Velatia Ormazabal cpg.1 Series Instruction manual

cpg.1
Fully SF6 gas insulated single and
double busbar GIS switchgears up
to 36 kV in accordance with IEC
Standards
General Instructions
IG-137-EN, version 03; 23/06/2016 LIB

Legal Deposit: BI-1548/2015
CAUTION!
When medium voltage equipment is operating, certain components are live, other parts may be in movement and some may reach high
temperatures. Therefore, the use of this equipment poses electrical, mechanical and thermal risks.
In order to ensure an acceptable level of protection for people and property, and in compliance with applicable environmental
recommendations, Ormazabal designs and manufactures its products according to the principle of integrated safety, based on the
following criteria:
• Elimination of hazards wherever possible.
• Where elimination of hazards is neither technically nor economically feasible, appropriate protection functions are
incorporated in the equipment.
• Communication about remaining risks to facilitate the design of operating procedures which prevent such risks, training
for the personnel in charge of the equipment, and the use of suitable personal protective equipment.
• Use of recyclable materials and establishment of procedures for the disposal of equipment and components so that
once the end of their service lives is reached, they are duly processed in accordance, as far as possible, with the
environmental restrictions established by the competent authorities.
Consequently, the equipment to which the present manual refers complies with the requirements of section 11.2 of Standard IEC
62271-1. It must therefore only be operated by appropriately qualified and supervised personnel, in accordance with the requirements
of standard EN 50110-1 on the safety of electrical installations and standard EN 50110-2 on activities in or near electrical installations.
Personnel must be fully familiar with the instructions and warnings contained in this manual and in other recommendations of a more
general nature which are applicable to the situation according to current legislation1.
The above must be carefully observed, as the correct and safe operation of this equipment depends not only on its design but also on
general circumstances which are in general beyond the control and responsibility of the manufacturer. More specifically:
• The equipment must be handled and transported appropriately from the factory to the place of installation.
• All intermediate storage should occur in conditions which do not alter or damage the characteristics of the equipment or
its essential components.
• Service conditions must be compatible with the equipment rating.
• The equipment must be operated strictly in accordance with the instructions given in the manual, and the applicable
operating and safety principles must be clearly understood.
• Maintenance should be performed properly, taking into account the actual service and environmental conditions in the
place of installation.
The manufacturer declines all liability for any significant indirect damages resulting from violation of the guarantee, under any jurisdiction,
including loss of income, stoppages and costs resulting from repair or replacement of parts.
Warranty
The manufacturer guarantees this product against any defect in materials and operation during the contractual period. In the event that
defects are detected, the manufacturer may opt either to repair or replace the equipment. Improper handling of this equipment and its
repair by the user shall constitute a violation of the warranty.
Registered Trademarks and Copyrights
All registered trademarks cited in this document are the property of their respective owners. The intellectual property of this manual
belongs to Ormazabal.
1For example, in Spain the “Regulation on technical conditions and guarantees for safety in high voltage electrical installations” –
Royal Decree 337/2014 is obligatory.
In view of the constant evolution in standards and design, the characteristics of the elements contained in this manual are subject to
change without prior notice. These characteristics, as well as the availability of components, are subject to confirmation by Ormazabal.

General instructions
3
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
Contents
1 Description and main characteristics .......................................... 6
1.1 Models .................................................................................6
1.2 Standards applied........................................................................6
1.3 Main components ........................................................................7
1.3.1 Levers for manual operation .........................................................10
1.3.2 Main manual operation panel ........................................................11
1.4 Name plate.............................................................................14
2 Technical characteristics ................................................... 15
2.1 Electrical characteristics .................................................................15
2.2 Mechanical characteristics ...............................................................16
2.2.1 Dimensions and weights...........................................................16
2.2.2 Protection grade .................................................................17
3 Service conditions......................................................... 18
4 Handling and transport ..................................................... 19
4.1 Transport conditions ....................................................................19
4.2 Lifting means...........................................................................19
5 Storage conditions ........................................................ 21
6 Installation ............................................................... 22
6.1 Unpacking the equipment ................................................................22
6.2 List of supplied materials.................................................................22
6.3 Minimum installation distances............................................................30
6.4 Cable trench ...........................................................................30
6.5 Fastening to the floor ....................................................................31
6.6 Cubicle joints ..........................................................................32
6.6.1 cpg.1-v ..........................................................................32
6.6.2 cpg.1-s ..........................................................................33
6.6.3 cpg.1-ct / cpg.1-cl ..................................................................33
6.6.4 cpg.1-f ..........................................................................34

