Taylex ABS4200 User manual

Installation Manual
ADVANCED BLOWER SYSTEM 4200
ABS4200 Standard

Page 2 of 13
TABLE OF CONTENTS
1.
INTRODUCTION...................................................................................................................................
3
2.
SAFETY INSTRUCTIONS .....................................................................................................................
3
3.
STANDARDS & LICENCING ................................................................................................................
4
4.
PRE SITE INSPECTION ........................................................................................................................
4
5.
MARK OUT..............................................................................................................................................
4
6.
DELIVERY AND PLACEMENT ............................................................................................................
5-7
7.
INSTALLATION......................................................................................................................................
7-8
8.
ELECTRICAL CONNECTION .........................................................................................................
8
9.
COMMISSIONING ............................................................................................................................
8
10.
EXCAVATION & LIFTING INSTRUCTIONS.....................................................................................
9
a. ABS4200 Excavation Instructions ............................................................. 9
b. ABS4200 Lifting Instructions....................................................................10
11.
ELECTRICAL CONNECTION DIAGRAM...................................................................................................
11-12
Note: Do not act solely on the basis of the material contained in this document. Items
herein are general comments only and do not convey advice per say. We therefore
recommend that formal advice be sought before acting in any of these areas.

Page 3 of 13
1.
INTRODUCTION
Th
e
Tay
l
e
x
A
BS
4200
S
ec
o
n
d
a
r
y
T
r
ea
t
men
t
S
y
s
t
em
i
s
d
es
i
g
n
ed
t
o
b
e
i
n
s
t
all
ed
b
ot
h
i
n
-
ground and aboveground, collecting all wastewater from a domestic residence or
suitable commercial properties. This manual hasbeen put together to explain the
installation process of the ABS4200 system as a guide only. Some sites may differ in
access and slope, which need to be taken into account when delivering and installing the
system.
2.
SAFETY INSTRUCTIONS
Follow all safety instruction provided by the onsite builder and ensure you
have all the relevant licences to perform this work.
Ensure the correct measurements are in place to prevent the
general public from entering the site during the installation of the
ABS4200. Excavated holes should be fenced if the ABS4200 is not
immediately installed.
SLIPPERY WHEN WET!
During cleaning, maintenance & repair work, the surrounding area may
become extremely slippery due to spilt water. Caution is to be taken
when walking/standing near the ABS4200 when these activities are
being conducted.
Use safe lifting techniques when installing/relocating the ABS4200.
Ensure that all lifting equipment is in a safe working order and the area is
clear of obstructions. Ensure all lifting equipment used has a suitable
capacity and current testing/compliance.
The waste water contained in the ABS4200 may contain harmful
bacteria. Persons coming in contact with wastewater must immediately
wash and disinfect allexposed areas. Contact your personal physician
for allhealth concerns.
WARNING - To reduce the risk of electrical shock, all works requiring
access to the blower boxMUST be carried out by a licenced electrician or
Taylex Accredited Service Agent (TASA) prior to final commissioning.

Page 4 of 13
3.
STANDARDS &LICENCING
All Installations must be completed in accordance with AS/ANZ 3500.1 and AS/ANZ
3500.2
I
rr
ig
a
tio
n
A
r
e
a
s
/
L
a
n
d
A
pp
lic
a
tio
n
A
r
e
a
s
(
L
AA
)
m
u
s
t
b
e
in
s
ta
lle
d
a
s
p
e
r
A
S
1
5
4
7
a
n
d
all
relevant State/Local Codes or Guidelines
Ensure the appointed Licensed trades only complete this work –
Plumbers/Drainers/Electrical.
4.
PRE SITE INSPECTION
A pre site inspection should be conducted the day prior to installation. During this
inspection the following details should be checked.
Access requirements for excavation, Crane Truck, Truck or Crane.
A Crane Truck requires the following:
Access to site – 12m long x 4m wide x 4.5m
high Level Pad at the hole – 12m long x 7m
wide
Overhead obstructions
Slope of site
Soil moisture (for heavy equipment access)
Weather conditions
5.
MARK OUT
To ensure the ABS4200 is installed in the position nominated by the Home Owner/
Builder, the location of the ABS4200 should be marked out prior to excavation. The
installer at this stage should have a copy of the approved site plans showing the location
of the ABS4200 as well as the required local authority approval. If not, it is advised to
delay the installation until the plans have been received.
Mark out a 3000mm x 6000m with line marking paint
Place pegs on each of the corners as well as in the middle of the rectangle and
spray it with white paint or a colour that it noticeable from a distance
Indicate on the centre peg or by spraying on the ground, the type of system
that is
to be installed as a reference for the installer.
Allow a minimum of 300mm between Tank and the edge of excavation.
There should be a minimum gap of 550mm between the tanks.

