Maico BSB FSD-TD Series Manual

V12109
Installation, Operation and Maintenance Instructions
SD-TD Series
M A N U A C T U R E R S O A I R , I R E A N D S M O K E P R O D U C T S
M
A
D
E
I
N
B
R
I
T
A
I
N
SD-TD ire and Smoke Damper
1. Health and Safety
1.1 Only competent personnel may carry out the work outlined within this document.
1.2 The wearing of appropriate Personal Protective Equipment (gloves, footwear, safety glasses etc.) is
required for safe working and as the site dictates.
1.3 Dampers may be heavy. Large dampers will require suitable lifting and supporting equipment, with
due consideration given for manual handling.
1.4 Dampers may close without warning. Do not introduce limbs/fingers between blades whilst the
actuator is fitted.
1.5 Where dampers are only accessible with the need for additional elevation, any equipment used
should be done so with due consideration to the Work at Height regulations 2005 and current site
rules.
1.6 All work should be carried out in accordance with HSE guidelines and regulations and any specific
local site rules.
2. Important
2.1 These instructions should be read in its entirety before commencing work. The installer must be
Competent with the manufacturer’s fire barrier separating element construction.
2.2 Actuators are IP54 rated – Check actuator connection box is suitably located.
2.3 Do not cut/shorten the Thermal use lead (-T Actuators). This will render the unit inoperable and
invalidate the warranty.
2.4 Where an actuator is supplied with a Thermal use (T ), the T MUST be fitted in accordance with
Section 15. ailure to meet this requirement will invalidate the warranty and the damper will fail to
respond as designed/tested.
2.5 All ire / Smoke Damper installations must be installed to a BSB tested method and carried out to
the satisfaction of the appropriate Building Control officer and/or specifying authority.
These instructions must be left with the damper
ig. 1
Page 1

SD-TD - Installation Operation and Maintenance Instructions
2. Important continued
2.6 Refer to actuator label for wiring of actuator and page 12.
2.7 Refer to section 19 for testing. Complete Installation Check List (at end of this document) and retain
for future reference.
2.8 or existing dry walls – When cutting the opening for damper, and (partial) removal of stud is
unavoidable, ensure the structure is sufficiently supported to conform to the design specification.
See Page 2.
2.9 Dry wall openings must be lined. Please see page 2.
2.10 Ensure that appropriate ‘fire-rated’ plasterboard is used throughout the construction of drywall
partitions that need to act as fire separation barriers.
2.11 Ductwork to be fitted and connected to the damper spigot in accordance with DW 144/145.
Aluminum rivets should be used (to act as breakaway joint).
2.12 Where more than one duct penetrates a wall or floor, adjacent fire damper assemblies should be
separated by a structural element with a minimum width of 200mm (to comply with
BS EN1366-2 13.6).
2.13 EMinimum distance from adjacent dampers and structures.
ire dampers must be separated by a structural 200mm minimum distance between cases and
have a minimum 75mm between the fire damper case and a construction element (wall/floor).
Other services should not share the same opening as the installed damper.
3. Equipment Required
3.1 Equipment and tools will vary dependent upon the fire barrier construction that the damper is being
installed within. Standard equipment normally used for the building of the particular barrier should
suffice.
3.2 Access-equipment as necessary.
3.3 Temporary support equipment (to retain damper in position).
3.4 Cordless drill with 2,5mm and 10mm drill bits for fitting T .
3.5 4mm (drywall) and 8mm (concrete/masonry) drill bits as required, for the A fixing frame fixing
holes.
3.6 Phillips №2 screwdriver to suit thermal fuse screws.
3.7 Screwdriver to suit junction box terminals.
3.8 8mm A/ spanner for motor fixing bolt.
3.9 12mm A/ Spanner for TD drive shaft.
4. Preparation for Installation
4.1 or each damper installation type, refer to the relevant installation detail below.
4.2 Remove packaging materials with the exception of the actuator packaging - leaving this in place will
protect the actuator wiring / thermal fuse whilst the damper is being installed.
4.3 Before installation, the damper should be inspected to ensure that it has not been damaged and is
in good condition.
4.4 Check damper (label) reference and size to site specification.
4.5 Determine required position of damper. Check sufficient space exists to fit the product. Ensure any
services (e.g. electrical/plumbing) within the structure or running close to the structure will not be
affected.
4.6 Consideration should be given to the depth of the wall, relative to damper case length, ensuring that
the case is not exposed once fitted.
4.7 Drill the relevant peripheral EASY IX ® pilot holes for the wall type.
Page 2