General Instructions
4cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
6.7 Equipment earthing .....................................................................34
6.7.1 Top section.......................................................................34
6.7.2 Bottom section ....................................................................35
6.7.3 Top and bottom earth side link........................................................35
7 Operations sequence ...................................................... 36
7.1 cpg.1-v1 cubicle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
7.1.1 Commissioning from open position ....................................................37
7.1.1 Medium voltage cable earthing .......................................................38
7.2 cpg.1-v2 cubicle .........................................................................39
7.2.1 Commissioning from open position ....................................................39
7.2.2 Medium voltage cable earthing .......................................................40
7.2.3 Replacing a busbar ................................................................40
7.3 cpg.1-s1 cubicle .........................................................................42
7.3.1 Connection.......................................................................42
7.3.2 Earthing .........................................................................43
7.4 cpg.1-s2 cubicle .........................................................................43
7.4.1 Connection.......................................................................44
7.4.2 Earthing .........................................................................44
7.5 cpg.1-c cubicle ..........................................................................45
7.5.1 Busbar coupling ...................................................................46
7.5.2 Busbar earthing on the right .........................................................47
7.5.3 Busbar earthing on the left...........................................................48
7.6 cpg.1-cl cubicle..........................................................................49
7.6.1 Busbar coupling ...................................................................49
7.6.2 Busbar earthing on the right .........................................................50
7.6.3 Busbar earthing on the left: ..........................................................52
7.7 cpg.1-ct cubicle .........................................................................53
7.7.1 Busbar connection .................................................................54
7.7.2 Main busbar earthing ...............................................................55
7.7.3 Secondary busbar earthing ..........................................................56
7.8 cpg.1-f1 cubicle .........................................................................57
7.8.1 Commissioning the cubicle ..........................................................57
7.8.2 Earthing .........................................................................58
7.9 cpg.1-f2 cubicle .........................................................................58
7.9.1 Commissioning the cubicle ..........................................................59
7.9.2 Earthing .........................................................................59
7.10 Fuse replacement sequence in cpg.1-f .....................................................60
7.10.1 Selection of fuses recommended for cpg.1-f ............................................62

General instructions
5
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
8 Safety elements ........................................................... 63
8.1 Maintenance ...........................................................................63
8.2 Voltage presence detectors ...............................................................63
8.2.1 Locking with a padlock..............................................................64
8.2.1 Locking with lock ..................................................................64
8.3 Interlocks ..............................................................................64
9 Spares and accessories .................................................... 65
9.1 Preventive maintenance for the cpg.1 cubicle ................................................65
10 Environmental information ................................................ 66
10.1 Sulphur Hexafluoride SF6................................................................66
10.2 Recyclability ..........................................................................66

General Instructions
Description and main characteristics
6cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
1 Description and main characteristics
The cpg.1 family is a series of GIS modular cubicles
with full SF6gas insulation, for single and double busbar
primary distribution applications in medium voltage
networks up to 36 kV.
1.1 Models
Function Designation
Single busbar Double busbar
Circuit breaker cubicle cpg.1-v1 cpg.1-v2
Disconnector cubicle cpg.1-s1 cpg.1-s2
Transversal busbar coupling cubicle -- cpg.1-ct
Longitudinal busbar coupling cubicle cpg.1-c cpg.1-cl
Fuse protection cubicle cpg.1-f1 cpg.1-f2
1.2 Standards applied
Standard Description
IEC 62271-1 Common specications for high voltage switchgear standards
IEC 62271-200 Metal-enclosed alternating current switchgear for rated voltages
above 1 kV and below or equal to 52 kV
IEC 62271-100 Alternating current circuit breakers
IEC 62271-102 Alternating current disconnectors and earthing switches
IEC 62271-105 Alternating current circuit breaker-fuse combinations for rated voltages
above 1 kV and below or equal to 52 kV
IEC 62271-206 / IEC 61243-5
Voltage presence indicating systems

