.
Installaon guide

6
DoorLIFT DL-6
Remote door system
1. In case the track will be mounted to
roof bows a reinforcement (A) at the
header (above the roller shuer) could
be necessary, as forces applied upwards
can go up to 1000N. In worse case, it
can li the roof.
2. Never glue the complete track against
the roof. In case of installaon errors or
future repairs, it should be possible to
disconnect the track from the roof.
3. Keep a minimum clearance of 700 mm
behind the track! This because for a
proper service to the system the motor
unit needs to be removed from the
track. This only can be done by
removing the rear cover and slide the
700 mm long motor unit out of the
track.
Note: If the length of the aluminium
track needs to be reduced, the cut must
be made at rear of the track (furthest
from the door opening). The shortest
length of track required, to operate
properly is: door height + 92 cm.
4. Shuer door reinforcement is needed in
case of a plasc type door or a thin
wooden door. Consult with your doorli
supplier if this is needed on your roll-up
door.
2.4 Body specic requirements
As every vehicles body is dierent, your Doorli supplier can not be responsible for the body specic mechanical
connecons to roof and shuer door. Although we strongly suggest:
A
700 mm
Installaon guide

7
DoorLIFT DL-6
Remote door system
3. Electrical planning
The rst decision to make is where to install the control module. Ideally this is to be installed as close to the baery
as possible keeping in mind the supplied baery cable is 2,5m long (or longer on request). Depending on which side
of the vehicle the baeries are on will determine the route of the DoorLIFT prole cable. Baery cable has a
diameter of 9mm while the prole cable has a diameter of 8,5mm. These will be relave if these cables are routed
into conduits.
The diagram below depicts suggested posions of the control module for trucks.
In small truck applicaons you could install the control module in the cab. This is only recommended if there is an
alternave entry into the cargo area, side door or cab pass-through. If the door does not open for any reason, you
will have no access to the control box without these alternave entry points.
Insulated trucks or trailers will require some addional support in the ceiling before installing the DoorLIFT rail. Do
not aempt to install the DoorLIFT track to an unsupported substrate. Track mounng measures for insulated retro
ts should of been accounted for already in the preliminary phase.
If installing auxiliary items such as switches, lights, etc, plan locaons and wiring routes. Note: these auxiliary items
are not included with the DoorLIFT and are supplied by the er or end-user.
Mounng details of the housing:
Doorli Control box
Baery (power supply)
Connecon ignion, buzzer and oponal controls
Doorli system
Prole cable
Installaon guide

8
DoorLIFT DL-6
Remote door system
4. Track installaon
4.1 Posioning the rail on the roof
Mark the center line on the roof and measure
100mm sideways, as in the picture.
BE AWARE: Check pre-installaon requirements (page 4) for any reinforcements needed.
NOTE: Depending on the roof/body structure the installer is required to decide on the type of fasteners and
amount of connecons.
NOTE: Keep a space of 20-30 mm between the front of the
track and the balancer
20-30 mm
Place the le side (facing the door) of the
track allong the line. Keep a clearance
between balancer and track.
BE AWARE: when the distance between track and balancer is too
much, it will hurt the operaon of the system.
Installaon guide

9
DoorLIFT DL-6
Remote door system
4.2 Fastening the rail to the roof
Use the groves in the track to DRILL the
required holes. The number of holes depends
on the roof structure. Minimum
requirements: front, back and middle of the
track. In case of dry freight applicaons,
always connect to every roof bow.
Insulated ceilings require furring strips or
some type of mounng brackets to secure the
track to the ceiling liner and roof. These
measures should of been accounted for in the
Pre Install Inquiry. DO NOT SECURE TRACK TO
THE CEILING LINER ONLY WITH NO SUPPORT.
Never glue the track to the ceiling
TIP: Moving the motor unit back and forth in the track in this step and the next
makes liing the track assembly easier. Move the lever, shown at the right, to
the manual posion. The motor unit can now be moved by hand. Moving the
lever towards the baery icon will put the motor unit back in automac mode.
Use large diameter head screws or rivets
where the screw heads or rivet heads do not
protrude more than 1.8mm from their seated
posion. The motor unit will hit the
protruding screw or rivet heads during its
travel if the heads protrude more than
1.8mm into its path of moon.
Secure the track to the roof. The number of
rivets is to be decided by the installer, as
every body is dierent. The aluminium prole
weighs approximately 14Kg and the motor
unit 7Kg.
* Important: Please drill and
install the fasteners using the
V-shaped guides on the track.
This will have motor clearance
implicaons if not followed.
Installaon guide