SD-TD - Installation Operation and Maintenance Instructions
Page 3
5. Dry Wall Preparation - ig.2
5.1 Preferably, prepare the opening whilst building the fire separation barrier,
or cut opening if barrier already exists. (see 2.8)
5.2 (CL) Cleated and rameless Installations
5.2.1 The finished aperture size to be nominal duct width +160mm and nominal duct height
+100mm.
5.3 (A ) EASY IX ® Angle rame Installations
5.3.1 The finished aperture sizeshould have an allowance of 10mm between the damper case
and the finished aperture size top and bottom. An allowance of 10mm on the non actuator
side and 35mm on the actuator side between the damper case and finished aperture size.
to be nominal duct width +125mm and nominal duct height +100mm.
5.3.2 Ensure that the metal track is fitted between the plasterboard as shown in ig. 2 and that
the aperture is lined out with 12.5mm minimum fire board providing the finished aperture
size.
5.3.3 Mark out the position and size required on the wall, taking into account the fire board
thickness used for lining out.
5.4 Using appropriate means (e.g. jig saw), cut the hole in the wall, removing each layer and any infill
that is present.
5.5 Cut 2 pieces of steel track equal opening width.
5.6 it track to top and bottom of opening, screwing in position from both sides of wall at each end of
track with drywall screws and at maximum 300mm centers.
5.7 Cut 2 more pieces of track, equal to the opening height.
5.8 it track to sides of opening, screwing in position in a similar manner as above.
5.9 Cut 4 ‘batons’ of board to suit opening. Screw each baton with 25mm drywall screws @max 300mm
pitch to the track that is lining the opening. Ensure batons are flush with the surfaces of the wall.
ig. 2 ire separation barrier
Dry Wall Construction
Steel track fitted to all four
sides of the opening
12.5mm ire board
lining the opening and
fitted flush to each side

SD-TD - Installation Operation and Maintenance Instructions
Page 4
6. Dry Wall – (A ) EASY IX® Angle rame Installation – ig. 3
6.1 Drill out the inner row of 2mm diameter angle frame pilot holes to 4mm diameter.
6.2 Position the damper centrally in wall opening (width/height), with blades running horizontally. Using
the inner row of pilot holes, screw the EASY IX® angle frame to the wall using drywall screws @
150mm max pitch.
6.3 It is not a necessity to fill the void behind the angle frame, but suitable fire rated infill may be used if
considered required for insulation purposes.
6.4 Important: Ensure the screws ‘pick up’ the track lining the hole, so that the proper fire integrity of the
installation will not be compromised.
6.5 On the reverse side, fit a single layer pattress around the damper spigot using drywall screws of
appropriate length to screw into the steel tracking around the opening.
ig. 3

Page 5
SD-TD - Installation Operation and Maintenance Instructions
7. Masonry Wall – (A ) EASY IX® Angle rame Installation – ig. 4
7.1 Preferably, prepare the opening whilst building the wall, or cut an opening if the
wall already exists.
7.2 The damper is not load-bearing and additional support for the top of the wall opening is achieved by
means of a lintel or other approved method.
7.2.1 The finished aperture size to be nominal duct width +125mm and nominal duct height
+100mm.
7.3 Mark out the position and size of the required cut size on the wall.
7.4 Make the hole in the wall. Oversizing the hole will require BCO approval to install the damper.
7.5 Prepare a pair of spacing blocks, (approx. 10mm high x 25mm square) from any available material
(such as drywall boards). Position spacing blocks within the opening at extremities of damper and
stand the damper (with blades running horizontally) on blocks so that damper is central in opening.
7.6 Drill out the outer row of 2mm diameter angle frame pilot holes to the appropriate size.
7.7 ix the angle frame to the wall using suitable steel sleeved wall anchors in the
drilled holes.
7.8 It is not a necessity to fill the void behind the angle frame.
7.9 Important: Ensure that the fixing anchors are located 20mm min from the opening’s
edges, so that the proper fire integrity of the installation will not be compromised.
Using the EASY IX® flange system and following the instructions for making the aperture will
ensure a correct fit is achieved.
7.10 On the reverse side, fit a single pattress layer.

