Changing Components - Page 12
When changing components ensure that electrical and
gas supplies are isolated.
Before changing any components please read the
Important Information section on page 3
THERMOCOUPLE
1) Remove the outer case front panel by pulling forwards
at the top and lifting upwards.
2) Turn off the gas supply at the service tap or at the
ON/OFF button on the gas valve.
3) Release the thermocouple nut at the side of the gas
valve from the interrupter adaptor (Fig. 12).
4) Release the thermocouple nut at the pilot bracket.
5) Re-assemble in reverse order of dismantling.
THERMOCOUPLE RE-ROUTE DEVICE
1) Remove the burner and controls assembly as
described in steps 1 to 6 - Servicing the Unit.
2) Remove valve heat shield.
3) Release thermocouple nut and interrupter device from
the valve (Fig 12).
4) Disconnect the re-route nut.
5) Remove terminal cover and re-route device.
6) Re-assemble in reverse order of dismantling.
INJECTOR
1) Remove the burner and controls assembly.
2) Remove the burner securing screws and remove the
burner (Fig 11).
3) Unscrew the injector from the feed pipe.
4) Re-assemble in reverse order of dismantling.
BURNER
1) Remove the burner and controls assembly.
2) Remove the burner securing screws and remove the
burner (Fig 11).
3) Re-assemble in reverse order.
T.T.B. ASSEMBLY (Fig 12)
1) Disconnect the two terminals from the thermocouple
interrupter on the valve.
2) Remove the leads from their clips on the boiler.
3) Remove the four screws securing the top inspection
panel.
4) Slacken the R.H. baffle securing screw. There is no
baffle on 80 & 60 models.
5) Lift the T.T.B. bracket upwards to disengage it from the
screw.
6) Withdraw the complete assembly out through the
combustion box.
7) Reassemble in reverse order of dismantling.
BOILER THERMOSTAT
1) Remove the outer case front panel by pulling forwards
at the top and lifting upwards.
2) Remove the outer case top panel by pulling upwards.
3) Remove the two facia retaining screws (Fig 8) taking
care not to lose the two spacer washers and allow the
facia to swing forwards on its hinges.
4) Release the thermostat capillary from behind its
retaining clip and remove the thermostat phial from the
boiler (Fig 8).
5) Remove the screws securing the thermostat cover to
the facia.
6) Disconnect the three spade electrical terminals from the
thermostat.
7) Pull off the thermostat knob and remove the locknut
securing the thermostat to the facia panel.
8) Re-assemble in reverse order of dismantling ensuring
that the thermostat phial is replaced into the thermostat
pocket.
GAS VALVE (Fig 12)
1) Remove the burner and controls assembly as
described in steps 1 to 6 - Servicing the Unit.
2) Disconnect the thermocouple nuts at the valve and at
the pilot bracket.
3) Disconnect interrupter adaptor.
4) Disconnect the pilot feed pipe at the valve and at the
pilot bracket ensuring that the pilot injector is not
misplaced.
5) Disconnect the electrode lead and remove the piezo
unit.
6) Remove the screw securing the electrical terminal
cover to the gas valve. Disconnect the electrical
connections.
7) Remove the valve complete with the heat shield and
inlet pipe by disconnecting the flanged burner feed pipe
(Fig 7).
8) Disconnect the flanged inlet pipe. Retain the O rings for
re-assembly but replace if damaged.
9) Remove the heat shield by undoing the retaining
screws.
10) Release the thermocouple re-route nut and remove the
re-route.
11) Individual sub components of the valve may be
replaced as outlined by Honeywell instructions.
12) Re-assemble in reverse order of dismantling.
INSULATION IN COMBUSTION BOX
1) Remove the burner and controls assembly as
described in steps 1 to 6 - Servicing the Unit.
2) Release the 2 screws securing the front insulation
assembly and remove the assembly (Fig 9).
3) Remove the two screws and air guides securing the
two side insulation panels (Fig 13) and carefully remove
diagonally through the door opening.
4) Remove the two screws and washers securing the back
panel insulation (Fig 13).
5) Remove the ceramic insulation pad from the front
insulation assembly by bending the securing tabs.
6) 60, 50, 40 OF only - Remove the two sloping panels of
insulation adjacent to the heat exchanger by removing
four screws and washers. Ease out the bottom edge of
the insulation panel and slide down (Fig 13).
7) Replace insulation as necessary and bend down
securing tabs where applicable.
8) Re-assemble in reverse order of dismantling taking
care not to damage the new insulation.
PIEZO UNIT (Fig 12)
1) Remove the burner and controls assembly as
described in steps 1 to 6 - Servicing the Unit.
2) Disconnect the electrode lead at the piezo unit.
3) Remove the nut securing the piezo unit to the heat
shield and remove the piezo unit.
4) Re-assemble in reverse order of dismantling.
SPARK ELECTRODE (Fig 12)
1) Remove the burner and controls assembly as
described in steps 1 to 6 - Servicing the Unit.
2) Disconnect the electrode lead at the electrode.
3) Remove the nut securing the electrode and remove the
electrode.
4) Re-assemble in reverse order of dismantling.