11
Vertical package air conditionners
WICHTIG: WIEDERBEHEIZUNG DER
OLWANNE
IMPORTANT: CRANKCASE HEATING
IMPORTANT: SURCHAUFFE CARTER D’HUILE
IMPORTANTE: RISCALDARE IL CARTER
DELL’OLIO
IMPORTANTE: RECALENTAMIENTO DE
ACEITE DEL CÁRTER
KOENNEN.
TO ALLOW THE COMPRESSOR(S) STARTING
AU PREMIER DÉMARRAGE OU APRÈS UNE ABSCENCE
TENSION 24 HEURES AVANT D’AUTORISER LE
DÉMARRAGE DU(DES) COMPRESSEUR(S).
AL PRIMO AVVIAMENTO U DOPO UNA INTERRUZIONE
PROLUNGATA DELLA ALIMENTAZIONE ELETTRICA,
LASCIARE LA MACCINA SOTTO TENSIONE PER 24 ORE
PRIMA DI AUTORIZZARE L’AVVIAMENTO DEL(DEI)
COMPRESSORE(I).
ANTES DEL PRIMER ARRANQUE O DESPUÉS DE UNA
AUSENCIA DE CORRIENTE POR UN LARGO PERIODO DE
TIEMPO, CONVIENE QUE LA UNIDAD ESTÉ CONECTADA
UN MÍNIMO DE 24 HORAS.
BEIDER ERSTEN INBETRIEBSETRUNZ ORDER NACH EINER
LANGEN STROMUNTER-BRECHUNG BRINGEN SIE DIE
MASCHINE UNTER SPANNUNG 24 STRUNDERLANG
BEVOR SIE DEN(DIE) KOMPRESSOR(EN) EINSCHALTEN
FOR THE FIRSTSTART OR AFTER ALONG TIME OUT OF
VOLTAGE PUT THE MACHINE ON LIVE 24 HOURS BEFORE
DE COURANT PROLONGÉE, METTRE LA MACHINE SOUS
- Allmodelsof50NZ/NFSeriesare equipped with Scroll compressors
and include a phase control relays.
Check that they rotate in the correct
sense,andifit does not occur,reverse
two wires of the power supply.
- When starting the compressor, check
the undercooling and overheating and thus verify if the refrigerant
charge is appropriate to the operating
conditions. To adjust the refrigerant charge, a
schrader valve is available on the liquid line.
- Verify the absence of any leaks of the
refrigerant.
- Check the unit operation and verify the safety elements.
COMPRESOR SCROLL.
COMPROBAR SENTIDO DE GIRO
COMPRESSEUR SCROLL.
VÉRIFIER LE SENS DE ROTATION
SCROLL COMPRESSOR.
CHECK SENSE OF ROTATION
11. COMMISSIONING
Operational checks
Check the unit operation by verifying the electronic control and the
safety elements.
It is also recommendable to create a report, taking note of the date,
which includes the following information: the nominal voltage, current
absorbed by the compressors, fans and other electrical components,
significant temperatures in the cooling circuit (see table below) and
other aspects considered interesting such as alarms detected by the
electronic control of the unit. The recording of these parameters whilst
the unit is running allows controlling the installation performance and
it is the best possible way to avoid breakdowns since the analysis
of these data makes early detection of anomalies possible or the
provision of the necessary means available to ensure that they do
not take place.
Possible problems at commissioning
All indications given in this brochure must be respected and
complied with to guarantee a correct operation of the units.
Next, several possible operation problems are stated which could
happen if the conditions of the commissioning are not appropriate.
- Airflow lack:veryhighdifferencesbetweeninletand outlet, originated
by a high pressure drop in the ducts, or by other causes that impede
the correct air circulation.
- Air recirculation in the unit, originated by some obstacle in the air
aspiration or outlet.
- Noise problems because of excessive air flow in the grille.
- Water overflowing to the pan problems, originated by an excessive
flow, an incorrect siphon installation or becauseadefectiveunitlevel.
- Refrigerantcircuithumidity problem, because of an incorrectvacuum
realization.
Checks prior to commissioning
- Itisadvisabletomake a complete sketch of the installation including
thelocationoftheunitandallthecomponentsused.This will be very
helpful for maintenance and repairs to the installation.
- Check that the electrical power supply matches the unit voltage and
that its value lies within acceptable limits.
- It must also be verified that the electric installation has been carried
out according to the electric wiring diagram provided with the unit
(consult the chapter on “Checking before commissioning”).
- Once the above verifications have been carried out, the control
circuit is supplied with voltage by the automatic control switch. It is
necessary to leave with voltage the compressor crankcase heater
for 24 hours before starting the compressor.
Cooling MODE Heating MODE
Compressor
Aspirationpressure bar
Compressor
Aspirationpressure bar
Aspirationtemp. (1) ºC Aspirationtemp. (1) ºC
Condens.pressure bar Condens. pressure bar
Condens.temp. (2) ºC Condens.temp. (2) ºC
Air
condenser
Gasinlet temperature ºC
Air
evaporator
Liquidinlet temp. ºC
Liquidoutlet temp.(3) ºC Gas outlettemp. (4) ºC
Airinlet temperature ºC Airinlet temperature ºC
Outdoortemperature ºC Outdoor temperature ºC
Airoutlet temperature ºC Airoutlet temperature ºC
Air
evaporator
Airinlet temperature ºC
Air
condenser
Airinlet temperature ºC
Airoutlet temperature ºC Airoutlet temperature ºC
Liquidinlet temp. ºC Gasinlet temperature ºC
Evap.outlet temp.(4) ºC Liquidoutlet temp. (3) ºC
Undercooling (2) - (3) ºC Undercooling (2) - (3) ºC
Overheating (4) - (1) ºC Overheating (4) - (1) ºC