Description and main characteristics
General instructions
7
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
1.3 Main components
Each cubicle is made up of a series of independent
compartments:
Figure 1.1 Main elements of cpg.1 cubicles
Gas tanks
These are the compartments which house the switching
and breaking switchgear, where the insulating medium is
SF6gas. There are 2 or 3 separate compartments:
• 1 for each of the feeder disconnectors
• 1 for the circuit breaker and the earthing switch
These are sealed compartments, made of stainless steel
and sealed for life. They are designed and tested to
withstand an internal arc of up to 31.5 kA - 1 s.
Depending on the function for which the cubicle was
designed, it may contain the following components:
• Feeder disconnectors
• Earthing switch
• Internal busbar and connections
• Vacuum circuit breaker
• Switch - disconnector
• Fuse holders Figure 1.2 Gas tanks of circuit breaker and disconnectors for
cpg.1-v2 cubicle
There are sets of bushings in the top and bottom of the
compartments for connection of the busbar and the power
cables respectively.
1. Gas tanks
2. Busbar compartment
3. Cable compartment
4. Gas pressure relief duct (optional)
5. Control compartment
6. Driving mechanism area

General Instructions
Description and main characteristics
8cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
For testing the gas pressure in each compartment, a
temperature-compensated pressure switch is installed,
with a volt-free contact, for possible use as a remote alarm
or blocking/trip for the functional unit.
Top busbar
This is used for connecting cubicles. It has solid and
shielded insulation, earthed by means of the compartment's
specific earthing bar.
As an option, the busbar is able to segregate the phases
by means of a set of earthed metal plates (metal-clad).
Toroidal current transformers and/or plug-in voltage
transformers can be installed in this compartment, thus
avoiding the need for metering cubicles.
Cable compartment
Figure 1.3 Phase segregation in the cable compartment
(optional)
Located in the bottom part of the cubicle, this has a cover,
interlocked with the earthing circuit, which allows front
access to the medium voltage cables.
In the most complete case, the base can house the
following components:
• Phase segregation consisting of the main box
and the segregating cover.
• Up to 4 screw-in shielded terminals per phase,
as well as space for the corresponding incoming
power cables.
• Clamp flanges for the medium voltage cables.
• Earthing plates.
• Toroidal current transformers.
• Plug-in voltage transformers.
• Surge arresters.
All the elements making up the enclosure are earthed by
means of a conductor consisting of a copper bar capable
of withstanding the rated short-time current. It is located
in the base in such a way that it does not need to be
dismantled in order to insert or remove a cable and its
corresponding termination.

Description and main characteristics
General instructions
9
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
Gas pressure relief duct (optional)
Figure 1.4 Internal arc gas pressure relief duct (optional)
This component is used to direct the gases produced by
an internal arc in any of the compartments towards the
top of the cubicle: Disconnector compartment and circuit
breaker compartment, top busbar compartment and cable
compartment.
Control compartment
Placed at the top of the cubicle and separate from the
medium voltage area, this is ready for installation of the
metering equipment and protection relays. It contains
the whole terminal block with the control signals already
identified.
Figure 1.5 Control compartment
a. Gas vent from busbar compartment
b. Gas vent from disconnector compartments
c. Gas vent from circuit breaker and earthing switch
compartment
d. Internal arc gas directional duct (optional)