10
DoorLIFT DL-6
Remote door system
5. Installing the door connector plate
IMPORTANT: Page 6 indicated that top panel reinforcements may be required.
NOTE: Depending on the shuer structure the installer has to decide on the type of fasteners.
With the door in the closed posion and the motor
as close to the door as possible, raise the door
slightly to ensure the tab on the connector plate is
aligned with the tab on the motor unit. Once you
are sased with the posion of the connector
plate, secure it to the top panel.
Dry-freight door connecon plate
Insulated-freight door connecon plate
or
Place the door connecon plate in te
center of the door.
Center line Center line
9x
IMPORTANT: Conrm alignment with the motor unit
before drilling holes
Installaon guide

11
DoorLIFT DL-6
Remote door system
6. Installing turnbuckle connecng rod
50mm
Make sure the roll-up door is in the fully
closed posion.
Slide the DoorLIFT motor unit towards the
door, as far as it will go, then slide it back
from the stop screw approximately 50mm.
See marker on the track. Lock the motor at
this posion.
NOTE: This is very important! The motor
unit should never touch the screw.
Measure A
Dry freight
Meassure A
Insulated freight
Select the right holes and measure the distance in between
6.1 Installing the turnbuckle connecng rod
Installaon guide

12
DoorLIFT DL-6
Remote door system
NOTE: The operaon of the system will be interfered when the rod does protrude into the fork.
The length of the threaded rod is:
Measurement A - 70 mm
Cut the threaded rod to length
Install the connecon bar in the previous selected
holes and secure the nut.
13 mm
Installaon guide

13
DoorLIFT DL-6
Remote door system
30-45 degrees
25mm
Aer installaon the connecon bar should be in a 30-45 degree angle, when the door is in
closed posion.
The motor-unit should always be 25mm away from the end screw.
6.2 Checking the turnbuckle connecng rod
Installaon guide

14
DoorLIFT DL-6
Remote door system
7. Installing the emergency release cable system
7.1 Drilling the holes
Apply the drill template decal and align the le edge
of the template with the centerline of the connector
plate.
Drill the holes completely through as per drill
template.
7.2 Installing the lock
1. Locate the lock assembly, turn the key
90 degrees and remove the core of the
lock from the lock housing plate. Insert
the housing plate into the holes on the
face of the door. Use masking tape if
necessary to hold the housing to the
face of the door.
2. Select the appropriate length screw
from the kit and secure the interior
mounng plate to the housing.
Installaon guide

15
DoorLIFT DL-6
Remote door system
7.3 Installing the release cable
1. Insert the end of the cable with the stop into the
guide tube at door-end of the motor unit, push
the cable through unl you can see it in the
opening where the lever is. Insert the
stop through the release lever and
engage the lever (lock the DoorLIFT).
With the lever engaged, push the cable
50mm further into the motor. You can
temporarily hold the cable 50mm past
the lever with masking tape to keep it
from moving.
2. Slide the cable sleeve over the cable and 50mm
into the guide tube in the motor housing.
3. Mark the sleeve 25mm below the door
connector plate. Remove the sleeve and cut it
on the mark. DO NOT CUT THE CABLE. Slide the
sleeve back over the cable and into the motor
housing tube.
50 mm
Installaon guide

16
DoorLIFT DL-6
Remote door system
4. Ensure the cable is sll 50mm past the release
lever in the motor housing and the lever is sll
engaged. Using good quality cuers cut the
cable 25mm below the lock mounng plate. Not
using a proper tool to cut the stainless cable can
cause the end of the cable to fray and become
dicult to insert into the lock cylinder.
5. Slide the red tube, the 60mm piece of cable
sleeve and the plasc cover base over the cable.
Push the cable through the door and lock
housing so it protrudes through the face
6. Insert the cut end of the cable into the hole on
the back of the lock core. Secure the cable by
ghtening the set screw on the side of the core
with a 2mm Allen key. Be sure it is as ght as
possible. Insert the core into the housing, turn
90 degrees, and remove the key.
Installaon guide

