
PowerGATE®ReadySwitch™
Installation – Initial Setup - Main Power
Step 1: Wiring the Main Terminals
WARNING
Ensure circuit breakers are OFF and the transfer switch is
locked out from utility power prior to connection.
Failure to install transfer switch will create the potential
for the generator to energize utility lines and endanger
utility personnel. Conversely, utility lines may energize
the PowerGATE® ReadySwitch™ and endanger generator
personnel.
The PowerGATE® ReadySwitch™ is for the connection to a
main panel of a structure, with an option to switch to backup
generator via a CAM-Type connection, such that the inlets are
only energized from the generator.
1. Pull the cables to the PowerGATE® ReadySwitch™
2. First, strip and install the ground cable to the ground terminal
block
A. NOTE: See Figure 5A
3. Tighten terminal screws to 375 lb.-in. torque each
A. NOTE: See Figure 9
4. If metallic conduit is used, connect ground wire from ground
bushing on conduit to the ground connection point in the
bottom left quadrant of the panel
A. Ground conductor must be a minimum of 2 AWG
B. NOTE: Conduit shall NOT be relied upon to provide
grounding protection to tap box
5. Continue to connect the neutral wire to the ground terminal
block. (Service Entrance rated models ONLY)
6. Verify the 3 phases of the service entrance
WARNING
Three phase power systems consist of three phase or hot
conductors that are shifted by 120 degrees. Three phase
loads such as motors may only work properly if the phases
are connected in the correct order. Some motors may work
when connected improperly, but will operate backwards.
Utility power and electrical generators may be wired either in
a clockwise or counter-clockwise order. It is important that
any generator connected to the PowerGATE® ReadySwitch™
is connected in the same rotation (clockwise or counter-
clockwise) as the utility power.
7. Connect the 3 phases of the switch here:
A. MAIN TERMINAL
B. BUILDING TERMINAL
8. Replace dead front panel and secure using hardware
Place rotation label here
WARNING
AVERTISSEMENT
Risk of Electric Shock
Plug connection should be in the following order:
1) Equipment grounding conductor connectors,
2) Grounded circuit conductor connectors, and
3) Ungrounded conductor connectors.
Disconnection should be in the reverse order”
Risque de choc électrique
Le raccordement devrait être effectué dans l’ordre qui suit:
1) Conducteur de mise à la terre de l’appareillage
2) Conducteur du circuit mis à la terre
3) 3) Conducteurs non mis à la terre
La mise hors tension doit se faire dans l’ordre inverse
DANGER
HIGH VOLTAGE
KEEP OUT
HAUTE TENSION
NE PAS TOUCHER
Do not start the generator until all connectors are connected
or made to be inaccessible. Any terminal may be energized
when any cable is connected. De-energize cables at the
generator prior to connecting or removing any connectors
Ne pas mettre la génératrice en marche avant que tous les
connecteurs soient connectés ou rendus inaccessibles.
N’importe quelle borne peut être mise sous tension si un
câble est raccordé. Débrancher les câbles à la génératrice
avant de brancher ou de débrancher les connecteurs
DANGER
Model
Rating
S/N
Transfer Switch Accessory
Made in USA
www.lexproducts.com
1-800-643-4460
LBL-PGIP
TYPE 3R
RAINPROOF
A
LBL-A
B
LBL-B
C
LBL-C
N
LBL-N
G
LBL-G
DANGER
HIGH VOLTAGE
KEEP OUT
HAUTE TENSION
NE PAS TOUCHER
DANGER
DANGER
DANGER
HIGH VOLTAGE
KEEP OUT
HAUTE TENSION
NE PAS TOUCHER
DANGER
Do not start the generator until all connectors are connected
or made to be inaccessible. Any terminal may be energized
when any cable is connected. De-energize cables at the
generator prior to connecting or removing any connectors
Ne pas mettre la génératrice en marche avant que tous les
connecteurs soient connectés ou rendus inaccessibles.
N’importe quelle borne peut être mise sous tension si un
câble est raccordé. Débrancher les câbles à la génératrice
avant de brancher ou de débrancher les connecteurs
Risk of Electric Shock
Plug connection should be in the following order:
1) Equipment grounding conductor connectors,
2) Grounded circuit conductor connectors, and
3) Ungrounded conductor connectors.
Disconnection should be in the reverse order
Risque de choc électrique
Le raccordement devrait être effectué dans l’ordre qui suit:
1) Conducteur de mise à la terre de l’appareillage
2) Conducteur du circuit mis à la terre
3) 3) Conducteurs non mis à la terre
La mise hors tension doit se faire dans l’ordre inverse
WARNING
AVERTISSEMENT
C
LBL-C
3Ø Power
Counter
Clockwise
3ØPower
Clockwise
3Ø Power
Clockwise
3Ø Power
Counter
Clockwise
LBL-PGIP-D1LBL-PGIP-D2LBL-PGIP-W1
Apply 1 to inside door of
Input Panel Connection Chamber
LBL-PGIP-ROTATION
Figure 7
Figure 8
P/N: LBL-PGIP-ROTATION
Figure 7A
P/N: LBL-SERVICEDIS
(Label only applicable for Service Entrance rated version of ReadySwitch)
Installation – Initial Setup - Main Power (continued
Step 2: Determine Phase Rotation
The following information will be needed when connecting a
generator:
1. Determine phase rotation of the utility power
A. Connect a phase rotation meter to a three phase power
source in the building and record whether the building is
wired clockwise or counter-clockwise
2. Apply the provided label (Figure 7) to the inside of the
PowerGATE® ReadySwitch™ on the inside of the cam
connection chamber door. (Figure 8)