BFT D6000 User manual

O&M Manual
Revision 1.0
Maximum span - 5.0m gate leaf and 300kg weight.
Automatic Swing gates
C/w BFT Giuno A50 Rams
Made in
Maximum span - 2.0m gate leaf and 800kg weight

Index
1. Inductions and warnings Page 03
2. Delivery, Movement and transport Page 04
3. Lifting plan Page 05
4. Layout Drawings Page 06
5. Installation Page 07 - 08
6. Commissioning Certificate Page 09
7. BFT Giuno Rams Manual release Page 10 - 15
8. BFT Thalia P Control panel Page 16 - 24
9. Maintenance Page 25
10. Technical data Page 26

/ /20
!
Important Safety Notice
Automatic gates are designed to Control the flow of vehicular
traffic only. It can be dangerous to allow the passage of
pedestrians and any other self-powered animal or device to utilise
this method of access without appropriate warnings and or
signage.
It may be necessary for the end user of this product to provide an
alternative, safe method of access to cater for the previously
mentioned categories.
The end user should fit all necessary signage and warning
notices to either side of the gate, which should be visible and
clear from all directions of approach.
The product that was shipped to you was designed with a control
program to protect all categories from harm or affect this however
is only a safety precaution and should not be modified or
tampered with by any unauthorised person not sanctioned by the
manufacturer.
Please sign and date below to say that you have read and
understood this notice before ANY installation work:
The “Warnings” leaflet and “Instruction booklet” supplied with this
product should be read carefully as they provide important information
about safety, installation, use and maintenance.
Scrap packing materials (plastic, cardboard, polystyrene etc) according
to the provisions set out by current standards. Keep nylon or polystyrene
bags out of children's reach.
Keep the instructions together with the technical brochure for future
reference.
This product was exclusively designed and manufactured for the use
specified in the present documentation.Any other use not specified in
this documentation could damage the product and be dangerous.
The Company declines all responsibility for any consequences resulting
from improper use of the product, or use which is different from that
expected and specified in the present documentation.
Do not install the product in explosive atmosphere.
The construction components of this product must comply with the
following European Directives: 89/336/CEE, 73/23/EEC, 98/37/EEC
and subsequent amendments.As for all non-EEC countries, the abovementioned
standards as well as the current national standards should
be respected in order to achieve a good safety level.
Information on using
this manual
?Read all information thoroughly
?Pay attention to all safety advice
?Be aware of the symbols (shown above right and
above left) as they have different meanings. One is an
information symbol, the other a warning.
?There are many artists impressions of the product in
this manual you should refer to the images as a guide
only. Professional CAD drawings should be used as
a reference drawing and nothing else. As before every
effort has been made to be 100% accurate in this
manual but we cannot make any guarantees.
?As we constantly innovate our products we may
change the quoted spec and any other details that
have been documented in this manual so you should
always refer to the supplier to see if the manual that
was shipped with your product is the latest edition.
?As with all electrical installations you should use a
qualified electrician and obey all of the latest laws and
regulations.
?Be sure to fill out and complete ALL paperwork where
instructed as this manual is the equipments log book
and maintenance manual.
The Company declines all responsibility for any consequences resulting
from failure to observe Good Technical Practice when constructing closing
structures (door, gates etc.), as well as from any deformation which might
occur during use.
The installation must comply with the provisions set out by the following
European Directives: 89/336/CEE, 73/23/EEC, 98/37/EEC and
subsequent amendments.
Disconnect the electrical power supply before carrying out any work on
the installation. Also disconnect any buffer batteries, if fitted.
Fit an omnipolar or magnetothermal switch on the mains power supply,
having a contact opening distance equal to or greater than 3mm.
Check that a differential switch with a 0.03A threshold is fitted just before
the power supply mains.
Check that earthing is carried out correctly: connect all metal parts for
closure (doors, gates etc.) and all system components provided with an
earth terminal.
Fit all the safety devices (photocells, electric edges etc.) which are
needed to protect the area from any danger caused by squashing,
conveying and shearing, according to and in compliance with the
applicable directives and technical standards.
This equipment is part of a large range of traffic flow products. They are designed to be easy to install, as
all settings and internal wiring have been completed in our factory. Any of the instructions in this manual
should only be carried out by a qualified service engineer or a competent person.
The Gates are ready to bolt down, connect to a single phase power supply and have any pre-cut loops
wired into them (Please note that loop detectors are sold separately). The steps must be completed before
the power is turned on to prevent accidents.
The following information is a guide only, and whilst we have made every effort to be accurate and correct
there may be printing errors which we cannot be held responsible for.
With a correct installation you can expect to enjoy many years of reliable service from this product, we do
however recommend that the product has a bi-annual service carried out by a qualified engineer. Please
contact our service department to obtain a quote. As we manufacture the products we are best suited to
care for your equipment.
Introduction and Warnings
Page 3

