1.7 IMMERGAS FLUE SYSTEMS.
Immergas supplies various solutions separately
from the boiler regarding the installation of air
intake terminals and ue extraction, which are
fundamental for boiler operation.
Important: e boiler must only be installed
together with an original Immergas air intake
and ue gas exhaust system. is system can be
identied by an identication mark and special
distinctive marking bearing the note: “not for
condensing boilers”.
e ue exhaust pipes must not be in contact with
or be near to ammable materials. Moreover,
they must not pass through buildings or walls
made of ammable material.
See following paragraphs for the detailed descrip-
tion of the kits available.
Positioning of double lip seals. For correct
positioning of lip seals on elbows and extensions,
follow the direction of assembly given in gure
(Fig. 1-6).
• Resistance factors and equivalent lengths. Each
ue extraction system component has a Resi-
stance Factor based on experimental tests and
specied in the table below. e resistance factor
for individual components is independent from
the type of boiler on which it is installed or the
actual dimensions. It is, however, conditioned
by the temperature of the uids that pass throu-
gh the pipe and therefore varies according to
applications for air intake or ue exhaust. Each
single component has a resistance corresponding
to a certain length in metres of pipe of the same
diameter; the so-called equivalent length, obtained
from the ration between the relative Resistance
Factors. All boilers have an experimentally obtaina-
ble maximum Resistance Factor equal to 100. e
maximum Resistance Factor allowed corresponds
to the resistance encountered with the maximum
allowed pipe length for each type of Terminal
Kit. is information enables calculations to be
made in order to verify the possibility of various
congurations of ue extraction systems.
1.8 OUTDOOR INSTALLATION IN
PARTIALLY PROTECTED AREA.
N.B.: a partially protected area is one in which the
appliance is not exposed to the direct action of the
weather (rain, snow, hail, etc..).
• Conguration type B, open chamber and fan
assisted.
The relevant terminal must be used for this
conguration (present in the intake kit for the
installation in question), which must be placed
on the central hole of the boiler (Fig. 1-9). Air
intake takes place directly from the environment
in which the boiler is installed and ue exhaust
in individual ue or to the outside.
In this conguration the boiler is classied as
type B22.
With this conguration:
- air intake takes place directly from the envi-
ronment in which the boiler is installed and
only functions in permanently ventilated
rooms;
- the ue exhaust must be connected to its own
individual ue or channelled directly into the
external atmosphere.
The technical regulations in force must be
respected.
Flue gas separator adjustment. For correct
functioning of the boiler in conguration with
direct intake it is necessary to regulate the ue
gas shutter according to that stated in the relative
tables (Fig. 1-11).
• Cover kit assembly (Fig. 1-8). Remove the
two plugs and the gaskets present from the two
lateral holes with respect to the central one. Now
cover the right intake hole using the relevant
plate, xing it onto the le side using the two
supplied screws. Install the Ø80 outlet ange on
the central hole of the boiler, taking care to insert
the gasket supplied with the kit and tighten by
means of the screws provided. Install the upper
cover, xing it using the 4 screws present in the
kit, positioning the relevant gaskets. Engage the
90° Ø80 bend with the male end (smooth) in
the female end (with lip seal) of the Ø80 ange
unit until it stops. Introduce the gasket, making
it run along the bend. Fix it using the sheet steel
plate and tighten by means of the straps present
in the kit, making sure to block the 4 gasket
aps. Fit the male end (smooth) of the exhaust
terminal into the female end of the bend 90°
Ø80, making sure that the relevant wall sealing
plate is already tted; this will ensure hold and
joining of the elements making up the kit.
• Coupling of extension pipes. To install push-
tting extensions with other elements of the
ue extraction elements assembly, proceed as
follows: Install the pipe or elbow with the male
side (smooth) in the female section (with lip
seal) to the stop on the previously installed
element. is will ensure sealing eciency of
the coupling.
Max. length of exhaust duct. The flue pipe
(vertical or horizontal) can be extended to a
max. length of 12 m straight route, using insulated
pipes (Fig. 1-28). To prevent problems of ue gas
condensate in the exhaust pipe Ø80, due to ue
gas cooling through the wall, the length of the
pipe (not insulated) must be limited to just 5 m.
Example of installation with direct vertical
terminal in partially protected location. When
the vertical terminal for direct discharge of com-
bustion products is used, a minimum gap of 300
mm must be le between the terminal and the
balcony above. e height A + B (always with
respect to the balcony above), must be equal to
or greater than 2000 mm. (Fig. 1-10).
• Configuration without cover kit (boiler
typeC).
By leaving the side plugs tted, it is possible to
install the appliance externally, in partially co-
vered places, without the cover kit. Installation
takes place using the Ø60/100 and Ø80/125
concentric horizontal intake/ exhaust kits. Refer
to the paragraph relative to indoor installation.
In this conguration the top cover kit guarantees
additional protection for the boiler. It is recom-
mended but not compulsory.