ModvFresh Kascata: System to connect on cascade several hdw pump units
Page 2 of 6 Rev.3 - 12/01/2017
Hydraulic connection scheme
REMARK: Approximate scheme only. temperature values marked with an asterisk (*) have to be
considered as nominal. For more information, please refer to the section “eld of utilization”
Water
supply (10 °C)*
Users
Supply from the storage tank (60 °C)*
Return to
the storage
tank
Recycling (where present)
HDW to users (45 °C)*
(1)
Master
VFS 10-200 l/min
(2)
Slave
(3)
Slave
(4)
Slave
(5)
Slave
Do the hydraulic connections following the scheme of picture 1. We underline that the scheme here represented is to be considered as not
compulsory but, as a rule, it is the most suitable feasible solution from the plant simplication point of view.
Go on with the carrying ou of the installation by preparing each pump unit to be connected to the common pipings, by placing on the pump
units the special valve for the housing of ModvMaster and ModvSlave servomotors; this valve, as it is not symmetric, must be connected
in accordance with the ow direction (please take as a reference the arrow on the body of the valve).
Picture 1: Schematization of an installation to supply hot domestic
water (HDW), managed by ModvFresh Kascata control system.
Directions concerning the system equipped with recycling line:
If in the cascade system is foreseen the recycling line too, it has to
be made, during the installation of the components, placing the only
ModvFresh with recycling as last unit.
For instance, if we want to make a 4 pump units cascade system
(400 nominal kW – 160 l/min) with recycling line, it would be better
to foresee the installation of three ModvFresh, standard model so
placed:
the rst linked to ModvMaster, identied with number 1;
the second end the third, respectively linked to ModvSlaves,
number 2 and 3;
To nish the system the fourth pump unit, equipped with recycling
and linked to ModvSlave number 4.
To install the ball valves suitable to fit the servomotors you must remove
the connection on the feeding way of the supply water network to go on
to remove of the pipe union connection, as shown in the picture at side;
this operation also requires the elimination of the built in check valve.
As the logic of the system requires that almost one isolating valve is always
open, to prevent the emptying of the installation, we recommend to install,
before the VFS sensor, a check valve with a size t to the piping of the
common supply line of the pump units.
TAKE CARE!
Then, always with reference to the picture 1, do the connection to
the check valve and the VFS sensor on the supply watering line,
and place them at the bottom of the connecting derivations of each
pump unit.
Finally connect the pump units to the common lines; to select the
right size of the pipes t to the dimension of the installation, see the
chart at side.
FIELD OF UTILIZATION:
For a maximum nominal power of 500 kW and ow up to 200 l/min.
Nominal supply temperature of the storage tank: 60°C.
Nominal temperature of the water supply: 10°C.
Nominal temperature of HDW production: 45°C, adjustable from 30°C to 70°C.
Recycling line temperature adjustable from 10°C up to 40°C.
Recycling line pipings
(if present)
DN15
DN20
DN20
DN15
No. of ModvFresh
pump units, 100 kW
Installation
pipings [mm]
3 pcs
4 pcs
5 pcs
DN32 (Cu 35x1,5)
DN32 (Cu 35x1,5)
DN40 (Cu 42x1,5)
2 pcs DN25 (Cu 28x1,5)
Minimum pipings diameters