Page 6
SD-TD - Installation Operation and Maintenance Instructions
7. Masonry Wall – (A ) EASY IX® Angle rame Installation – ig. 4 continued
ig. 4

SD-TD - Installation Operation and Maintenance Instructions
8. Concrete loor – (A ) EASY IX® Angle rame Installation – ig. 5
8.1 Preferably, the opening would have already been formed. If not, cut an opening
in the floor ensuring that the correct finished size is achieved.
8.2 Mark out the position and size of the required cut size on the floor.
8.3 Make the hole in the floor.
8.4 Check that the prepared finished opening before placing the damper in the floor
8.4.1 The finished aperture size to be nominal duct width +125mm and nominal duct height +100mm.
8.5 When placing the damper into the hole, ensure that it sits central in both width and depth.
8.6 With damper in place, drill the 2mm diameter outer pilot holes (View A) out and into the concrete floor to
the appropriate size.
8.7 Place damper in prepared hole and secure in place.
8.8 ix the angle frame to the floor using suitable steel sleeved anchors min Ø6.5mm.
8.9 It is not a necessity to fill the void behind the angle frame.
8.10 Important: Ensure that the fixing anchors are located 20mm min from the opening’s edges, so that the
proper fire integrity of the installation will not be compromised.
Using the EASY IX® flange system and following the instructions for making the aperture will ensure a
correct fit is achieved.
Page 7
ig. 5

SD-TD - Installation Operation and Maintenance Instructions
9. (H ) HEVAC rame Installation (wall and floor) Procedure - igs. 6-8
9.1 Preferably, prepare opening whilst building the wall/floor (or cut an opening if the wall/floor already
exists).
9.2 inished sizes should be 50mm min to 100mm max > HEVAC frame assembly extremities.
9.3 The damper is not load-bearing and additional support for the top of the wall opening is achieved by
means of a lintel or other approved method.
9.4 it looped steel wall anchors (06mm min) all round the inside of the opening in corresponding
positions to the HEVAC frame builder's ties.
9.5 Bend the builder's ties out. (See ig. 6)
9.6 (Vertical installation only) Prepare a pair of spacing blocks, (approx. 25mm cubed) from any
available material (such as drywall boards). Position spacing blocks within the opening at
extremities of damper and stand the damper on blocks so that damper is central in opening.
9.7 While supporting the damper centrally in the cavity, secure the builders ties to the looped wall
anchors with 1.5mm galvanized steel wire. (The loops must be tight and a minimum of 3 loops is
recommended). (See ig. 7)
9.8 ill the surrounding cavity with 4:1 mortar and finish to desired standard.
Page 8
ig. 8 ( loor)

Page 9
SD-TD - Installation Operation and Maintenance Instructions
9. (H ) HEVAC rame Installation (wall and floor) Procedure - igs. 6-8
continued
ig. 8 (Wall)

Page 10
SD-TD - Installation Operation and Maintenance Instructions
10. Rockwool Ablative Batt Penetration Seal - ig. 9
10.1 Prepare the Dry Line Wall section as shown. Two layers of fire board either side of the metal track
forming the aperture and line with a single layer of fire board.
10.2 Using threaded drop rods of the correct length affixed to the underside of the slab/soffit, pass the
other end through the damper cleat hole to provide support prior to fitting the fire batt into position.
See ig.12 for general connection detail.
10.3 Ensure the damper is level and will align with any connecting ductwork.
10.4 Ensure that all connecting edges including the perimeter of the fire batt and between the A return
and fire batt have ire Pro glue applied as directed by the manufacturers directions.
10.5 The ire Batt is better to be slightly over sized that allows for a firm push into place, than fitted
loosely.
10.6 Once the ire Batt has been fitted, apply a 10-15mm bead of Rockwool irePro acoustic
intumescent sealant around the perimeter on both sides. please see ig. X.
10.7 It is preferable to allow the intumescent sealant to cure before connecting any ductwork.
10.8 Ensure that the Thermal use that is wired into the fitted actuator remains protected until fitted into
the ductwork.
ig. 10
Drop-rod load bearing specification
Drop-rod
Size
Max. load per pair of studs (kg)
E60 E120 E240
M6
M8
M10
M12
54.7
100.4
159.8
233.1
36.5
66.9
106.6
155.4
21.9
40.2
63.9
93.2
ig. 9