General Instructions
Description and main characteristics
10 cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
Driving mechanism area
In addition to a mimic diagram customised for each type of
cubicle, this has the driving elements in its middle section:
disconnector/earthing switch and circuit breaker driving
mechanisms, circuit breaker opening/closing pushbuttons,
status indicators, groove for access of the spring loading
lever, etc.
Figure 1.6 General manual operation panel detail
1.3.1 Levers for manual operation
Figure 1.7 Lever for manual loading of the circuit breaker
springs in cpg.1-v cubicle
Figure 1.8 Manual operation lever of the feeder disconnectors
Figure 1.9 Manual driving lever of the earthing switch
Figure 1.10 Manual operation lever of the cpg.1-f cubicle
1. Cable compartment cover interlocking
2. Driving shaft access interlocking
3. Circuit breaker operation and indication area
4. Voltage presence - absence detector
5. Feeder disconnector operation and indication area
6. Earthing switch operation and indication area

Description and main characteristics
General instructions
11
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
1.3.2 Main manual operation panel
cpg.1-v1
Figure 1.11 Manual operation general panel and mimic
diagram for cpg.1-v1
cpg.1-v2
Figure 1.12 Manual operation general panel and diagram for
cpg.1-v2
a. Disconnector operation and indication area
b. Voltage presence-absence indicator
c. Driving shaft access handle
d. Circuit breaker operation and indication area
e. Earthing switch operation and indication area
f. Cable compartment cover interlocking
cpg.1-s1
Figure 1.13 Manual operation general panel and mimic
diagram for cpg.1-s1
cpg.1-s2
Figure 1.14 Manual operation general panel and mimic
diagram for cpg.1-s2
a. Disconnector operation and indication area
b. Voltage presence-absence indicator
c. Driving shaft access handle
d. Earthing switch operation and indication area
e. Cable compartment cover interlocking

General Instructions
Description and main characteristics
12 cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
cpg.1-c
Figure 1.15 Manual operation general panel and mimic
diagram for cpg.1-c
cpg.1-cl
Figure 1.16 Manual operation general panel and mimic
diagram for cpg.1-cl
a. Disconnector operation and indication area
b. Driving shaft access handle
c. Circuit breaker operation and indication area
d. Earthing switch operation and indication area
a. Disconnector operation and indication area
b. Driving shaft access handle
c. Circuit breaker operation and indication area
d. Earthing switch operation and indication area

Description and main characteristics
General instructions
13
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
cpg.1-ct
Figure 1.17 Manual operation general panel and mimic
diagram for cpg.1-ct
cpg.1-f1
Figure 1.18 Manual operation general panel and mimic
diagram for cpg.1-f1
cpg.1-f2
Figure 1.19 Manual operation general panel and mimic
diagram for cpg.1-f2
a. Disconnector operation and indication area
b. Voltage presence-absence indicator
c. Driving shaft access handle
d. Switch - disconnector operation and indication area
e. Earthing switch operation and indication area
f. Cable compartment cover interlocking
g. Blown fuse indicator
h. Switch manual opening handle
Conguration with motorised circuit breaker-
disconnector driving mechanism.
Operation of the earthing switch mechanism
cannot be motorised.
a. Disconnector operation and indication area
b. Driving shaft access handle
c. Circuit breaker operation and indication area
d. Earthing switch operation and indication area

General Instructions
Description and main characteristics
14 cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
1.4 Name plate
Every cubicle incorporates a name plate, indicating some
of the following values:
Figure 1.20 Example of name plate for cpg.1-v2 cubicle
Name plate
Nº Cubicle serial number(*).
Type Ormazabal cubicle system.
Designation Cubicle model.
Standard Regulations applied to the equipment.
UrEquipment rated voltage.
UpLightning impulse withstand voltage.
UdPower frequency withstand voltage.
frEquipment rated frequency.
IrEquipment rated current.
Ik/ IpShort-time withstand current/Short-time withstand peak value.
tkShort-circuit time.
lsc Rated short-circuit breaking capacity.
Pre Gas pressure inside the compartment (MPa).
Pme Minimum operation pressure (MPa).
SF6Weight (g) of insulating fluid.
Year Year of manufacture.
TC Minimum working temperature.
DC% Percentage value of the aperiodic component.
Uop Driving mechanism rated supply voltage for one closing and one opening operation.
(*) In the case of any incidents, note down this number and report it to Ormazabal.