Delivery,Movement&Transportation
This article describes how your equipment will be delivered to you, specifications on the transportation
used and advice including health & safety on movement of the equipment.
The manufacturer will use a qualified transport company to deliver the product conforming to the
necessary regulations as detailed below:
?All drivers are qualified
?All drivers are tested once yearly ( If applicable )
?All drivers carry risk assessments and method statements (available on request)
?They are controlled under law to conform as there are no trade regulation standards to comply with
Health and safety Considerations:
Moving Goods Safely (MGS) is a national project involving both the Health and Safety Executive (HSE) and
LocalAuthorities (LA) working in partnership. The project aims to reduce injuries and ill-health arising from
the movement of goods from supplier through haulier to the recipient and end user including any home
deliveries. The project will focus upon the delivery and collection of goods and the hazards this generates. It
covers the main areas that cause the majority of injuries and ill-health to workers, including:
?Workplace transport;
?Slips & trips, and;
?Musculoskeletal disorders (MSD).
The movement of goods presents us, as health and safety regulators, with the challenge of dealing with a
huge variety of issues. The commercial organisations involved within the movement of goods are diverse
including haulier, third party logistics providers, pallet networks, retailers etc, with some very large companies,
thousands of small businesses and the self-employed. The movement of goods is more than just trucks on
the road with a large proportion of accidents happening at the delivery/collection sites that are often not
directly under the control of the company making the delivery or collection. Communication and cooperation
problems can arise due to the many organizations involved in the movement of the goods, and this can also
lead to difficulties in effectively managing health and safety.
(Source H&S Executive UK 2008)
The gates should ALWAYS! be moved with care and attention. The products are very heavy individually
as well as a whole. You should not attempt to move this or any other products by unapproved handling
methods.
Page 4

Lifting and Handling
WARNING
Always take safety precautions when lifting and handling heavy objects, in
accordance with Manual Handling Operation Regulations 1992.
Always wear correct safety equipment in the vicinity of equipment being off loaded.
The gate is to be steadied by means of ropes attached to each end of the gate;
preventing it from swinging whilst being manoeuvred. It is important to use the
correct nylon slings with a SWL of 2 tonne for each sling.
HANDLING
Due to the size and weight of most D6000 swing gates, the services of a
mobile crane/ hiab are essential for safe off-loading and positioning. The
Posts are to be lifted off first and bolted down ready for the leafs to be
hung. Once the posts are bolted down and secure the leafs can be hung
using the crane. The gate leafs should be supported centrally, ensuring
that the frame/ leaf are balanced and unlikely to cause excessive
movement in the air that may cause the gate damage.
Fig.1 Lifting posts onto foundations. Fig.2 Lifting Gate leafs onto the posts
Page 5

General Layout
Span 2.0m
Frame
Height 1.0m
300.00
600.00 Inbetween Foundation Dim
700.
Std Tube
Control panel to be
located
within 5m of the
gates, Mains
The top 300mm of concrete is to
Internal
C
D
E
F

Installation
All foundations should be installed as per drawing supplied as base size’s will vary
depending on the size of the gates. (Contact your supplier if you have not been issued one.)
All foundations should be installed 10 x days prior to the gates being installed.
If details of the base have not been specified, we recommend a concrete mix to
BS EN 206-1:2000 “Concrete specification, Performance, Production and Conformity”
to type C32/40, which
:
is equally suitable for external and internal environments.
Foundations
The foundation must be positioned accurately and installed to the correct levels to
ensure successful installation.
Careful consideration should be made when deciding the location of the gate to
avoid overhead obstructions such as power cables, telephone wires building
canopies, trees and other types of likely obstructions and hazards, which will not
Ducting
Ducting carrying cables for power and control should enter the gate support frame
from underground. Two ducts are normally required, one for the power supply,
the other for the control. Where the power supply and control cables are to come
from a common place; a single duct can be used.
These ducts must be sited accurately in the base as shown on the contract
drawing. The use of cable access pits is recommended where there may be a
number of ducts used entering the gate or long cable runs are necessary. We also
recommend the ducts used be of 100mm diameter PVC. Alternative types and sizes
may be acceptable, subject to discussions with your equipment supplier.
Slow bends should always be used wherever possible, and the inclusion of draw
ropes throughout the ducting system, will ensure that the cables are easily installed.