Page 11
SD-TD - Installation Operation and Maintenance Instructions
11. {SA) Sleeve and Angle Installation Procedure - ig. 11
11.1 This installation method is suitable for all wall structures (the installation shown
here is in a dry wall for information purposes).
11.2 If need be, to ease connection to ductwork, connect stub duct(s) to damper spigot(s) before
positioning damper in wall opening.
11.3 it sleeve around damper using 16off steel pop rivets (provided).
11.4 it sleeve around damper using 16off steel pop rivets (provided).
11.5 Drywalls must be 'lined' so cut hole size is Sleeve OAL + 2 x wall board thickness+10mm (it is
acceptable to have zero gap at bottom and 20mm gap at top). Also refer to 2.8
11.6 Block Work Walls, cut size = finished size.
ig. 11

SD-TD - Installation Operation and Maintenance Instructions
11. {SA) Sleeve and Angle Installation Procedure - ig. 11 continued
11.7 By using appropriate means, make and finish hole in wall. Ensure both surfaces of wall around
perimeter of opening are flat and smooth to allow angle to be fitted without gaps in excess of 2mm.
11.8 Position and temporarily support damper centrally in wall opening.
11.9 There are 8 off 'angle' pieces provided, 4off for the 'sides' and 4 for top/bottom of the sleeve. The
'sides' are identified with an 'S' close lo 1st tabbed end of each piece. Be especially careful when
the lengths of T/B nearly are same as the sides.
11.10 it to one side of wall, 1st angle assembly. it this to sleeve by positioning around sleeve, fitting
tabs through slots, and bending tabs lightly with hammer to begin with, and when all are positioned
correctly, and 1st angle assembly is flush up to wall, knock all four down fully to secure.
11.11 Rivet 1st angle assembly to sleeve with 3mm min steel pop rivets at max 150mm centres all round,
tight and flush against surface of wall. Check gaps (if any) between angle and wall are less than
2mm.
11.12 it second angle in similar manner to 1st making sure both angles are tight up against wall
surfaces and all gaps (if any) are less than 2mm.
11.13 Do not fix angles to wall, as damper should be free to move within opening.
11.14 Connect ductwork as required.
12. Dry wall - (CL) Cleated Installation Procedure - ig. 12
12.1 Refer to section 5 for wall preparation instructions.
12.2 This installation method is to be followed when extra support is required due to the damper size
(weight) or other factors.
12.3 Ensure that the supporting drop rods are suitably sized for the damper. (Refer ig. 9)
12.4 Ensure that the drop rods are anchored/fastened in the top-supporting structure.
12.5 Depending on wall thickness, it may ease connection of ductwork, if connecting ductwork is
attached to damper prior to fabricating the wall.
12.6 Plasterboard pattress (16 off piece of the same material as main wall construction), should be
sufficiently wide to butt up to damper spigots/duct and overlap the outer edge of the track lining the
opening by at least 10mm. They need to be long enough to form neat comers.
12.7 Two layers of pattress are required each side of wall and the corners should 'overlap' between the
first and second layers.
12.8 it second pattress to other side of wall in similar manner.
12.9 Apply intumescent sealant to the pattress parts and fit snugly up against the spigot.
12.10 It is not a necessity to fill the void between the pattresses, but it can be done for insulation purposes
if desired.
12.11 Important: Ensure the drywall screws 'pick up' the track lining the hole, so that the proper fire
integrity of the installation will not be compromised.
Page 12

SD-TD - Installation Operation and Maintenance Instructions
12. Dry wall - (CL) Cleated Installation Procedure - ig. 12 continued
ig. 12
Page 13