Page 5 of 13
Typical Taylex ABS4200 Excavation Mark Out
6.
DELIVERY AND PLACEMENT
In most areas, tanks will be delivered by a truck equipped with a crane located
at the rear of the vehicle. Such vehicles will back up to the hole, lift and slew the
tank into position behind the vehicle before placing it into the prepared hole.
Maximum reach from the rear of the truck to the centre of ABS4200 will vary
depending on the size of the crane.
To enable the ABS4200 to be unloaded, a minimum width of 7m (may vary
depending on crane truck) will be required at the hole. This distance allows for
the width of the crane truck, the width of the tank itself, and clearance for safe
and free maneuvering of the ABS4200 into the excavated hole.

Page 6 of 13

Page 7 of 13
PLEASE NOTE
Tanks should not be lifted over houses, sheds or other property of value,
nor should they be lifted under low power lines
Tank sites that are cut out of sloping hills will require enough flat area for
the truck to be unloaded
Unloading on awkward and dangerous sites will be at the driver's
discretion. Safe and clear access is the responsibility of the
propertyowner/builder.
7.
INSTALLATION
Alwaysensure the installation location including the future landscaping provision
allows for the diversion of storm-water and surface waters away from the system.
Width
Height
Inlet Height
(from bottom of
tank)
Inlet
Depth
(from ground
level)
Required
Base
(5-7mm Drainage
Gravel/ Sand)
Hole
Width
Hole
Depth
TANK 1*
2425
2700
2070
530
100
3000
2700
TANK 2*
2425
2700
1950
650
100
3000
2700
*
Refer to Excavation & Lifting Instructions on Pages 9 & 10
STANDARD Taylex
ABS4200
NON TRAFFICABLE LOADS ONLY
NON TRAFFICABLE LOADS ONLY
2425 mm
2425 mm
100mm of 5mm-7mm drainage gravel or sand
100mm of 5mm-7mm drainage gravel or sand
100mm
Inlet
Lifting
Holes
Lifting
Holes
100mm
Outlet
100mm
Inlet
Lifting
Holes
Lifting
Holes
Top of tank to be a minimum
of 100mm above landscaped ground level

Page 8 of 13
Except for person/s responsible for lifting and positioning of the tank in the
excavated hole, there must not be any person within 20m of the installation site
during the lifting and positioning of the tank. Excavation Instructions show
excavated walls to be perpendicular. However, depending on the soil conditions,
the excavator may need to batter or retain the side walls to ensure they don’t
cave in during installation.
Level the base of the hole using an excavation bucket with a laser level attached.
Ensure that the excavated ground or base material is capable of
carrying loads of approximately 8 tonne.
The ABS4200 must be level in both inflow/outflow direction and 90° to the
inflow/outflow direction (<1° deviation).
Backfilling - Use sand or excavated material/spoil with maximum particle size of
300mm. Backfilling of excavation to be completed in not more than 500mm
equally distributed layers around the tank perimeter. Ensure that sand or
excavated material does not fall on the lid ofthe ABS5000 asthis will fall into
the system through the manholes and clog the system and irrigation pump.
Ensure that the backfill material is kept at least 100mm below the surface of the
systems lid.
Evenly fill each system with approximately 5,000L of water through the
centre Chambers to prevent movement through the ground as the
waterpressure enters the system.
Organise drainage contractors to connect the main sewer line to the system
and between Tank
1
& 2. The drainage connection is a standard 100mm PVC
sewer inlet.
Refer to Excavation & Lifting Instructions on Pages 10 and 11

Page 9 of 13
8.
ELECTRICAL CONNECTION
The electrical contractor must follow the electrical specification
supplied with the ABS4200 system
Ensure all electrical works are only completed by licenced persons.
Ensure all electrical work is completed and compliant with AS/ANZ 3000.
Refer to Electrical Specifications on Page 12 & 13
9.
COMMISSIONING
Please ensure the following is completed prior to having the system commissioned
Tanks is full of water (5,000lt each)
Effluent Disposal area is installed
Effluent Disposal Area feed line is connected to ABS4200 (Tank 2)
Electrical power is connected (Tank
1
& 2)
Drains connected (main sewer into tank 1 and connection between Tank 1 & 2)
I
M
PO
R
T
A
NT
:
T
h
e
T
a
y
l
ex
A
BS
4200
S
y
s
t
em
c
a
nn
ot
b
e
c
ommi
ss
i
o
n
ed
un
l
es
s
p
ow
er
i
s
connected to the system.
T
h
e
A
BS
4200
w
ill
t
h
en
b
e
s
w
i
t
c
h
ed
o
n
(
c
o
mmi
ss
i
on
ed
)
b
y
a
n
E
mp
l
oy
ee
of
T
a
y
l
ex
Australia
,
a
T
ay
l
e
x
A
cc
r
ed
i
t
ed
D
is
tr
ib
u
to
r
(T
A
D)
or
a
T
a
y
l
ex
A
cc
r
ed
i
t
ed
S
er
v
i
c
e
Te
c
hni
c
ia
n
(TASA).

