
INSTALLATION & OPERATION
OPERATION
When the external controls are calling
for heat,and the temperature in the
monotube is below the temperature set
on the thermostat, the pump will run.
Once the flow through the boiler is
established and the temperature in the
boiler is below the one set on the boiler
thermostat, the water pressure switch
will allow the grey safety solenoid and
the blue first stage solenoid to open.
The ignition sequence begins. A
continuous, high speed stream of
sparks ignites the gas. Once the
ionisation circuit detects the flame the
orange secondary solenoid opens to
allow the full, or set, gas rate to the
burner. If a flame is not detected within
8 - 10 seconds the security solenoid
will close and shut off the gas. The red
lockout indicator bulb will light. The
temperature of the primary circuit is
sensed by the thermostat in the
monotube and the flow temperature of
the boiler is detected by the thermistor
in the flow pipe. These two thermostats
interact with each other and the boiler
thermostat must always be set above
the monotube temperature.
INSTALLATION REQUIREMENTS
Location
The Moduloflame 140 is wall mounted
and the position chosen should allow
adequate space for servicing and for
sufficient air flow around the boiler.
The location must permit the
satisfactory routing and termination of
the flue. The surface should be flat and
non combustible and able to
adequately support the weight of the
boiler and ancillary controls.
For guidance, a wall area of:
900 mm (36 ins) wide and 1185 mm
(47 ins) high would provide the
necessary clearances for case removal
and for air movement.
As it is an open flued appliance certain
locations are banned, for example
bedroom, bedsitting rooms, private
garages or rooms containing a bath or
a shower. A cupboard or compartment
used to house the boiler must have
been designed and constructed, or
modified, specifically for the purpose.
Refer to BS 6798 for further guidance.
Flue
The following notes are for general
guidance only. For detailed
recommendations refer to BS 5440:
pt 1.
There should be at least 600 mm of
vertical flue after the boiler before the
use of any bends. The flue must take
the most direct route practicable. The
number of bends must be kept to a
minimum. Long external runs and
Horizontal or slightly inclining runs
must be avoided.
Ventilation
The following notes are for general
guidance only. For detailed
recommendations refer to BS 5440:
pt 2.
The boiler must have a permanent air
supply. This may come from an
adjacent room or internal space which
must also have permanent ventilation
to outside or direct from outside. If the
supply is from another internal space
or room, that room must have a
permanent air supply at least the size
as required for the boiler. If installed in
a room, the boiler requires a vent with
175 cm2 free air space.
Where the boiler is installed in a
compartment, the air is supplied
through vents at high and low level as
shown in the chart below:
Note: both vents should communicate
with the same room, internal space or
be on the same wall to outside air.
If there is an extractor fan is installed
on the premises, a spillage test must
be carried out with the fan operating.
Position of air
vent Air from
room or
internal
space
350 cm2
700 cm2
Air direct
from
outside
175 cm*
--I
350 cm*
Gas Supply
Do not use pipe smaller than the boiler
gas connection which is 314” BSP. The
gas installation should comply with BS
6891. The meter and pipework must be
of sufficient capacity to supply the
boiler and other gas appliances. The
completed installation must be tested
for soundness in accordance with the
requirements of BS 6891.
Electrical Supply
The boiler requires an earthed 230V -
50 Hz single phase supply. It must be
possible to completely isolate the
appliance electrically. Connection
should be via a 3 amp fused double-
pole isolating or a fused three pin plug
and an unswitched shuttered socket
outlet. Either method must be in
accordance with the current I.E.E.
regulations. It should be readily
accessible and only supply the
appliance.
SYSTEM GUIDANCE
Flushing and Water Treatment
Before connecting to the system, the
pipework should be chemically
cleansed to remove metal filings,
solder, machining oils and other fluxes
and greases which might impair the
performance of the boiler and its
controls. Refer to BS 7593 (1992).
Consideration should also be given to
the treatment of the system water and
advice can be sought from the
manufacturers of water treatment
products such as
Betz Dearbon Ltd
Foundry Lane
Widnes
Cheshire
WA8 8UD
Tel: 0151 424 5351
Fernox Manufacturing
Britannica Works
Clavering
Essex
CBI1 4QZ
Tel: 01799 550811
If the boilers are being installed on an
existing system, a sump and drain
should be fitted on the heating return at
the lowest point. It is essential that the
system is fully flushed to remove any
sludge and debris before the boiler is
connected.
System Controls
The Moduloflame 140 is electrically
controlled and so most normal pumped
primary control systems can be used.
Please note that when thermostatic
radiator, or zone valves are used, the
controls should be so arranged as to
turn off the boiler when they are
satisfied. A by-pass will be necessary
to maintain a minimum flow rate of
27.5 I/h (6.05 g/m) 1.65 m3/h through
the monotube.
6