SD-TD - Installation Operation and Maintenance Instructions
13. Dry wall - rameless Installation Procedure – ig. 13
13.1 This is similar to Cleated installation. Refer to section 12 for this recommended
detail. Also, refer to section 5 for wall preparation instructions.
13.2 Depending on wall thickness, it may ease connection of ductwork, if connecting ductwork is attached to
damper prior to fitting pattress around damper.
13.3 Prepare a pair of spacing blocks, (approx. 10mm high x 25mm square) from any available material (such
as drywall boards). Position spacing blocks within the opening at extremities of damper, and stand the
damper on blocks so that damper is central in opening, with blades running horizontally.
13.4 Position and temporarily support damper centrally in wall opening.
13.5 Prepare 16 off pattress pieces from plasterboard of same material as main construction). Plasterboard
pattress should be sufficiently wide to butt up to damper spigots/duct and overlap the outer edge of the
track lining the opening by at least 10mm. They need to be long enough to form neat comers.
13.6 Two layers of pattress are required each side of wall and the corners should
'overlap' between the first and second layers.
13.7 it second pattress to other side of wall in similar manner.
13.8 Apply intumescent sealant to the pattress parts and fit snugly up against the spigot.
13.9 It is not a necessity to fill the void between the pattresses, but it can be done for insulation purposes if
desired.
13.10 Important: Ensure the drywall screws 'pick up' the track lining the hole, so that the proper fire integrity of
the installation will not be compromised.
ig. 13
Page 14

14. Actuator General Information
14.1 Actuators are fitted to the 12mm A/ square shaft on the Transfer Drive (TD) box.
14.2 Check that the actuator, thermal fuses (where present) and wires are undamaged.
14.3 Check the actuator label to for correct voltage and operation as below:
• 24V AC/DC or 230V AC
• Spring Closed
• With Thermal use (T )
15. Instructions for fitting Thermal use (T )
15.1 or dampers fitted with T actuators - ix self-adhesive T template (supplied) onto the duct. This
should typically be above the actuator. or round ducts, the three drilled holes must be in-line with the
duct axis. ( or ductless installations, a T bracket is available from BSB and can be fixed to the
damper casing).
15.2 Drill holes in duct (sizes/positions are detailed on template label - see fig. 14). Remove burrs.
15.3 it the T to the duct with the two screws provided using Philips No.2 screwdriver/bit.
16. Instructions for itting the SD-TD actuator (fall-safe closed) - ig. 1
16.1 Actuators are normally factory fitted, but optionally may be supplied loose for fitting on site.
16.2 When fitting the actuator for the first time, check the actuator voltage.
16.3 Damper must be in the closed position.
16.4 it actuator cradle In desired orientation and then slide actuator into position. it indication pointer, large
washer and 8mm A/ screw (all provided) and tighten to 5Nm max torque. See ig. 1
16.5 When power is applied, the damper blades will start to travel to the open position.
16.6 Dampers can be manually wound open to allow duct work systems to be tested.
Manually wind the actuator, using the crank handle (provided) fully to the 'reset open' position, and lock
into position by turning the key in reverse sharply a quarter tum. (Due care should be taken to stop
winding when slight resistance is encountered - over-winding can result in permanent damage to the
damper/ actuator which may invalidate the wamanty). It is important that you use the manual winding
key provided. The use of a powered drill or screwdriver is not permitted.
17. Instructions for Wiring the SD-TD actuator
17.1 Terminate wires within a junction box (supplied by others) compliant with site rules and Electrical
Installation Regulations (8S7671) in close proximity to actuator, also referring to wiring diagram on
actuator label. Please refer to Page XX for wiring detail.
17.2 Due care should be taken to stop winding when slight resistance is encountered — over-winding can
result in permanent damage to the damper/ actuator which may invalidate the warranty.
17.3 Test the unit. (see section 22)
Page 15
SD-TD - Installation Operation and Maintenance Instructions
ig. 14

