manuals.online logo
Brands
  1. Home
  2. •
  3. Brands
  4. •
  5. AOBOET
  6. •
  7. Storage
  8. •
  9. AOBOET Uhome-LFP 2400 User manual

AOBOET Uhome-LFP 2400 User manual

Popular Storage manuals by other brands

IBM 40/80 GB HH DLTVS user guide

IBM

IBM 40/80 GB HH DLTVS user guide

Synology DiskStation DS716+II Quick installation guide

Synology

Synology DiskStation DS716+II Quick installation guide

Vantec NexStar-HX4 user manual

Vantec

Vantec NexStar-HX4 user manual

LaCie Christofle Galet datasheet

LaCie

LaCie Christofle Galet datasheet

LaCie Rugged Thunderbolt user manual

LaCie

LaCie Rugged Thunderbolt user manual

OCZ IBIS datasheet

OCZ

OCZ IBIS datasheet

Transcend JetFlash 110 Brochure & specs

Transcend

Transcend JetFlash 110 Brochure & specs

QNAP TS 32PXU Series user guide

QNAP

QNAP TS 32PXU Series user guide

LaCie RUGGED RAID user manual

LaCie

LaCie RUGGED RAID user manual

Freecom CLS DOCK Quick install guide

Freecom

Freecom CLS DOCK Quick install guide

PNY Attache P-FD64MBATT3 install guide

PNY

PNY Attache P-FD64MBATT3 install guide

OWC Mercury Elite Pro Dual mini Assembly manual

OWC

OWC Mercury Elite Pro Dual mini Assembly manual

OLT 6x6 Maximizer Assembly manual

OLT

OLT 6x6 Maximizer Assembly manual

Transcend JetFlash 160 Specifications

Transcend

Transcend JetFlash 160 Specifications

Thunderbolt 600 user manual

Thunderbolt

Thunderbolt 600 user manual

Intel RAID High Availability user guide

Intel

Intel RAID High Availability user guide

LaCie 12big Thunderbolt 3 Quick install guide

LaCie

LaCie 12big Thunderbolt 3 Quick install guide

Spectra Logic T-Series Spectra T50e quick start guide

Spectra Logic

Spectra Logic T-Series Spectra T50e quick start guide

manuals.online logo
manuals.online logoBrands
  • About & Mission
  • Contact us
  • Privacy Policy
  • Terms and Conditions

Copyright 2025 Manuals.Online. All Rights Reserved.

Quick Installation Guide
Model:Uhome-LFP 2400
1.Wall mounting
1.Determine bracket mounting place to be
fixed using this Positioning cardboard.
2.Drill holes in the wall for the M8 expansion
screw anchors, which depth should be at least
50 mm. Tighten the screws to a torque around
2.5 N·m.
3.Fasten the battery to bracket fasten hole
with M6 screws with 2.0N·m roughly.
4.Meanwhile, two or four batteries could be
installed by theses brackets.
Note:
If more than 4 batteries installed, a cabinet recommended to be selected for
the battery’s stable.
2.Ground installation
1.Fix the braced feet to battery’s mounting
holes one by one.
2.If more power and energy needed, two or
more (less than 4) batteries could be installed
in one stack.
3.But if the number of batteries at the range
of 4~8, a cabinet recommended to be selected.
3.Address select of Master and Slave battery(ies)
connection
Step 1 :Check dips SW1,4 and 5 are set as the diagram above.
Step 2 :Set Dips SW2 and SW3 as the settings below.
Step 3 : Check the cable connections are as Section 4.
AOBOET
Step 1 Step 2
6.Commissioning
6.1Commissioning battery
6.2Shutting down battery
If there is only one battery installed, use the following steps to put it in operation:
1.Press and hold the panel button on the left side of the unit for about 5s, after the indicator
lights on, release the panel button.
2.Make sure that the Run light is on. If it stays off, do not use the battery and contact AOBO
or your distributor.
3.Turn the inverter on, and wait for the start-up sequence to complete fully.
When there are two or more batteries connected with parallel mode, after the charging cable
and the data cable has been connected correctly, follow these steps to put them in operation:
1.Check battery voltage level is above 48V
a)If battery voltage is under 45V contact your distributor or AOBO after service hot line for
help.
2.Press and HOLD the panel button for about 5s, then the indicator lights will turn on.
3.Release the panel button.
a)For all batteries, make sure that the Run light is on.
b)Make sure the maximum voltage different between batteries less than 2.0V.
c)If not, the installer should balance the battery voltage and then parallel connect batteries
together.
d)Set the DIP switches like part 5-1 Setting for communication interface.
4.Turn the inverter on, and wait for the start-up sequence to complete fully.
For wall mounting, the battery Series connection number should be less than 4, if more
batteries installed, a cabinet was recommended.
Note:
Before two or more batteries installed in parallel, please check the voltage of
each battery and make sure the voltage different less than 2.0V.
Note:
The battery default protocol is CAN bus, if an inverter communication mode is
RS485 or other protocol, please contact AOBO before installation.
4.2 Wall mounting
5. Configuration
5.1Settings for CAN /485 bus pins
SW1,SW4 and SW5 should be set correctly for proper communication between inverter and
battery.
SW1: For CAN communication, please set pin1 and pin2 at on, pin3 and pin4 at off
For 485 communication, please set pin1 and pin2 at off, pin3 and pin4 at on
SW4,SW5: Please use them to set the port of RJ45
Low signal (CAN) / B (485)--SW4
High signal (CAN) /A (485)--SW5
Example (above picture ):CAN communication, port 5 of RJ45 is low signal, port 4 of RJ45 is
High signal.
1.Press and hole the Panel Button about 5s, after a disconnect voice of relay come can release it.
2.Make sure that every light on the battery is off.
For parallel installation, please pay attention on Cable connection, and the DIP8 of SW2 no
need to be changed and stayed on Initial Factory state.
4.Cable connection for Parallel connection
4.1 Ground installation
Grounding Cables