Page 9
Downflow Coil Installation
IMPORTANT: Installing “A" coils rotated 90
degrees from the front of the furnace in
downow applications can cause water blow
o or coil freeze up. This is due to the
concentration of air on one coil slab or lack of
air on the opposite coil slab. If the airow is
high due to ductwork or other causes, and
there is a chance for water blow o, it is
recommended that a 4-in. minimum
eld-supplied adapter be placed between
the coil and the furnace to allow the air to
distribute evenly to both coil slabs.
Horizontal Coil Installation
The unit can be installed on a work platform,
secured to roof truss in attic, suspended from
hangers on oor joists in crawl space, or installed
on blocks. It is designed to allow airow in either
direction, to mate with horizontal-left or
horizontal-right furnace installations. Ensure
coil cabinet is level side to side and front to back.
It is allowable to add up to 1/2-in. additional
slope over length and depth of coil cabinet in
the direction of drain pan connection.
Horizontal Right Installation
1. Use eld fabricated attachment plates to
secure coil to furnace.
2. Use self-tapping screws to mount attachment
plates to coil casing.
3. Connect furnace snugly against coil casing.
4. Use self-tapping screws to attach furnace.
5. Seal joint between coil casing and furnace to
create an air tight seal using locally approved
materials.
6. Use cork tape to create air seal between the
undersides of the pan extension and front of
the vertical drain pan as shown below.
8. If coil is wider than furnace, use 4-in minimum
transition and self tapping screws to attach
furnace.
7. Install included condensate pan extension
and two corner screws as shown below.
4. Set cased coil on supply duct opening.
5. Place eld fabricated 4-in. minimum adapter
on coil casing. Adapter should be tapered to
t coil/furnace combination when one of
them is larger than the other.
6. Set furnace on adapter.
NOTE: In downow installation with a 4-way
multipoise furnace, break o perforated duct
anges on furnace. See furnace installation
instructions.
Downow Installation with Coil Rotated 90° Horizontal Left Installation
1. Unbend the 4 tabs at the right side of the
casing.
2. Connect furnace snugly against coil casing.
3. Use self-tapping screws to attach furnace.
4. Seal joint between coil casing and furnace to
create air tight seal using locally approved
materials.
5. If coil is wider than furnace, use 4-in. Minimum
transition and self tapping screws to attach
furnace.
Installation
4"