Installation Cont.
CABLE REQUIREMENTS
As each installation is likely to have different forms of control, each contract will be allocated
its own circuit diagram but the following notes should always apply.
Cables when laid into the ducting should be left with 3m long tails. Any internal cable must
be completely installed to the final location of the equipment to be used and be left with a
suitable length of tail. All cable glands used must be suitable for the type of cable used.
IMPORTANT NOTE
It is essential to route the ducting with care, to ensure that it does not interfere with
the floor anchor equipment fixings.
It is important that this electrical work only be undertaken by competent electrical
Staff and that all electrical work is carried out in accordance work IEE Regulations –
current edition.
All cables when installed must be tested in accordance with the current edition of
The I.E.E. Regulations.
POWER CABLES
A dedicated 230V, 50Hz, 1Ph power supply, including a neutral connection for each Pair of
swing gates is required from an external source and run back to a local, suitably rated
isolator and/or to the main distributor board and protected by a 16 amp M.C.B. The
isolation and protection of the equipment must by others.
A 3-core PVC /SWA /PVC type cables to BS 6346: 1997 should be provided. The conductor
size is to be calculated by the installer as per the above specification. Typical current
consumption of the gate motors is 6 Amps.
All cables should be fed by underground ducting from: -
i. Main electrical supply point
ii. Various control devices (i.e. push buttons, induction loops, card readers etc…)
Gland off on the plates provided in the main control cabinet, the cable tails being long
enough to route to the terminal rail.
All cabling can then be terminated in accordance with the relevant circuit diagram. See page
13 for connection details.
The system is now ready for testing, All testing must be carried out by a fully trained
engineer and should be commissioned off to the end user and the commissioning
certificate should be filled in by the engineer.
Page 8

We certify that the system covered by this certificate has been commissioned satisfactorily.
Site Name
Site Reference
Installation Commenced / /20
Completion
Engineers Installing
Commissioning
Equipment Fitted
Handover Date
Part 2. Existing Installation Items not covered under warranty/ This certificate:
Installers Name
On Behalf of
Address
Signature
Date of Signing
Position
Part 3. Certificate Signing off Section
Client Name
On Behalf of
Site Address
Signature
Date of Signing
Position
Commissioning Certificate
Page 9