18. 18 Removing/replacing or repositioning the SD-TD actuator - ig. 1
18.1 Ensure that the power has been isolated from the actuator and that the damper is now in the failsafe
position, this would normally be with the blades in the closed position.
18.2 Using the 8mm spanner, undo the centre-bolt anti-clockwise and remove along with the washer keeping
safe and close to hand.
18.3 Lift the actuator and cradle and place in a safe secure place within the limitations of the attached wiring.
Ensure that the actuator is not supported/left hanging solely by the connected wiring.
18.4 or repositioning the actuator, tum cradle through 90° to the desired position and then relocate actuator,
pointer, washer 8mm A/ screw into position and tighten to 5Nm max torque.
19. Routine Inspection. Testing and Maintenance
19.1 In accordance with BS 9999 Annex W.1, inspection should be undertake annually. Local
regulations/conditions may override this with periodic Inspection being carried out more frequently
where corrosive or dirty conditions prevail. The maintenance log should be reviewed at each
inspection and the frequency adjusted as required dependent upon findings. (BSB recommend a
maximum of 1 year between inspections and to start more frequently initially and reduce
frequencies only if conditions are proven to allow).
19.2 or actuators fitted with a thermal fuse), check T is correctly fitted to duct. (Refer to section 15)
19.3 Where a thermal fuse is present, the LED on the thermal fuse will be illuminated when the actuator
is powered. Refer to Section 20.1, if it is not illuminated.
19.4 Remove access door to reveal damper's internal elements.
19.5 Visually inspect the internal damper elements for signs of corrosion, obstruction or accumulated
dirt/dust.
19.6 If there are any obstructions or if the damper's blades/gasket seals are dirty, they need to be
cleaned. It is recommended to remove the actuator before cleaning the internal elements to avoid
trapping your fingers. (Refer to section 20)
19.7 Visually check that the damper is in its 'powered state' (opposite to fail-safe position). If the damper
is not in its 'powered state', refer to fault finding chart, otherwise continue.
19.8 Temporarily remove electrical power to the actuator (either by using the test switch on the thermal
fuse (T actuator), or by isolating power to actuators without a thermal fuse).
19.9 The actuator should reach its SPRING-END (fail-safe position) in <30 seconds. Confirm visually
that the blade position and indication pointer on the actuator corresponds.
19.10 Release the T test switch (T ) and ensure it reaches its DRIVE END in <60 seconds. Confirm
visually that blade position and indication pointer on the actuator corresponds.
19.11 If the damper has seized (failing to reach either drive end or spring end):-
19.11.1 Isolate and remove actuator.
19.11.2 Spray a light lubricant into blade end bearings through the holes on the side
gaskets.
19.11.3 Using the 12mm A/ spanner on the TD box Drive Shaft, begin to progressively
operate the blades manually.
Page 16
SD-TD - Installation Operation and Maintenance Instructions

19. Routine Inspection. Testing and Maintenance - continued
19.12 Open the damper using a 12mm A/ spanner on the TD box. Check for foreign
items in and around blades, paying particular attention to blade fishtails. Remove
any obstructions.
19.12.1 Clean the inside of the damper case where the blades make contact with the
gasket seals. Use a soft cloth with a light application of light lubricant. (Connect
Duck Oil recommended).
19.12.2 Lightly apply a light lubricant into blade axle bearings depressing the side gaskets
to allow access. It may be necessary to re-apply lubricant a couple of times, whilst
operating the damper using the 12mm A/ spanner, until the torque has reduced to
less than 5Nm for mid-range travel, and 10Nm for full damper closure.
19.12.3 There should be no more than a thin film of lubricant applied. Remove all excess
lubricant. It is particularly important as excess oil will tend to collect dirt and dust
which will have a negative effect on dampers remaining clean.
19.12.4 Refit the actuator (Refer to section 16).
19.12.5 Switch on power to the actuator.
19.12.6 The actuator should reach its 'powered state' position in <60 seconds. If it does not.
refer to sections 20 and 22.
19.12.7 Replace access doors, and ensure the damper is left in its 'powered state'.
19.12.8 Record all work that has been undertaken in the maintenance log.
19.12.9 It is important to log and review maintenance frequency based on inspections and
test history.
19.12.10 The actuator is maintenance-free.
20. ault inding
20.1 T Actuator
21. Actuator orientation change
21.1 Refer to sections 16 and 18. Position the actuator to the required position as necessary.
SD-TD - Installation Operation and Maintenance Instructions
SYMPTOM AULT ACTION
Green LED on the
thermal fuse (T )
is not illuminated
No power / incorrect supply Check supply
T tripped. Remove T from
duct, separate two halves,
continuity check the two contacts
within the probe section (or test
with new probe)
If open circuit, replace probe
Actuator faulty Replace actuator
Synchronization of actuator and
damper incorrect
Remove actuator and refit.
(Refer to sec1ions 16 and 17)
Damper seized Refer to section 21.1
Blades do not
travel fully open /
closed
Lack of maintenance to the blade
bearings
Apply DEB duck oil or similar
to the side gasket and blade
bearing and wipe away any
dirt/dust with a soft cloth
Noisy damper
during operation
Page 17