2425 mm
TAYLEX ABS4200
LIFTING INSTRUCTIONS
ABS4200 CONCRETE
Lifting Instructions (Tank 1 & 2)
Total Mass = 8.00 Tonne
Total Height = 2700mm
Total Width = 2425mm
REACH OF CRANE/ CRANE TRUCK
To be determined by your crane/ crane truck
operator.
Lifting
Holes
Lifting
Holes
Lifting
Hole Lifting
Hole
USE ONLY CERTIFIED LIFTING BARS
2700 mm
1. Always use a Spreader Bar and ensure
it is certified
2.Lower chains through TOP lifting
holes provided in the lid of the ABS4200
3.Loop chains through the lifting holes
directly below on the inside wall of the
ABS4200
4. Steel reinforcing bars have been
installed inside the concrete for lifting
purposes. Only lift this tank from these
holes
5.If you don’t use a Spreader Bar, you
risk damaging the ABS4200
6. Ensure the tank is empty before
lifting

2700 mm
2070 mm 530 mm
6000 mm
2425 mm
100 mm
2700 mm
100 mm
350 mm
TAYLEX ABS4200
EXCAVATION INSTRUCTIONS
ABS4200 CONCRETE
Excavation Instructions
Tank Total Mass = 8.00 Tonne each
Lifting
Hole
25mm
Electrical
Inlet
Lifting
Holes
100mm
Inlet
Lifting
Holes
Lifting
Hole
Lifting
Hole
Please Note:
5,000lt of water
to be placed in
this chamber to
prevent flotation
ELECTRICIAN
Connect through conduit on side of ABS4200.
Run wire (min 2.5mm) through the flexible
conduit provided and up into the switch located
in the blower box.
Active - Neutral - Earth.
TRUCK ACCESS
Unloading of ABS4200 via the back of the truck
NOT SIDE. Ensure BACK of truck has clear
level 6m wide access to the edge of the hole.
REACH OF CRANE/ CRANE TRUCK
To be determined by your crane/ crane truck
operator.
Top of tank to be a minimum
of 100mm above landscaped ground level
Ensure the installation location including the future
landscaping provision allows for the diversion of stormwater
and surface waters away from the system
NON TRAFFICABLE LOADS ONLY
1. Dig hole 6000mm x 3000mm & 2700mm Deep
2. Ensure drainage has a 1/60 fall to the inlet of ABS4200. Risers
are available if the tank needs to be installed deeper in the
ground to maintain fall
3. Cover base of hole with 100mm of 5mm to 7mm drainage
gravel or sand
4. Ensure bottom of hole is level
2425 mm
350 mm
Lifting
Holes
100mm
Inlet
Lifting
Holes
NON TRAFFICABLE LOADS ONLY
100mm of 5mm-7mm drainage gravel or sand 100mm of 5mm-7mm drainage gravel or sand
5. Backfill with soil from Excavation in no more than 500mm equally
distributed layers around the tank. Avoid backfilling with rocks
over 300mm.
6. To prevent flotation, fill each tank with 5,000lt of water
immediately through center hole (see diagram below)
7. Ensure top of gravel/sand is 2070mm (Tank 1) & 1950mm (Tank 2)
to bottom of inlet
650 mm
630 mm
100mm
OutInlet
1950 mm


Tank 2
This manual suits for next models
1
Table of contents
Other Taylex Water System manuals
Popular Water System manuals by other brands

Eco Pure
Eco Pure ECOP20 Installation and operation manual

Eco-Smart
Eco-Smart METLUND D’MAND S Series Installation and operating instructions

Airmax
Airmax SolarSeries SS20-BB owner's manual

Little Giant
Little Giant WRSC-6 owner's manual

BIO-MICROBICS
BIO-MICROBICS SeptiTech STAAR 1.2 Operation and maintenance manual

Blue Wave
Blue Wave FlowXtreme NE4487 manual