Install Instructions | Lattice Torus
Lattice Install Instructions | Metric | R1-0 | Autex Industries Ltd © December 2020
Page 2 of 3
57”
18”
18”
90°
19 1/2” 19 1/2”
Fig. 1
Fig. 2
Fig. 3
Fig. 8Fig. 7
Fig. 4
Fig. 6Fig. 5
When the Lattice is hung, use the adjuster to make minor
adjustments to set correct, level height*. Once set, trim
excess wire, leaving 1.5” for seismic compliance.
2 x Lattice Baffles
8 x 1m Galvanised Cables
8 x Ceiling Mounts
8 x Cable Adjusters
Start clipping the fins into the top ring as shown in
Fig. 1, 2 and 3 until complete.
Once all fins are clipped to the top ring, gently and
evenly press the bottom ring into position. Ensure
all joints are snug and carefully roll over so the
larger ring is on the top. Check again for any loose
connections, make sure the hooks on the fins have
clipped over the top ring.
Thread the ceiling mount caps (Fig. 6) onto the
cables (Fig. 7).
Thread the cable adjuster onto cables (Fig. 8).
Determine where you want the Lattice to hang (Fig. 4).
Mark the ceiling fixing points as per dotted lines.
Lift the Lattice up to meet the cables, thread the wires
through the holes in the top ring and insert into the cable
adjuster.
Screw assembled cables into the fixed ceiling mounts.
Separate the ceiling mounts into their individual parts -
ceiling mounts (Fig. 5) and ceiling mount caps (Fig. 6).
Screw ceiling mounts (Fig. 5) to the ceiling substrate at
the marked centres (Step 1) with a fixing appropriate for
the substrate.
*Speak to your Autex Account Manager for more information on setting the best suspension height for your application.
2.
1.
1.
2.
3.
4.
5.
PACK CONTENTS INSTALLATION