~
12
BK WH 123456
VT RD WH OG PK GY
Tf1 Tf2 Tf3 LED
<5 <85
Common
NC
NO
Common
NC
NO
THERMAL
FUSE
Damper
Closed
Damper
Open
PM24-TF
~
N L
12
BU BN
PM230-TF
Connections
shown with no
power to actuator
BSB PM24-T & BSB PM230-T
ELECTRICAL CONNECTIONS
DAMPER ENERGISED OPEN / SPRING CLOSED OPTION
• Wiring diagram shows switch positions based on no power to actuator
• Damper required normally open
• Spring close on removal of power or thermal fuse activation
24V AC/DC: Connect via safety isolation transformer
230V AC: or disconnection from the supply, a separate
device must be incorporated in the fixed wiring
(at least 3mm contact gap in all poles)
or damper closed indication use terminals 1 & 2
or damper open indication use terminals 4 & 6
Terminals 1 & 4 can be linked where required as an option
Unused cores should be isolated
Connecting cables need to be protected from sharp edges
22. Commissioning
22.1 The damper cannot be commissioned unless it is fully installed and connected to mains power in
compliance with regulations.
22.2 Dampers should be fully inspected and checked in accordance with the inspection handover check
sheet prior to the dampers and panel being commissioned.
22.3 Electro-mechanically operated dampers can be tested/commissioned by a locally appointed, competent
person.
22.4 The installation needs to be inspected thoroughly, before the damper actuation is tested.
22.5 Actuation testing should be completed as follows:
22.5.1 Isolate the power.
22.5.2 Remove access door(s).
22.5.3 Test manually, using the crank handle provided, to set the damper to the 'normal state'
(powered state). A quarter turn in the opposite direction locks it. Visually confirm that
the damper is in its 'normal state'.
22.5.4 Release the motor if it is locked by turning the crank handle a quarter turn in the
winding direction and allow the damper to travel to 'fail-safe' position.
22.5.5 Visually confirm that the damper is in the correct position.
22.5.6 Switch on power to actuator. LED on T (where present) will illuminate. The actuator
will start to travel to the DRIVE-END (normal state) position, reaching it within 60
seconds, visually check that the damper blade-position and signal corresponds.
22.5.7 IMPORTANT: Press and hold test switch lever on T to allow to allow actuator to travel
to its SPRING END position. Visually check that the damper blade position and signal
corresponds. (This is to ensure that the actuator functions electrically and overrides
the manual reset facility -should it have been used-, as it is feasible to leave the
damper inadvertently reset without the T being functional if this test is not carried out!)
22.6 Ensure the damper is left in its 'normal state' (powered) before re-fitting access doors.
23. Electrical Connections
SD-TD - Installation Operation and Maintenance Instructions
Page 18

Project Name:
This check sheet only applies to the BSB ire and ire/Smoke dampers.
The installer should complete this handover check sheet to ensure installation is in accordance
with BSB installation guides and is compliant before handover.
SD-TD - Inspection and handover check sheet
No. Question Guidelines Confirmed
Are the dampers the correct type?
Are the dampers individually correctly
identified?
Are the dampers located correctly
Is the installation method tested and approved
for the type of barrier that is being protected?
Is the damper installed & fixed in accordance
with the manufacturers tested and approved
method?
Have access doors been fitted to the ductwork
allowing the damper blades to be inspected?
Is access through the ductwork, to the damper
unhindered?
Is the penetration only used by the damper and
not used for the passage of other services?
Using the access opening provided. has the
damoer been left in the open position?
Is the correct power supply wired to the
actuator and power is on? (if motorised)
Is the Thermal use/link correctly installed?
Have the damper blades been released to
simulate failure of thermal release mechanism
(damper 'drop test')?
Have the dampers been checked for internal
cleanliness and free from damage and debris?
Have the dampers blades been re-set following
the drop test and the access panel replaced?
At the time of the damper handover, is the fire
damper installation completed in accordance
with the above check list?
Is the damper installation completed and
available for handover prior to system
commissioning?
Is the completed handover register cross
referenced back to the identification codes
listed in the system designer's damper
schedule?
Confirm the damper is the correct type and
model.
Unique system identification and location
reference aids commissioning and must be
clearly indicated on the damper or agreed
location.
The damper position shall be checked against
the installation drawings/details.
Ensure modifications have not been made to
the tested method.
Check the damper has been fixed correctly to
the fire barrier and is independently supported
from the ductwork
Access doors are required for commissioning
and servicing.
Unobstructed space shall be provided for safe
access to damper. Also consider access
through ceiling voids and adjacent services.
The presence of other services will invalidate
the approved installation method.
Check blade position
Check power is on to actuated damper to
ensure testing can be carried out
Confirm fitted correctly to ductwork/damper
Test button on thermal fuse probe shall be
used or fusible link removed to drop test
With the damper in the closed position inspect
for damaoe and contamination.
After re-setting the damper blades, check
position of blades to ensure correct.
Damper installer to record, on the register, any
incomplete works relevant to the damper
installation.
Obtain relevant acceptance of the damper
installation from the system designer
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
16
17
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
YES / NO
Manufacturers Product model(s): ..........................................................................................................
Damper Reference I.D: ................................................. Damper Reference I.D: ................................................
I the undersigned confirm that the damper referenced above has been checked and is installed to the
manufacturers tested installation method.
Company Name: Installers name:
Installers Telephone Number: E-mail:
Installers signature: Print Name:
www.bsb-dampers.co.uk
Page 19