Technical characteristics
General instructions
15
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
2 Technical characteristics
2.1 Electrical characteristics
Characteristics cpg.1-v1/v2 cpg.1-s1/s2 cpg.1-c/cl/ct cpg.1-f
Rated voltage kV 24 / 36
Rated current in continuous operation
In main busbar A 1250 / 1600 / 2000 1250 / 1600
/ 2000
1250 / 1600
/ 2000
Branching A 630 / 1250 / 1600 / 2000 200
Rated frequency Hz 50 / 60
Lightning impulse voltage
Between phases and phase-to-earth kV 125 / 170
145 / 195
Isolating distance kV
Power frequency voltage
Between phases and phase-to-earth kV 50 / 70
60 / 80
Isolating distance kV
Reclosing sequence O-0.3 s-CO-
15 s-CO NO O-0.3 s-CO-
15 s-CO NO
Rated short-time current main circuit kA 25 / 31.5
Rated short-time current earth circuit kA 25 / 31.5 1 / 3
Rated peak current main circuit kA 62.5 / 80
Rated peak current earth circuit kA 62.5 / 80 2.5 / 7.5
Rated short-circuit time s 1 / 3
Short-circuit breaking rated current kA 25 / 31.5 25 / 31.5
Breaking rated current in short-circuit kA 62.5 / 80 62.5 / 80
DC % 45 45
Opening time ms < 45 < 45
Short-circuit breaking time ms < 50 < 50
No-load feeder rated current A 50 50
No-load cable rated current A 31.5 / 50 31.5 / 50
Condenser battery rated current A 400 400
Transfer rated current A 800
Internal fault rated current kA 31.5
Internal fault rated time s 1
Electrical endurance E2/C2 E2/C2 E3 / C2
Auxiliary voltage Vdc 125
Motorised charging time ms < 15 < 15
Mechanical endurance M2 M0 M2 M2

General Instructions
Technical characteristics
16 cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
2.2 Mechanical characteristics
2.2.1 Dimensions and weights
cpg.1-v circuit breaker cubicle
Figure 2.1 Dimensions of cpg.1-v cubicle
Level With single busbar
cpg.1-v1
With double busbar
cpg.1-v2
a600 600
h2500* 2500*
f1900* 1900*
Anchors [1]
b550 550
c500 500
d590 590
Weight [kg]
Total 1100** 1400**
* For control compartment 480 mm high and 561 mm deep. For other
control compartment measurements, check with Ormazabal.
** Cubicles with IAC classification AFLR have an additional 30 kg weight.
[1] See plan of anchoring points in section 6.5.
cpg.1-s disconnector cubicle
Figure 2.2 Dimensions of cpg.1-s cubicle
Level With single busbar
cpg.1-s1
With double busbar
cpg.1-s2
a600 600
h2500* 2500*
f1900* 1900*
Anchors [2]
b550 550
c500 500
d590 590
Weight [kg]
Total 1000** 1200**
* For control compartment 480 mm high and 561 mm deep. For other
control compartment measurements, check with Ormazabal.
** Cubicles with IAC classification AFLR have an additional 30 kg weight.
[2] See plan of anchoring points in section 6.5.

