9
GB
Drill
Drill
80 mm dia.
bell saw
attachment
Inside
Inside
Outside
Outside
B
AWall Wall
3.3 DRILLING THE HOLES FOR THE PIPES
(for pipes entering through the rear of the air handler)
• Using an 80 mm dia. bell saw attachment, drill a hole in the wall for the pipes.
C
A- Start drilling (at a slight
angle) from the inside. B-
Completethedrillingfrom
the outside, keeping to
the same angle.
C- Put in a plastic tube and adapt it to suit. Fix the trim
which is part of the equipment.
3.4 HOOKING OF THE INTERNAL UNIT
• Remove the foam packing-pieces in the baffle.
5 - 10 mm
Trim
Hooking
• Hook the air handler on the support
plate according to the sketch
opposite.
• Connect the water pipes (see § 4).
• Run in any electric cables (see § 4).
• Then,pressonthebottom ofthe unit
inorderto engagethebottom hooks
in the holes in the support plate.
• Remove the setting wheel in order to reveal the ther-
mostat cover fixing screw.
• Remove the cover.
• Fix the thermostat using 2 screws (dimensions in
accordance with sketch opposite).
POSITIONING THE THERMOSTAT
• Fixing height: approx. 1.50 m above the floor.
• Avoid draughts from doors and windows.
• Also make sure that the thermostat is in the premises'
normalconvectioncurrents, andthatit is notfitted inside
shelving or covered by curtains.
• Allunwantedheat sourcesadverselyaffect control;avoid
therefore sunlight, the proximity of supplementary
heaters, lights, chimneys, television sets, etc...
869 36
113
8,5
53,55
67
3.6 FIXING THE ROOM THERMOSTAT
3.5 UNHOOKING THE INTERNAL UNIT
• In order to unhook the unit from the support plate, push the unit upwards and pull
it towards you.The hooks are then released from the support plate.
80 mm dia.
bell saw
attachment