17
DoorLIFT DL-6
Remote door system
7. Use the two screws provided to secure the
exterior cover over the lock assembly.
8. Locate and secure the rear cable cover on the
mounng plate using the two 4,8x32 screws pro-
vided. This cover also acts as a clamp for the
60mm secon of cable sleeve. Make sure the
cable sleeve ends in the middle of the lock. See
picture
9. Slide the cable sleeve up so there is a clearance
of 30mm to the red sleeve. Use the two 4,8x19
screws and plasc clamp to secure the cable
sleeve and clamp to the holes on the door con-
nector plate.
10. Make sure that the sleeve is only 50mm into the
guide tube and not protruding in the slot of the
motor-unit. This will prevent the lever from mo-
ving and the door cannot be disengaged anymo-
re.
Outside door
Installaon guide
30mm

18
DoorLIFT DL-6
Remote door system
8. Installing the control box
8.1 Mounng the control box
Mount the control box as determined earlier in the manual. Double check the points
below to ensure the ideal locaon.
Reminder: the standard baery cable is 2,5m long so the distance from
the box to the baery can’t be more than that. (longer cable on request).
Be aware: of the environmental condions of your chosen locaon when
the truck is in use. For example, placing the box behind the wheels could
result in high pressure water and road debris against the box.
Cable direcons
Make sure the cable connectors
are down to prevent moisture
entering the box
WARNING: The size of the supplied cable(s) is determined by the DoorLIFT power requirements. DO NOT splice
wires for extra length, this can cause voltage drop, resulng in poor/intermient operaon or damage.
Longer cable (ll 5m) is available on request.
DO NOT CONNECT THE BOX TO THE BATTERY YET
8.2 Feeding the cable through the box
Run the prole cable from the track to the control box. This cable comes in two pieces and will have to be spliced
with the solder/bu connector kit given in package. Match the color scheme below between the two cut cables.
Note: If the cable is too long, it can be cut accordingly.
WARNING: Be sure to protect all cables from sharp edges by using loom and or grommets whileroung cables
through conduits and bulkheads.
Installaon guide

19
8.3 Connect the cable to the control box
8.4 Connect the cable to the track
Plug the other end of the prole cable to the track plug. While connecng, push unl you
hear a "click".
DoorLIFT DL-6
Remote door system
Push in unl you hear it “click”
Plug the one end of the prole cable to the box. While connecng, push unl you hear a "click".
Push in unl you hear it “click”
Installaon guide

20
DoorLIFT DL-6
Remote door system
8.5 Oponal funcons
8-lead wire harness
Wire Item
1Up/down input
2Up input
3Down input
4Signal block (ignion lockout)
5+ 12V output (max 250 mA)
6Door ajar output (ground)
7Cargo light output (ground)
Yellow/green Ground (max 250 mA)
Connect auxiliary devices to the DoorLIFT control box through the 8
-lead auxiliary harness using the wire chart below as a guide. The
pig-tailed end of the harness has numbers.
The 8-pin male receptacle on the box comes equipped with a plug
to protect the connector from water and dirt if the harness is not
used. This plug is removed if the harness is ulized.
WARNING: Protect unused harness leads against water, debris, dust and possible short-circuits
Push in unl you hear it “click”
Installaon guide
Other manuals for DoorLIFT DL-6
1
Table of contents
Popular Gate Opener manuals by other brands

CAME
CAME U 8700 installation guide

Heras
Heras F422 Installation instruction

Viking Access Systems
Viking Access Systems X-390 Installation instructions and safety information

CAME
CAME F1000 installation manual

Genius
Genius FALCON 5 manual

Roger Technology
Roger Technology M30 Series INSTRUCTIONS AND RECOMMENDATIONS FOR THE INSTALLER

CAME
CAME STYLO Series installation manual

Nice
Nice RUN400HS Instructions and warnings for installation and use

BFT
BFT BAT installation manual

BFT
BFT BAT KIT 2 installation manual

LOCKEY USA
LOCKEY USA TB-950 Magnum installation instructions

Motorline professional
Motorline professional LINCE Series User's and installer's manual