BFTGiunoA50Rams
TECHNICAL SPECIFICATIONS
Installing the GIUNO ULTRA BFT A50
This is a powerful swing gate operator, however is easy to insall and can
become operational within no time at all.
Power Supply - 24v
Max power output -90w
Gate leaf length - 2m/5m
Max leaf - 800kg/300kg
Control Panel - Thalia P
Cycle Time - 20 secs
Impact reaction - d-track
Ambiant temperature range - -20 degrees to 60 degrees
Impact reaction - electronic clutch (with control panel)
Manual operation - release key
BLOCK APPLICATION LIMITS
Locking type - Hydraulic
Actual travel time - 20 secs
Leaf Max m - 5-2
Leaf Max kg - 300/800
Travel mm usable - 390
Travel mm total - 410
WARNING WITH LEAVES OVER 3 METERS LONG, THE SOLENOID
LOCK MUST BE USED AND LOCKING DEVICES MUST BE OPENED
(Fig.M Ref.2)
TUBE ARRANGEMENT Fig.A
PILLAR FASTENINGS INSTALLATION DISTANCES Fig.B
INSTALLATION DIAGRAM Fig.C
P rear bracket fastening to pillar
F front fork fastening leaf
A-B distances for determining bracket “P” fastening point
C value of fastening centre-centre distance see fig O
D gate leaf
X distance from gate axis to corner of pillar
Z value always greater than 5mm (b-x)
Kg max weight of leaf
A leaf opening angle
MAIN PARTS OF AUTOMATED SYSTEM
M) 24v permanent magnet motor
P) Lobe pump
D) Control valve assembly
C) Cylinder with piston
F) Limit switch sensors
Components provided: fittings that attach to pillar and gate - release key -
instruction manual
ADJUSTING THE LIMIT SWITCHES
Position the slow down sensors towards the centre of the motor, near the
limit board, position the limit switch sensors at the motor ends.
Enter the limit switch adjustment menu and bring the door to the desired
position. To postion the door you can release the motor and position it
manually or operate buttons + and - (+ opens, - closes). Once the door is in
the desired position, adjust the limit switch sensor: starting from the motor
end, move the sensor towards the centre of the motor unit the limit switch
board LED lights up, when the limit switch is working , the relative board
LED is on, when it is not, the LED is off. Adjust both the opening and
closing limit switches. After adjusting the limit switch position, adjust the
position of the slow down start.
An Oil chance is recommended every 5 years.
1) GENERAL OUTLINE
The GIUNO ULTRA BFT A50 marries cutting edge engineering with
power and function to create the ideal residential swing gate solution.
Advanced track technology analyses real-time torque data to provide the
optimal amount of force in order to create a smooth closing/opening
action without causing excessive wear.
The ULTRA BFT A50 hydraulic gate opener is extremely versatile and is
suited to all kinds iof settings. Each operator is cable of swing a gate leaf
800kg 2 metres in length, 400kg for 5m lengths. It has a built in obstacle
through the exclusive D track torque management system.
2) GENERAL SAFETY
WARNING! An incorrect installation or improper use of the product
can cause damage to persons, animals or things.
• The “
Warnings
” leaflet and “
Instruction booklet
” supplied with this
product should be read carefully as they provide important information
about safety, installation, use and maintenance.
• Scrap packing materials (plastic, cardboard, polystyrene etc) according
to the provisions set out by current standards. Keep nylon or polystyrene
bags out of children’s reach.
• Keep the instructions together with the technical brochure for future
reference.
• This product was exclusively designed and manufactured for the use
specified in the present documentation. Any other use not specified in
this documentation could damage the product and be dangerous.
• The Company declines all responsibility for any consequences resulting
from improper use of the product, or use which is different from that
expected and specified in the present documentation.
• Do not install the product in explosive atmosphere.
• The construction components of this product must comply with the
following European Directives: 73/23/EEC, 98/37 EEC and subsequent
amendments. As for all non-EEC countries, the above-mentioned
standards as well as the current national standards should be respected
in order to achieve a good safety level.
• The Company declines all responsibility for any consequences resulting
from failure to observe Good Technical Practice when constructing
closing structures (door, gates etc.), as well as from any deformation
which might occur during use.
• The installation must comply with the provisions set out by the following
European Directives: 73/23/EEC, 98/37 EEC and subsequent
amendments.
• Disconnect the electrical power supply before carrying out any work on
the installation. Also disconnect any buffer batteries, if fitted.
• Fit an omnipolar or magnetothermal switch on the mains power supply,
having a contact opening distance equal to or greater than 3mm.
• Check that a differential switch with a 0.03A threshold is fitted just before
the power supply mains.
• Check that earthing is carried out correctly: connect all metal parts for
closure (doors, gates etc.) and all system components provided with an
earth terminal.
• Fit all the safety devices (photocells, electric edges etc.) which are
needed to protect the area from any danger caused by squashing,
conveying and shearing.
• Position at least one luminous signal indication device (blinker) where
it can be easily seen, and fix a Warning sign to the structure.
• The Company declines all responsibility with respect to the automation
safety and correct operation when other manufacturers’ components
are used.
• Only use original parts for any maintenance or repair operation.
• Do not modify the automation components, unless explicitly authorised
by the company.
• Instruct the product user about the control systems provided.
Lifting Power
·
30 Bar maximum pressure
·
3,000 newton operating force
·
2,600 operating force
Hard Wearing & Flexible
·
Suitable for intensive everyday use
·
20 second cycle time
·
Opening angle of 110 degrees.
Page 10

BFTGiunoA50Rams

BFTGIUNOA50RAMS
Page 12

BFTGIUNOA50RAMS

BFTGIUNOA50RAMS

BFTGIUNOA50RAMS

BFTGIUNOA50RAMSBFTGIUNOA50RAMSBFTGIUNOA50RAMS

BFTGIUNOA50RAMSBFTGIUNOA50RAMSBFTGIUNOA50RAMS

BFTGIUNOA50RAMSBFTGIUNOA50RAMSBFTGIUNOA50RAMS

BFTGIUNOA50RAMSBFTGIUNOA50RAMSBFTGIUNOA50RAMS

BFTGIUNOA50RAMSBFTGIUNOA50RAMSBFTGIUNOA50RAMS
Table of contents
Other BFT Fencing & Gate manuals
Popular Fencing & Gate manuals by other brands

BENITO
BENITO Urban Reb VRV480 Anchoring instructions

Casanoov
Casanoov DO 370C160 instruction manual

Carlson Pet Products
Carlson Pet Products 0930 PW Assembly instructions

Orbinox
Orbinox BC Installation, operation & maintenance manual

Fortress Technologies
Fortress Technologies Osbourn IBL-H operating instructions

PRAESIDIAD
PRAESIDIAD BETAFENCE Securifor with Bekafix Ultra posts installation manual