Technical characteristics
General instructions
17
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
cpg.1-c busbar coupling cubicle
Figure 2.3 Dimensions of cpg.1-c cubicle
Level With single busbar
cpg.1-c
With double busbar
cpg.1-cl cpg.1-ct
a600 1200 600
h2500* 2500* 2500*
f1900* 1900* 1900*
Anchors [3]
b550 550
c500 500
d590 590
Weight [kg]
Total 1500* 3000* 1500*
* For control compartment 480 mm high and 561 mm deep. For other
control compartment measurements, check with Ormazabal.
** Cubicles with IAC classification AFLR have an additional 30 kg weight.
[3] See plan of anchoring points in section 6.5.
cpg.1-f fuse protection cubicle
Figure 2.4 Dimensions of cpg.1-f cubicle
Level With single busbar
cpg.1-f1
With double busbar
cpg.1-f2
a600 600
h2500* 2500*
f1900* 1900*
Anchors [4]
b550 550
c500 500
d590 590
Weight [kg]
Total 1000** 1300**
* For control compartment 480 mm high and 561 mm deep. For other
control compartment measurements, check with Ormazabal.
** Cubicles with IAC classification AFLR have an additional 30 kg weight.
[4] See plan of anchoring points in section 6.5.
2.2.2 Protection grade
All power circuit elements are installed inside a stainless
steel gas tank, providing IP65 degree of protection.
The maximum degree of protection for the cubicle
assembly, in all designations, is IP42.

General Instructions
Service conditions
18 cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
3 Service conditions
Installation Indoor
Maximum ambient temperature + 40 ºC
Minimum ambient temperature – 5 ºC
Maximum mean ambient temperature, measured over a 24-hour period + 35 ºC
Maximum mean relative humidity, measured over a 24-hour period < 95%
Maximum mean relative humidity, measured over a 1-month period < 90%
Maximum height above sea level 1000 m
Solar radiation Negligible
Ambient air pollution (dust, smoke, corrosive and/or flammable gases, vapours or
salt) Insignificant
Vibrations caused by causes external to the switchgear or by seismic movements Negligible
The specications refer to the section "Normal
service conditions for indoor cubicles" in the
IEC 62271-1 standard 'Common specications
for high voltage cubicle standards”.
For special service conditions: ambient
temperature above + 40 ºC, installation and/
or transport over 1000 m above sea level,
signicant pollution level, or others dierent to
those described, check with Ormazabal.

Handling and transport
General instructions
19
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
4 Handling and transport
4.1 Transport conditions
During transport, the switchgear must be perfectly seated
and fixed so that it cannot move about and possibly
damage the equipment. Always in upright position, directly
on the ground or on a pallet, depending on the type of
handling involved. Check that the switchgear is perfectly
balanced at all times.
4.2 Lifting means
The cubicles must always be kept upright, directly on the
ground or on a pallet depending on the type of handling
involved.
The cpg.1 cubicles are fitted with four eyebolt-type
suspension points which can be used for handling the
cubicles with a crane; to do this, four slings or cloth straps
are used capable of carrying at least 2500 kg.
Check that the cubicle is perfectly balanced at
all times.
Once the cubicle has been sited as close as possible to
its final installation position, remove all four suspension
points from the cubicle.
Figure 4.1 Lifting a cpg.1 cubicle using slings
If a forklift truck is available, this should have a fork at least
2 m long and be capable of carrying at least 2500 kg.
Figure 4.2 Lifting a cpg.1 cubicle by forklift truck
The cubicle should always be loaded onto the
forklift truck from the front, as indicated in
gure 4.2.

General Instructions
Handling and transport
20 cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 23/06/2016
To put the cubicles in their final position, elevating caster
wheels can be used; please check with Ormazabal.
Figure 4.3 Wheel anchors in the cubicle
Figure 4.4 Detail of the positioned wheel
This manual suits for next models
8
Table of contents
Other Velatia Industrial Electrical manuals
Popular Industrial Electrical manuals by other brands

IFM Electronic
IFM Electronic Efector250 E3D304 installation instructions

Murata
Murata GJM0335C1E300GB01 Series Reference sheet

Grizzly
Grizzly G1095 owner's manual

nvent
nvent TR-400A instruction sheet

Murata
Murata GRM0335C1ER80BA01 Series Reference sheet

Murata
Murata GJM0335C1H1R0WB01 Series Reference sheet