Model
SD-TD ire and Smoke Damper
Case Type
S Rectangular Spigot Connection
C Circular Spigot Connection
O lat Oval Spigot Connection
Case Material
C1 Galvanised Steel
C2 430 Stainless Steel - erritic (430) type 1.4016
C3 316 Stainless Steel - Austenitic (316) type 1.4401
Blade Material
B1 Galvanised Steel
B2 430 Stainless Steel - erritic (430) type 1.4016
B3 316 Stainless Steel - Austenitic (316) type 1.4401
SD-TD S C1 B1 H PM230-T
SD-TD Series
ire and Smoke Dampers – Ordering Codes
M A D E I N B R I T AIN
SOLD TO THE WORLD
M
A
D
E
I
N
B
R
I
T
A
I
N
Actuator Options
PM24-T 24 volt spring return actuator
with thermal fuse
PM230-T 230 volt spring return actuator
with thermal fuse
Installation Method
A -BATT Batt rame
A Angle rame
H HEVAC rame
CL Cleats
or full details of the complete BSB Product Range, please refer to our individual product brochures, sales office or website.
BSB Engineering Services Limited
Unit 56, Trinity Trade Centre, Mill Way, Sittingbourne, Kent ME10 2PD, UK • Tel: +44 (0)1795 422609
or purchase orders and order related enquiries, please email: orders@bsb-dampers.co.uk
or pricing, technical and general enquiries, please email: enquiries@bsb-dampers.co.uk
Website: www.bsb-dampers.co.uk • A member of the Maico group
BSB Engineering Services Ltd. reserves the right to modify or withdraw any specification without prior notice that may result from
continuous product development. The information contained within this brochure is correct at the time of going to press. ( SDTD-05-2021)
Other Air, ire and Smoke Control Products in the BSB Range:
A60 Series
Marine ire Dampers
D Series
ire Dampers
Control Systems
D-C Series
Circular ire Dampers
BD Series
Backdraught Dampers
HD Series
Heavy Duty Dampers
SS Series
SlimSeal Dampers
SD-C Series
Circular ire/Smoke Dampers
ETD Series
Elevated Temperature Dampers
VC Series
Volume Control Dampers
This manual suits for next models
1
Table of contents
Other Maico Fire And Smoke Damper manuals
Popular Fire And Smoke Damper manuals by other brands

System air
System air fantech bathfan Select SC50-80-110 installation instructions

Nailor
Nailor D1200 Series manual

MAT
MAT Roto-Twist RT-150 Installation, operation & maintenance instructions

Rf-t
Rf-t CU2 manual

Komfovent
Komfovent UVA60 M installation manual

LUCOMA
LUCOMA WSG-H3 Installation, operation and maintenance instructions

Lennox
Lennox C1DAMP20C-1 installation instructions

Lindab
Lindab SDR2-M technical information

Greenheck
Greenheck HBT Series Installation, operation and maintenance manual

NuAire
NuAire Ecosmart NRG Installation and Maintenance

mercor
mercor mcr WIP LD Operation and maintenance manual

SMAY
SMAY WKZ-O installation manual