5
1) - Temperature: Required temperature settled temp.value (°C)
2) - Waiting time:Waiting time in required settled temperature (min.)
3) - Cooling set:Required cooling settled temp.value (°C)
4) - Pre-heat set: Temperature when machine is on. (°C), but not functioned.
5) - Pressure set:Adjustment of max.pressure required (Bar)
Recommended pressure between 150-200 bars depending on sample. (Max. applicable pressure is 250 Bars)
Entering required values on Digital Panel (see screens step by step)
3 Operation
Remove the mold locking system by turning the mold locking lever in the clockwise direction.
3.1 Placement of Sample and Bakelite Powder
Press the button and lift up the hydraulic cylinder manually and place the sample on the upper surface
of the piston by squeezing the separator. Manually by pressing the button down slightly depending on
the size of the sample.
Fig. 3
Put the bakalite powder in the appropriate amount to the sample size and lock the mold system.
Fig. 4